12812 W GREENE AVE 90066
Certificate Information: 12812 W GREENE AVE 90066
- Application / Permit
- 22010-10000-02948
- Plan Check / Job No.
- B22LA11325
- Group
- Building
- Type
- Bldg-Alter/Repair
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Accessory Dwelling Unit
- Work Description
- ePlan Conversion of a detached garage and storage into an ADU. PER GCS 65852.2(e) (1)(A)
- Permit Issued
- Issued on 8/21/2022
- Issuing Office
- Current Status
- CofO Issued on 10/17/2023
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 6/13/2022 | APPLICANT |
| Assigned to Plan Check Engineer | 6/14/2022 | DANIEL SANJUAN |
| Corrections Issued | 6/14/2022 | DANIEL SANJUAN |
| Applicant returned to address corrections | 6/29/2022 | DANIEL SANJUAN |
| Applicant returned to address corrections | 8/6/2022 | ZAW HAN |
| Plan Check Approved | 8/18/2022 | DANIEL SANJUAN |
| Issued | 8/21/2022 | APPLICANT |
| CofO in Progress | 10/17/2023 | HERBERT GIRON |
| Permit Finaled | 10/17/2023 | DANIEL ORRANTE |
| CofO Issued | 10/17/2023 | DANIEL ORRANTE |
| Permit Finaled | 10/17/2023 | DANIEL ORRANTE |
Permit Application Clearance Information
| Address approval | Cleared | 7/19/2022 | DINAH GARIN |
| Eng Process Fee Ord 176,300 | Cleared | 7/19/2022 | DINAH GARIN |
| Roof/Waste drainage to street | Cleared | 7/19/2022 | DINAH GARIN |
| Sewer availability | Cleared | 7/19/2022 | DINAH GARIN |
| Specific Plan | Cleared | 8/9/2022 | ROBERT SANCHEZ |
Contact Information
| Contractor | Gutierrez Omar; Lic. No.: 914077-B | , |
Inspector Information
| MORRIS JACKSON, (310) 914-3885 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Deputy Drilled-In Anchors | 9/8/2022 | Conditional Approval | RICHARD STEINBACH |
| Footing/Foundation/Slab | 9/16/2022 | Corrections Issued | HERBERT GIRON |
| METHANE-Rough | 9/16/2022 | Not Ready for Inspection | HERBERT GIRON |
| Wood Frame | 9/16/2022 | Not Ready for Inspection | HERBERT GIRON |
| Footing/Foundation/Slab | 10/13/2022 | Corrections Issued | HERBERT GIRON |
| Wall Anchors | 10/13/2022 | Not Ready for Inspection | HERBERT GIRON |
| Excavation/Setback/Form/Re-Bar | 10/18/2022 | Corrections Issued | HERBERT GIRON |
| Footing/Foundation/Slab | 10/18/2022 | Corrections Issued | HERBERT GIRON |
| Wall Anchors | 10/18/2022 | Not Ready for Inspection | HERBERT GIRON |
| Footing/Foundation/Slab | 10/24/2022 | Approved | DAVID FEILER |
| Pre-Inspection | 10/27/2022 | Corrections Issued | HERBERT GIRON |
| Floor/Roof Diaphrgm/Shear Wall | 12/1/2022 | Partial Approval | HERBERT GIRON |
| Final | 8/9/2023 | Corrections Issued | HERBERT GIRON |
| SGSOV-Seismic Gas S/O Valve | 8/9/2023 | SGSOV Approved | HERBERT GIRON |
| Smoke Detectors | 8/9/2023 | Approved | HERBERT GIRON |
| Final | 10/4/2023 | Corrections Issued | HERBERT GIRON |
| Wood Frame | 10/4/2023 | Approved | HERBERT GIRON |
| Final | 10/16/2023 | OK to Issue CofO | HERBERT GIRON |