225 S WINDSOR BLVD 90004

Certificate Information: 225 S WINDSOR BLVD 90004

Application / Permit
22010-10000-02966
Plan Check / Job No.
B22LA11381
Group
Building
Type
Bldg-Addition
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Accessory Dwelling Unit
Work Description
eplan: CARPORT ADDITION AND CONVERT (E) GARAGE TO 1-STORY ACCESSORY DWELLING UNIT PER CA Govt. Code 65852.2(e)(1)(A)
Permit Issued
Issued on 2/15/2024
Issuing Office
Current Status
CofO Issued on 11/30/2024
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 6/14/2022 APPLICANT
Assigned to Plan Check Engineer 6/23/2022 DANIEL YIP
Corrections Issued 6/23/2022 DANIEL YIP
Plan Check Approved 9/30/2022 DANIEL YIP
Issued 2/15/2024 APPLICANT
CofO in Progress 10/2/2024 JEFFREY MEAD
Permit Finaled 11/30/2024 DEROLD HAUFF
CofO Issued 11/30/2024 DEROLD HAUFF
Permit Finaled 11/30/2024 DEROLD HAUFF

Permit Application Clearance Information

Address approval Cleared 6/30/2022 CINDY QI
Sewer availability Cleared 6/30/2022 CINDY QI
Eng Process Fee Ord 176,300 Cleared 7/8/2022 CINDY QI
Construction near power lines Cleared 8/24/2022 RIDWAN HARDY
HPOZ Cleared 9/28/2022 DAMIAN GATTO

Contact Information

Architect Christopher,, William Robert; Lic. No.: C11333 732 N GARDNER      LOS ANGELES, CA 90046
Contractor Parry Construction Inc; Lic. No.: 1096448-B       ,

Inspector Information

JEFFREY MEAD, (213) 202-3240 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

BUILDING-Rough-Frame 3/15/2024 Corrections Issued AMIR NAZARIAN
Green Building Rough 3/15/2024 Corrections Issued AMIR NAZARIAN
METHANE-Rough 3/15/2024 Corrections Issued AMIR NAZARIAN
Deputy Wood Construction 7/16/2024 Conditional Approval BRENDAN MORELLI
Drywall Nailing 8/8/2024 Approved JEFFREY MEAD
Green Building Rough 8/8/2024 Approved JEFFREY MEAD
Interior/Exterior Lathing 8/8/2024 Approved JEFFREY MEAD
BUILDING-Rough-Frame 9/30/2024 Approved JEFFREY MEAD
ELECTRICAL-Final 9/30/2024 Approved JEFFREY MEAD
Final 9/30/2024 Corrections Issued JEFFREY MEAD
Footing/Foundation/Slab 9/30/2024 Approved JEFFREY MEAD
Green Building Final 9/30/2024 Approved JEFFREY MEAD
HVAC-Final 9/30/2024 Approved JEFFREY MEAD
METHANE-Barrier 9/30/2024 Approved JEFFREY MEAD
METHANE-Final 9/30/2024 Approved JEFFREY MEAD
METHANE-Rough 9/30/2024 Approved JEFFREY MEAD
METHANE-Subgrade 9/30/2024 Approved JEFFREY MEAD
PLUMBING-Final 9/30/2024 Approved JEFFREY MEAD
Smoke Detectors 9/30/2024 Approved JEFFREY MEAD
Final 10/2/2024 OK to Issue CofO JEFFREY MEAD