3220 N ETTRICK ST 90027
Certificate Information: 3220 N ETTRICK ST 90027
- Application / Permit
- 22010-10000-03013
- Plan Check / Job No.
- B22LA11602
- Group
- Building
- Type
- Bldg-New
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Accessory Dwelling Unit
- Work Description
- NEW CONSTRUCTION OF ACCESSORY DWELLING UNIT ATTACHED WITH STORAGE FOR SINGLE FAMILY DWELLING PER GCS 65852.2(e)(1)(B) AND LAMC12.22 A.33(c),(d) AND (G)
- Permit Issued
- Issued on 2/27/2023
- Issuing Office
- Current Status
- CofO Issued on 9/6/2024
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 6/15/2022 | APPLICANT |
| Assigned to Plan Check Engineer | 6/16/2022 | DANIEL SANJUAN |
| Corrections Issued | 6/21/2022 | DANIEL SANJUAN |
| Building Plans Picked Up | 6/29/2022 | APPLICANT |
| Applicant returned to address corrections | 2/3/2023 | MINA HABILI |
| Plan Check Approved | 2/7/2023 | DANIEL SMILEY |
| Issued | 2/27/2023 | APPLICANT |
| CofO in Progress | 8/21/2024 | ENRIQUE MIRELES |
| Permit Finaled | 9/6/2024 | RUBEN SALAS |
| CofO Issued | 9/6/2024 | RUBEN SALAS |
| Permit Finaled | 9/6/2024 | RUBEN SALAS |
Permit Application Clearance Information
| Address approval | Cleared | 7/20/2022 | CHRISTOPHER ROCHA |
| BHO/Hillside ordinance | Cleared | 7/20/2022 | CHRISTOPHER ROCHA |
| BHO/Hillside ordinance | Cleared | 7/20/2022 | CHRISTOPHER ROCHA |
| BHO/Hillside ordinance | Cleared | 7/20/2022 | CHRISTOPHER ROCHA |
| Eng Process Fee Ord 176,300 | Cleared | 7/20/2022 | CHRISTOPHER ROCHA |
| Sewer availability | Cleared | 7/20/2022 | CHRISTOPHER ROCHA |
| Grading Pre-Inspection | Cleared | 7/22/2022 | KIRK LINKLATER |
| Hydrant and Access approval | Cleared | 8/6/2022 | KURT CORRAL |
| Construction near power lines | Cleared | 9/6/2022 | RIDWAN HARDY |
| Low Impact Development | Cleared | 1/24/2023 | MARCO SANCHEZ |
| GPI Written Notices | Cleared | 2/3/2023 | DANIEL SANJUAN |
| Roof/Waste drainage to street | Cleared | 2/3/2023 | JEANETTE VONG |
Contact Information
| Contractor | Elliot Wall Design & Build Inc ; Lic. No.: 1095574-B | 832 ROBINSON ST LOS ANGELES, CA 90026 |
| Engineer | Hansen,, Neil Christian; Lic. No.: L9027 | 1545 VICTORY BLVD 2ND FLOOR N.C. HANSEN INC. GLENDALE, CA 91201 |
| Engineer | Phillips,, Craig; Lic. No.: C69673 | 2123 VESTAL AVE LOS ANGELES, CA 90026 |
Inspector Information
| ENRIQUE MIRELES, (213) 202-3438 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Pre-Inspection | 4/6/2023 | Approved | JOSEPH MCGARRY |
| BUILDING-Rough-Frame | 7/14/2023 | Not Ready for Inspection | JOSEPH MCGARRY |
| Green Building Rough | 7/14/2023 | Not Ready for Inspection | JOSEPH MCGARRY |
| PLUMBING-Rough | 7/14/2023 | Not Ready for Inspection | JOSEPH MCGARRY |
| Verify Sprinkler Sign Off | 7/14/2023 | Not Ready for Inspection | JOSEPH MCGARRY |
| BUILDING-Rough-Frame | 7/17/2023 | Partial Approval | JOSEPH MCGARRY |
| PLUMBING-Rough | 7/17/2023 | Partial Approval | JOSEPH MCGARRY |
| Floor/Roof Diaphrgm/Shear Wall | 8/10/2023 | Partial Approval | JOSEPH MCGARRY |
| Underground Mechanical | 9/19/2023 | Partial Inspection | JOSEPH MCGARRY |
| Underground Mechanical | 9/20/2023 | Approved | JOSEPH MCGARRY |
| BUILDING-Rough-Frame | 10/16/2023 | Approved | JOSEPH MCGARRY |
| ELECTRICAL-Rough | 10/16/2023 | Approved | JOSEPH MCGARRY |
| Green Building Rough | 10/16/2023 | Approved | JOSEPH MCGARRY |
| HVAC-Rough | 10/16/2023 | Approved | JOSEPH MCGARRY |
| PLUMBING-Rough | 10/16/2023 | Approved | JOSEPH MCGARRY |
| Verify Sprinkler Sign Off | 10/16/2023 | Approved | JOSEPH MCGARRY |
| Interior/Exterior Lathing | 10/23/2023 | Partial Approval | JOSEPH MCGARRY |
| Interior/Exterior Lathing | 10/26/2023 | Approved | JOSEPH MCGARRY |
| Shower Pan | 10/26/2023 | Approved | JOSEPH MCGARRY |
| Insulation | 10/31/2023 | Corrections Issued | JOSEPH MCGARRY |
| Insulation | 11/6/2023 | Approved | JOSEPH MCGARRY |
| Drywall Nailing | 11/8/2023 | Approved | JOSEPH MCGARRY |
| ELECTRICAL-Final | 3/26/2024 | Corrections Issued | ENRIQUE MIRELES |
| HVAC-Final | 3/26/2024 | Approved | ENRIQUE MIRELES |
| PLUMBING-Final | 3/26/2024 | Approved | ENRIQUE MIRELES |
| Final | 5/8/2024 | Corrections Issued | ENRIQUE MIRELES |
| Footing/Foundation/Slab | 5/8/2024 | Approved | ENRIQUE MIRELES |
| Green Building Final | 5/8/2024 | Approved | ENRIQUE MIRELES |
| SGSOV-Seismic Gas S/O Valve | 5/8/2024 | SGSOV Approved | ENRIQUE MIRELES |
| Service/Power Release | 5/8/2024 | Not Ready for Inspection | ENRIQUE MIRELES |
| Smoke Detectors | 5/8/2024 | Approved | ENRIQUE MIRELES |
| ELECTRICAL-Final | 8/1/2024 | Not Ready for Inspection | JOAQUIN GREENOUGH |
| Final | 8/1/2024 | Not Ready for Inspection | JOAQUIN GREENOUGH |
| PLUMBING-Final | 8/1/2024 | Not Ready for Inspection | JOAQUIN GREENOUGH |
| Service/Power Release | 8/1/2024 | Not Ready for Inspection | JOAQUIN GREENOUGH |
| ELECTRICAL-Final | 8/5/2024 | Corrections Issued | JOAQUIN GREENOUGH |
| ELECTRICAL-Final | 8/9/2024 | Approved | ENRIQUE MIRELES |
| Final | 8/13/2024 | OK to Issue CofO | ENRIQUE MIRELES |
| Service/Power Release | 8/13/2024 | Approved | ENRIQUE MIRELES |