1415 W 81ST ST 90047
Certificate Information: 1415 W 81ST ST 90047
- Application / Permit
- 22010-10000-03001
- Plan Check / Job No.
- B22LA07982
- Group
- Building
- Type
- Bldg-New
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Accessory Dwelling Unit
- Work Description
- EPLAN: NEW 2 STORY DETAHCED ADU WITH ATT. 2 CAR GARAGE PER ORDINANCE (LAMC 12.22 A.33(c) and (d))
- Permit Issued
- Issued on 1/18/2023
- Issuing Office
- Current Status
- CofO Issued on 9/21/2023
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 4/27/2022 | APPLICANT |
| Assigned to Plan Check Engineer | 5/26/2022 | GARO TELMI |
| Corrections Issued | 6/15/2022 | GARO TELMI |
| Quality Review Completed | 6/23/2022 | CHAD DOI |
| Plan Check Approved | 9/21/2022 | GARO TELMI |
| No Progress | 9/21/2022 | GARO TELMI |
| Plan Check Approved | 9/22/2022 | GARO TELMI |
| Issued | 1/18/2023 | APPLICANT |
| CofO in Progress | 9/12/2023 | MICHAEL LEWIS |
| Permit Finaled | 9/21/2023 | DEROLD HAUFF |
| CofO Issued | 9/21/2023 | DEROLD HAUFF |
| Permit Finaled | 9/21/2023 | DEROLD HAUFF |
Permit Application Clearance Information
| Address approval | Cleared | 6/28/2022 | JEANIE LAM |
| Eng Process Fee Ord 176,300 | Cleared | 6/28/2022 | JEANIE LAM |
| Permit | Cleared | 6/28/2022 | JEANIE LAM |
| Sewer availability | Cleared | 6/29/2022 | JEANIE LAM |
| Construction near power lines | Cleared | 7/15/2022 | TINA MIRANDA |
| Low Impact Development | Cleared | 7/20/2022 | LONDY ALVARADO |
| Roof/Waste drainage to street | Cleared | 7/29/2022 | JEANIE LAM |
| Hydrant and Access approval | Cleared | 7/30/2022 | KURT CORRAL |
Contact Information
| Contractor | K N Consulting Inc; Lic. No.: 993102-B | P O BOX 410 SUNSET BEACH, CA 90742 |
| Engineer | , ; Lic. No.: NA81695 | , |
Inspector Information
| JOHN QUINTANILLA, (213) 792-6055 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| PLUMBING-Rough | 3/30/2023 | Conditional Approval | LILIANA PORTILLO |
| Footing/Foundation/Slab | 4/5/2023 | Approved | LILIANA PORTILLO |
| Floor/Roof Diaphrgm/Shear Wall | 4/21/2023 | Corrections Issued | ALEJANDRO DE ARTOLA |
| Floor/Roof Diaphrgm/Shear Wall | 5/31/2023 | Approved | MICHAEL LEWIS |
| HVAC-Rough | 6/14/2023 | Approved | MICHAEL LEWIS |
| PLUMBING-Rough | 6/14/2023 | Approved | MICHAEL LEWIS |
| BUILDING-Rough-Frame | 6/15/2023 | Approved | MICHAEL LEWIS |
| ELECTRICAL-Rough | 6/15/2023 | Approved | MICHAEL LEWIS |
| Green Building Rough | 6/15/2023 | Approved | MICHAEL LEWIS |
| Verify Sprinkler Sign Off | 6/15/2023 | Approved | MICHAEL LEWIS |
| Insulation | 6/20/2023 | Approved | MICHAEL LEWIS |
| Drywall Nailing | 7/7/2023 | Approved | MICHAEL LEWIS |
| Interior/Exterior Lathing | 7/7/2023 | Approved | MICHAEL LEWIS |
| Sewer | 7/24/2023 | Approved | MICHAEL LEWIS |
| Underground Mechanical | 7/24/2023 | Approved | MICHAEL LEWIS |
| ELECTRICAL-Final | 8/15/2023 | Partial Approval | MICHAEL LEWIS |
| HVAC-Final | 8/29/2023 | Approved | MICHAEL LEWIS |
| PLUMBING-Final | 8/29/2023 | Approved | MICHAEL LEWIS |
| ELECTRICAL-Final | 8/30/2023 | Approved | MICHAEL LEWIS |
| Final | 8/30/2023 | Corrections Issued | MICHAEL LEWIS |
| Green Building Final | 8/30/2023 | Approved | MICHAEL LEWIS |
| SGSOV-Seismic Gas S/O Valve | 8/30/2023 | SGSOV Approved | MICHAEL LEWIS |
| Service/Power Release | 8/30/2023 | Approved | MICHAEL LEWIS |
| Smoke Detectors | 8/30/2023 | Approved | MICHAEL LEWIS |
| Service/Power Release | 8/31/2023 | Approved | MICHAEL LEWIS |
| Final | 9/11/2023 | OK to Issue CofO | MICHAEL LEWIS |