11825 W WAGNER ST 90230

Certificate Information: 11825 W WAGNER ST 90230

Application / Permit
22010-10000-03016
Plan Check / Job No.
B22LA11607
Group
Building
Type
Bldg-New
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Accessory Dwelling Unit
Work Description
eplan New Detached ADU per ordinance. Fully sprinklered throughout, NFPA 13D
Permit Issued
Issued on 2/9/2023
Issuing Office
Current Status
CofO Issued on 6/4/2025
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 6/15/2022 APPLICANT
Assigned to Plan Check Engineer 6/30/2022 FARSHAD ALIMOHAMADI
Corrections Issued 7/5/2022 FARSHAD ALIMOHAMADI
Quality Review Completed 7/6/2022 CHARLES CHANG
Applicant returned to address corrections 7/26/2022 FARSHAD ALIMOHAMADI
Applicant returned to address corrections 8/2/2022 FARSHAD ALIMOHAMADI
Plan Check Approved 8/3/2022 FARSHAD ALIMOHAMADI
Issued 2/9/2023 APPLICANT
CofO in Progress 5/14/2025 BOBBY KEY
No Progress 5/15/2025 DAVID FEILER
CofO in Progress 5/15/2025 DAVID FEILER
Permit Finaled 6/4/2025 RICHARD STEINBACH
CofO Issued 6/4/2025 RICHARD STEINBACH
Permit Finaled 6/4/2025 RICHARD STEINBACH

Permit Application Clearance Information

Address approval Cleared 7/8/2022 DINAH GARIN
Low Impact Development Cleared 7/8/2022 ANTHONY VARGAS
Specific Plan Cleared 7/11/2022 FREDDY GARCIA
Eng Process Fee Ord 176,300 Cleared 7/12/2022 DINAH GARIN
Roof/Waste drainage to street Cleared 7/12/2022 DINAH GARIN
Sewer availability Cleared 7/12/2022 DINAH GARIN

Contact Information

Contractor Lcp General Construction Inc; Lic. No.: 1031198-B       ,

Inspector Information

DAKOTA LOW, (310) 914-3895 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Footing/Foundation/Slab 2/23/2023 Corrections Issued HERBERT GIRON
Footing/Foundation/Slab 4/10/2023 Partial Approval HERBERT GIRON
Deputy Reinf. Concrete 4/11/2023 Conditional Approval MICHAEL PELHAM
Footing/Foundation/Slab 4/17/2023 Approved HERBERT GIRON
Special/Order Compliance 4/17/2023 Partial Inspection JESUS PINEDA
Masonry Wall/Backfill 4/27/2023 Approved JESUS RODRIGUEZ
Floor/Roof Diaphrgm/Shear Wall 5/26/2023 Partial Approval JESUS RODRIGUEZ
Wood Frame 5/26/2023 Partial Approval JESUS RODRIGUEZ
Floor/Roof Diaphrgm/Shear Wall 7/6/2023 Conditional Approval JESUS RODRIGUEZ
Verify Sprinkler Sign Off 7/6/2023 Corrections Issued JESUS RODRIGUEZ
Wood Frame 7/6/2023 Corrections Issued JESUS RODRIGUEZ
Underground Mechanical 8/16/2023 Approved HERBERT GIRON
BUILDING-Rough-Frame 9/8/2023 Corrections Issued BOBBY KEY
Interior/Exterior Lathing 9/8/2023 Partial Approval BOBBY KEY
Rough-Elec/Plmb/HVAC 9/8/2023 Partial Approval BOBBY KEY
Verify Sprinkler Sign Off 9/8/2023 Approved BOBBY KEY
BUILDING-Rough-Frame 9/12/2023 Approved RICHARD STEINBACH
ELECTRICAL-Rough 9/12/2023 Approved RICHARD STEINBACH
Insulation 10/5/2023 Corrections Issued JESUS RODRIGUEZ
Drywall Nailing 10/24/2023 Approved JESUS RODRIGUEZ
HVAC-Rough 10/24/2023 Approved JESUS RODRIGUEZ
Insulation 10/24/2023 Approved JESUS RODRIGUEZ
Interior/Exterior Lathing 10/24/2023 Approved JESUS RODRIGUEZ
PLUMBING-Rough 10/24/2023 Approved JESUS RODRIGUEZ
Shower Pan 11/3/2023 Approved TEMISTOCLES CAAL
ELECTRICAL-Final 8/6/2024 Corrections Issued JESUS RODRIGUEZ
Final 8/6/2024 Corrections Issued JESUS RODRIGUEZ
HVAC-Final 8/6/2024 Corrections Issued JESUS RODRIGUEZ
PLUMBING-Final 8/6/2024 Approved JESUS RODRIGUEZ
SGSOV-Seismic Gas S/O Valve 8/6/2024 SGSOV Approved JESUS RODRIGUEZ
Service/Power Release 8/6/2024 Approved JESUS RODRIGUEZ
Smoke Detectors 8/6/2024 Approved JESUS RODRIGUEZ
ELECTRICAL-Final 9/9/2024 Approved JESUS PINEDA
Final 9/9/2024 Not Ready for Inspection JESUS PINEDA
Final 5/14/2025 OK to Issue CofO BOBBY KEY
Special/Order Compliance 5/19/2025 Corrections Issued DAVID FEILER
Special/Order Compliance 6/4/2025 Partial Inspection DAVID FEILER