1659 W 183RD ST 90248
Certificate Information: 1659 W 183RD ST 90248
- Application / Permit
- 22010-10000-02942
- Plan Check / Job No.
- B22LA11319
- Group
- Building
- Type
- Bldg-New
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Accessory Dwelling Unit
- Work Description
- eplan New Detached ADU per ordinance.
- Permit Issued
- Issued on 10/24/2024
- Issuing Office
- Current Status
- CofO Issued on 9/23/2025
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 6/15/2022 | APPLICANT |
| Assigned to Plan Check Engineer | 7/14/2022 | FARSHAD ALIMOHAMADI |
| Corrections Issued | 7/18/2022 | FARSHAD ALIMOHAMADI |
| Quality Review Completed | 7/20/2022 | CHARLES CHANG |
| Applicant returned to address corrections | 8/17/2022 | FARSHAD ALIMOHAMADI |
| Applicant returned to address corrections | 1/20/2023 | FARSHAD ALIMOHAMADI |
| Applicant returned to address corrections | 2/28/2023 | FARSHAD ALIMOHAMADI |
| Plan Check Approved | 3/5/2023 | FARSHAD ALIMOHAMADI |
| Issued | 10/24/2024 | APPLICANT |
| CofO in Progress | 7/22/2025 | BEN MOLSTAD |
| CofO in Progress | 7/23/2025 | BEN MOLSTAD |
| CofO in Progress | 9/22/2025 | BEN MOLSTAD |
| Permit Finaled | 9/23/2025 | ANSON MAGLASANG |
| CofO Issued | 9/23/2025 | ANSON MAGLASANG |
| Permit Finaled | 9/23/2025 | ANSON MAGLASANG |
Permit Application Clearance Information
| Address approval | Cleared | 7/22/2022 | JOSE HERNANDEZ |
| Construction near power lines | Cleared | 9/18/2022 | RIDWAN HARDY |
| Eng Process Fee Ord 176,300 | Cleared | 9/29/2022 | JOSE HERNANDEZ |
| Low Impact Development | Cleared | 1/26/2023 | DEBORA LEITE |
| Roof/Waste drainage to street | Cleared | 1/26/2023 | ANA SORIANO |
| Sewer availability | Cleared | 2/16/2023 | ANA SORIANO |
| Hydrant and Access approval | Cleared | 2/24/2023 | KURT CORRAL |
Contact Information
| Contractor | Adu Concepts; Lic. No.: 1018294-B | , |
| Contractor | Green Source Energy Inc; Lic. No.: 1018294-B | , |
| Engineer | Yiu,, Siu; Lic. No.: S5801 | PO BOX 5143 EL MONTE, CA 91734 |
Inspector Information
| BEN MOLSTAD, (310) 732-4557 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Sewer | 11/4/2024 | Partial Approval | BEN MOLSTAD |
| Underground Mechanical | 11/15/2024 | Partial Approval | BEN MOLSTAD |
| Excavation/Setback/Form/Re-Bar | 11/19/2024 | Approved | BEN MOLSTAD |
| Deputy Drilled-In Anchors | 12/10/2024 | Conditional Approval | BEN MOLSTAD |
| BUILDING-Rough-Frame | 12/12/2024 | Not Ready for Inspection | EUGENE CASSIDY |
| Floor/Roof Diaphrgm/Shear Wall | 12/12/2024 | Corrections Issued | EUGENE CASSIDY |
| Wood Frame | 12/12/2024 | Not Ready for Inspection | EUGENE CASSIDY |
| Floor/Roof Diaphrgm/Shear Wall | 12/16/2024 | Partial Approval | BEN MOLSTAD |
| Wood Frame | 12/16/2024 | No Access for Inspection | BEN MOLSTAD |
| BUILDING-Rough-Frame | 12/18/2024 | Not Ready for Inspection | BEN MOLSTAD |
| ELECTRICAL-Rough | 12/18/2024 | Not Ready for Inspection | BEN MOLSTAD |
| Floor/Roof Diaphrgm/Shear Wall | 12/18/2024 | Not Ready for Inspection | BEN MOLSTAD |
| HVAC-Rough | 12/18/2024 | Not Ready for Inspection | BEN MOLSTAD |
| PLUMBING-Rough | 12/18/2024 | Not Ready for Inspection | BEN MOLSTAD |
| Verify Sprinkler Sign Off | 12/18/2024 | Not Ready for Inspection | BEN MOLSTAD |
