135-137 W 92ND ST 90003

Certificate Information: 135-137 W 92ND ST 90003

Application / Permit
22010-10000-02986
Plan Check / Job No.
B22LA11488
Group
Building
Type
Bldg-New
Sub-Type
1 or 2 Family Dwelling
Primary Use
(2) Duplex
Work Description
EPLAN NEW 2-STORY DUPLEX & ATTACHED 3-CAR GARAGE
Permit Issued
Issued on 4/17/2023
Issuing Office
Current Status
CofO Issued on 10/29/2023
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 6/15/2022 APPLICANT
Assigned to Plan Check Engineer 6/30/2022 ADRIANA LOPEZ
Corrections Issued 7/8/2022 ADRIANA LOPEZ
Quality Review Completed 7/19/2022 GARO TELMI
Plan Check Approved 4/5/2023 ADRIANA LOPEZ
Issued 4/17/2023 APPLICANT
CofO in Progress 10/21/2023 ALEJANDRO DE ARTOLA
Permit Finaled 10/29/2023 DEROLD HAUFF
CofO Issued 10/29/2023 DEROLD HAUFF
Permit Finaled 10/29/2023 DEROLD HAUFF

Permit Application Clearance Information

Low Impact Development Cleared 7/21/2022 LONDY ALVARADO
Address approval Cleared 8/11/2022 JEANETTE VONG
Permit Cleared 8/11/2022 JEANETTE VONG
Roof/Waste drainage to street Cleared 8/11/2022 JEANETTE VONG
Eng Process Fee Ord 176,300 Cleared 8/16/2022 JEANETTE VONG
Sewer availability Cleared 8/16/2022 JEANETTE VONG
Hydrant and Access approval Cleared 9/2/2022 RUEL COLE
SB8 RUD Cleared 1/12/2023 LOUIE MILLER

Contact Information

Contractor K N Consulting Inc; Lic. No.: 993102-B       ,
Engineer Madero,, Fidencio; Lic. No.: C81695 10002 PANGBORN AVE      DOWNEY, CA 90240
Engineer Madero,, Fidencio; Lic. No.: NA81695       ,

Inspector Information

JOHN QUINTANILLA, (213) 792-6055 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Excavation/Setback/Form/Re-Bar 4/27/2023 No Access for Inspection MICHAEL LEWIS
Footing/Foundation/Slab 4/27/2023 No Access for Inspection MICHAEL LEWIS
Excavation/Setback/Form/Re-Bar 4/28/2023 Approved ALEJANDRO DE ARTOLA
Footing/Foundation/Slab 4/28/2023 Conditional Approval ALEJANDRO DE ARTOLA
Floor/Roof Diaphrgm/Shear Wall 5/19/2023 Partial Approval MICHAEL LEWIS
Sewer 5/19/2023 Approved MICHAEL LEWIS
Underground Mechanical 5/19/2023 Approved MICHAEL LEWIS
Floor/Roof Diaphrgm/Shear Wall 5/22/2023 Partial Approval MICHAEL LEWIS
Insulation 5/22/2023 Partial Approval MICHAEL LEWIS
Floor/Roof Diaphrgm/Shear Wall 5/31/2023 Partial Approval MICHAEL LEWIS
Deputy Wood Construction 6/6/2023 Conditional Approval STUART CHAPMAN
Deputy Reinf. Concrete 6/13/2023 Conditional Approval MICHAEL LEWIS
Floor/Roof Diaphrgm/Shear Wall 6/14/2023 Approved MICHAEL LEWIS
HVAC-Rough 7/10/2023 Approved MICHAEL LEWIS
PLUMBING-Rough 7/10/2023 Approved MICHAEL LEWIS
BUILDING-Rough-Frame 7/11/2023 Approved MICHAEL LEWIS
ELECTRICAL-Rough 7/11/2023 Approved MICHAEL LEWIS
Green Building Rough 7/11/2023 Approved MICHAEL LEWIS
Verify Sprinkler Sign Off 7/11/2023 Approved MICHAEL LEWIS
Insulation 7/14/2023 Approved MICHAEL LEWIS
Interior/Exterior Lathing 7/14/2023 Approved MICHAEL LEWIS
Drywall Nailing 7/19/2023 Approved MICHAEL LEWIS
Interior/Exterior Lathing 7/27/2023 Approved MICHAEL LEWIS
ELECTRICAL-Final 8/24/2023 Partial Approval MICHAEL LEWIS
Footing/Foundation/Slab 10/5/2023 Approved MICHAEL LEWIS
Gas Test 10/5/2023 Approved MICHAEL LEWIS
HVAC-Final 10/5/2023 Approved MICHAEL LEWIS
PLUMBING-Final 10/5/2023 Approved MICHAEL LEWIS
SGSOV-Seismic Gas S/O Valve 10/5/2023 SGSOV Approved MICHAEL LEWIS
Smoke Detectors 10/5/2023 Approved MICHAEL LEWIS
ELECTRICAL-Final 10/16/2023 Approved ALEJANDRO DE ARTOLA
Final 10/16/2023 Corrections Issued ALEJANDRO DE ARTOLA
Green Building Final 10/16/2023 Approved ALEJANDRO DE ARTOLA
Service/Power Release 10/16/2023 Corrections Issued ALEJANDRO DE ARTOLA
Final 10/18/2023 Corrections Issued ALEJANDRO DE ARTOLA
Service/Power Release 10/18/2023 Approved ALEJANDRO DE ARTOLA
Final 10/20/2023 OK to Issue CofO ALEJANDRO DE ARTOLA
Service/Power Release 10/20/2023 Approved ALEJANDRO DE ARTOLA