5149 1/2 N DAHLIA DR 90041
Certificate Information: 5149 1/2 N DAHLIA DR 90041
- Application / Permit
- 22010-10000-02965
- Plan Check / Job No.
- B22LA11380
- Group
- Building
- Type
- Bldg-New
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Accessory Dwelling Unit
- Work Description
- eplan: (N) 1-STORY ACCESSORY DWELLING UNIT PER CA Govt. Code 65852.2(e)(1)(B) and applicable part of LAMC 12.22 A.33 (c)-(d), (g)
- Permit Issued
- Issued on 11/28/2022
- Issuing Office
- Current Status
- CofO Issued on 8/9/2023
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 6/13/2022 | APPLICANT |
| Assigned to Plan Check Engineer | 6/23/2022 | DANIEL YIP |
| Corrections Issued | 6/24/2022 | DANIEL YIP |
| Applicant returned to address corrections | 8/18/2022 | DANIEL YIP |
| Plan Check Approved | 11/16/2022 | DANIEL YIP |
| Issued | 11/28/2022 | APPLICANT |
| CofO in Progress | 8/9/2023 | CRAIG VAUGHAN |
| Permit Finaled | 8/9/2023 | RONALD MYRICK |
| Permit Finaled | 8/9/2023 | RONALD MYRICK |
| CofO Issued | 8/9/2023 | RONALD MYRICK |
Permit Application Clearance Information
| Grading Pre-Inspection | Cleared | 8/3/2022 | KIRK LINKLATER |
| Address approval | Cleared | 8/5/2022 | AMAAN MALIK |
| Roof/Waste drainage to street | Cleared | 8/5/2022 | AMAAN MALIK |
| Eng Process Fee Ord 176,300 | Cleared | 8/12/2022 | AMAAN MALIK |
| Sewer availability | Cleared | 8/12/2022 | AMAAN MALIK |
| Construction near power lines | Cleared | 8/23/2022 | RIDWAN HARDY |
| Miscellaneous | Cleared | 11/14/2022 | ALBERT TAM |
Contact Information
| Contractor | L A Developing Inc; Lic. No.: 1083426-B | , |
| Engineer | Grigoryan,, Souren; Lic. No.: C93320 | 6506 TEESDALE AVE NORTH HOLLYWOOD, CA 91606 |
| Engineer | Grigoryan,, Souren; Lic. No.: NA93320 | , |
Inspector Information
| RONNIE MEDINA, (213) 469-5852 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Sewer | 12/16/2022 | Approved | CRAIG VAUGHAN |
| Excavation/Setback/Form/Re-Bar | 12/23/2022 | Corrections Issued | THOMAS LOGRASSO |
| Footing/Foundation/Slab | 12/23/2022 | Not Ready for Inspection | THOMAS LOGRASSO |
| Excavation/Setback/Form/Re-Bar | 12/29/2022 | Not Ready for Inspection | CRAIG VAUGHAN |
| Footing/Foundation/Slab | 12/29/2022 | Corrections Issued | CRAIG VAUGHAN |
| Excavation/Setback/Form/Re-Bar | 1/6/2023 | Approved | JOAQUIN GREENOUGH |
| Floor/Roof Diaphrgm/Shear Wall | 2/9/2023 | Partial Approval | CRAIG VAUGHAN |
| PLUMBING-Rough | 2/9/2023 | Not Ready for Inspection | CRAIG VAUGHAN |
| BUILDING-Rough-Frame | 2/23/2023 | Corrections Issued | SCOTT FINNILA |
| ELECTRICAL-Rough | 2/23/2023 | Corrections Issued | SCOTT FINNILA |
| HVAC-Rough | 2/23/2023 | Approved | SCOTT FINNILA |
| PLUMBING-Rough | 2/23/2023 | Approved | SCOTT FINNILA |
| BUILDING-Rough-Frame | 3/9/2023 | Corrections Issued | CRAIG VAUGHAN |
| Footing/Foundation/Slab | 3/9/2023 | Approved | CRAIG VAUGHAN |
| Green Building Rough | 3/9/2023 | Approved | CRAIG VAUGHAN |
| HVAC-Rough | 3/9/2023 | Corrections Issued | CRAIG VAUGHAN |
| Interior/Exterior Lathing | 3/9/2023 | Partial Approval | CRAIG VAUGHAN |
| Verify Sprinkler Sign Off | 3/9/2023 | Approved | CRAIG VAUGHAN |
| Insulation | 3/17/2023 | Conditional Approval | AMY COLIN |
| Drywall Nailing | 3/22/2023 | Approved | JEFFREY MEAD |
| Interior/Exterior Lathing | 3/22/2023 | Partial Approval | JEFFREY MEAD |
| Shower Pan | 3/22/2023 | Approved | JEFFREY MEAD |
| SGSOV-Seismic Gas S/O Valve | 6/2/2023 | SGSOV Not Ready | BRIAN SULLIVAN |
| BUILDING-Rough-Frame | 6/12/2023 | Approved | BRIAN SULLIVAN |
| Final | 6/12/2023 | Corrections Issued | BRIAN SULLIVAN |
| Green Building Final | 6/12/2023 | Approved | BRIAN SULLIVAN |
| SGSOV-Seismic Gas S/O Valve | 6/12/2023 | SGSOV Not Ready | BRIAN SULLIVAN |
| Service/Power Release | 6/12/2023 | Not Ready for Inspection | BRIAN SULLIVAN |
| Smoke Detectors | 6/12/2023 | Approved | BRIAN SULLIVAN |
| SGSOV-Seismic Gas S/O Valve | 6/21/2023 | SGSOV Not Ready | CRAIG VAUGHAN |
| Final | 6/27/2023 | Corrections Issued | JEFFREY MEAD |
| SGSOV-Seismic Gas S/O Valve | 7/7/2023 | SGSOV Not Ready | CRAIG VAUGHAN |
| Final | 8/8/2023 | OK to Issue CofO | CRAIG VAUGHAN |
| SGSOV-Seismic Gas S/O Valve | 8/8/2023 | SGSOV Approved | CRAIG VAUGHAN |
| Service/Power Release | 8/8/2023 | Approved | CRAIG VAUGHAN |