| BUILDING-Rough-Frame | 12/21/2024 | Partial Approval | EUGENE CASSIDY |
| ELECTRICAL-Rough | 12/21/2024 | Partial Approval | EUGENE CASSIDY |
| HVAC-Rough | 12/21/2024 | Partial Approval | EUGENE CASSIDY |
| Interior/Exterior Lathing | 12/21/2024 | Partial Approval | EUGENE CASSIDY |
| PLUMBING-Rough | 12/21/2024 | Approved | EUGENE CASSIDY |
| ELECTRICAL-Rough | 12/24/2024 | Corrections Issued | ANSON MAGLASANG |
| Insulation | 12/24/2024 | Corrections Issued | ANSON MAGLASANG |
| Insulation | 12/27/2024 | Not Ready for Inspection | BOBBY KEY |
| BUILDING-Rough-Frame | 12/31/2024 | Approved | BEN MOLSTAD |
| Insulation | 12/31/2024 | Approved | BEN MOLSTAD |
| Rough-Elec/Plmb/HVAC | 12/31/2024 | Approved | BEN MOLSTAD |
| Verify Sprinkler Sign Off | 12/31/2024 | Approved | BEN MOLSTAD |
| Drywall Nailing | 1/3/2025 | Not Ready for Inspection | BEN MOLSTAD |
| Drywall Nailing | 1/7/2025 | Approved | BEN MOLSTAD |
| ELECTRICAL-Final | 3/6/2025 | Not Ready for Inspection | BEN MOLSTAD |
| Final | 3/6/2025 | Not Ready for Inspection | BEN MOLSTAD |
| Footing/Foundation/Slab | 3/6/2025 | Approved | BEN MOLSTAD |
| HVAC-Final | 3/6/2025 | Not Ready for Inspection | BEN MOLSTAD |
| PLUMBING-Final | 3/6/2025 | Not Ready for Inspection | BEN MOLSTAD |
| SGSOV-Seismic Gas S/O Valve | 3/6/2025 | SGSOV Not Ready | BEN MOLSTAD |
| Service/Power Release | 3/6/2025 | Not Ready for Inspection | BEN MOLSTAD |
| Smoke Detectors | 3/6/2025 | Not Ready for Inspection | BEN MOLSTAD |
| ELECTRICAL-Rough | 6/3/2025 | Partial Approval | BEN MOLSTAD |
| ELECTRICAL-Final | 6/5/2025 | Corrections Issued | BEN MOLSTAD |
| Service/Power Release | 6/5/2025 | Not Ready for Inspection | BEN MOLSTAD |
| Service/Power Release | 6/16/2025 | Not Ready for Inspection | BEN MOLSTAD |
| SGSOV-Seismic Gas S/O Valve | 6/17/2025 | SGSOV Not Ready | BEN MOLSTAD |
| SGSOV-Seismic Gas S/O Valve | 6/23/2025 | SGSOV Not Ready | BEN MOLSTAD |
| ELECTRICAL-Final | 6/25/2025 | Corrections Issued | BEN MOLSTAD |
| Final | 6/25/2025 | Corrections Issued | BEN MOLSTAD |
| HVAC-Final | 6/25/2025 | Corrections Issued | BEN MOLSTAD |
| PLUMBING-Final | 6/25/2025 | Corrections Issued | BEN MOLSTAD |
| Service/Power Release | 6/25/2025 | Not Ready for Inspection | BEN MOLSTAD |
| ELECTRICAL-Final | 7/14/2025 | Approved | BEN MOLSTAD |
| Final | 7/14/2025 | Corrections Issued | BEN MOLSTAD |
| HVAC-Final | 7/14/2025 | Approved | BEN MOLSTAD |
| PLUMBING-Final | 7/14/2025 | Approved | BEN MOLSTAD |
| SGSOV-Seismic Gas S/O Valve | 7/14/2025 | SGSOV Not Ready | BEN MOLSTAD |
| Service/Power Release | 7/14/2025 | Not Ready for Inspection | BEN MOLSTAD |
| Smoke Detectors | 7/14/2025 | Approved | BEN MOLSTAD |
| ELECTRICAL-Final | 7/16/2025 | Approved | BEN MOLSTAD |
| Final | 7/16/2025 | Corrections Issued | BEN MOLSTAD |
| HVAC-Final | 7/16/2025 | Approved | BEN MOLSTAD |
| PLUMBING-Final | 7/16/2025 | Approved | BEN MOLSTAD |
| SGSOV-Seismic Gas S/O Valve | 7/16/2025 | SGSOV Approved | BEN MOLSTAD |
| Service/Power Release | 7/16/2025 | Approved | BEN MOLSTAD |
| Final | 7/22/2025 | Not Ready for Inspection | BEN MOLSTAD |
| Final | 7/24/2025 | Corrections Issued | BEN MOLSTAD |
| Final | 9/22/2025 | OK to Issue CofO | BEN MOLSTAD |