1610 W 85TH ST 90047
Certificate Information: 1610 W 85TH ST 90047
- Application / Permit
- 22010-10000-02932
- Plan Check / Job No.
- B22LA11282
- Group
- Building
- Type
- Bldg-New
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Accessory Dwelling Unit
- Work Description
- PROPOSED NEW ONE STORY ADU AT REAR OF LOT (1,200 SF max per Ordinance, LAMC 12.22 A.33 (c)-(d))
- Permit Issued
- Issued on 1/23/2023
- Issuing Office
- Current Status
- CofO Issued on 9/25/2024
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 6/10/2022 | APPLICANT |
| Assigned to Plan Check Engineer | 6/13/2022 | AUNG SOE |
| Corrections Issued | 6/16/2022 | AUNG SOE |
| Building Plans Picked Up | 6/21/2022 | APPLICANT |
| Plan Check Approved | 1/23/2023 | KHUONG TRUONG |
| Issued | 1/23/2023 | APPLICANT |
| CofO in Progress | 8/14/2024 | JOSE MACIAS |
| Permit Finaled | 9/25/2024 | RUBEN SALAS |
| CofO Issued | 9/25/2024 | RUBEN SALAS |
| Permit Finaled | 9/25/2024 | RUBEN SALAS |
Permit Application Clearance Information
| Address approval | Cleared | 6/24/2022 | AMAAN MALIK |
| Tenant Habitability Plan | Cleared | 6/30/2022 | MICHAEL SOTO |
| Eng Process Fee Ord 176,300 | Cleared | 7/1/2022 | AMAAN MALIK |
| Sewer availability | Cleared | 7/1/2022 | AMAAN MALIK |
| Construction near power lines | Cleared | 8/19/2022 | RIDWAN HARDY |
| Construction within easement | Cleared | 8/19/2022 | RIDWAN HARDY |
| Low Impact Development | Cleared | 12/22/2022 | ROGELIO CORTES |
| Roof/Waste drainage to street | Cleared | 12/28/2022 | AMAAN MALIK |
Contact Information
| Contractor | Jerahian Araz; Lic. No.: 1045340-B | 5730 TROTTERS LANE RANCHO CUCAMONGA, CA 91701 |
| Engineer | Burnazyan,, Gegam; Lic. No.: C76761 | 5832 JAMIESON AVE ENCINO, CA 91316 |
Inspector Information
| SALVADOR MARTINEZ, (213) 202-3479 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Excavation/Setback/Form/Re-Bar | 8/14/2023 | Not Ready for Inspection | ENRIQUE MIRELES |
| Sewer | 8/14/2023 | Corrections Issued | ENRIQUE MIRELES |
| Underground Mechanical | 8/14/2023 | Not Ready for Inspection | ENRIQUE MIRELES |
| Underground Mechanical | 8/18/2023 | Approved | ENRIQUE MIRELES |
| Excavation/Setback/Form/Re-Bar | 8/30/2023 | Corrections Issued | ENRIQUE MIRELES |
| Excavation/Setback/Form/Re-Bar | 9/25/2023 | Corrections Issued | ENRIQUE MIRELES |
| Excavation/Setback/Form/Re-Bar | 9/28/2023 | Approved | ENRIQUE MIRELES |
| Footing/Foundation/Slab | 9/28/2023 | Approved | ENRIQUE MIRELES |
| Floor/Roof Diaphrgm/Shear Wall | 12/1/2023 | Corrections Issued | ENRIQUE MIRELES |
| Green Building Rough | 12/1/2023 | Approved | ENRIQUE MIRELES |
| Verify Sprinkler Sign Off | 12/1/2023 | Approved | ENRIQUE MIRELES |
| Wood Frame | 12/1/2023 | Approved | ENRIQUE MIRELES |
| Floor/Roof Diaphrgm/Shear Wall | 12/6/2023 | Approved | ENRIQUE MIRELES |
| Gas Test | 12/6/2023 | Approved | ENRIQUE MIRELES |
| Rough-Elec/Plmb/HVAC | 12/6/2023 | Approved | ENRIQUE MIRELES |
| Wood Frame | 12/6/2023 | Approved | ENRIQUE MIRELES |
| Floor/Roof Diaphrgm/Shear Wall | 12/7/2023 | Approved | ENRIQUE MIRELES |
| Gas Test | 12/7/2023 | Approved | ENRIQUE MIRELES |
| Rough-Elec/Plmb/HVAC | 12/7/2023 | Approved | ENRIQUE MIRELES |
| Wood Frame | 12/7/2023 | Approved | ENRIQUE MIRELES |
| Interior/Exterior Lathing | 12/22/2023 | Corrections Issued | ENRIQUE MIRELES |
| Wood Frame | 12/27/2023 | Corrections Issued | ALEJANDRO DE ARTOLA |
| BUILDING-Rough-Frame | 1/4/2024 | Approved | ENRIQUE MIRELES |
| Wood Frame | 1/4/2024 | Approved | ENRIQUE MIRELES |
| Insulation | 1/8/2024 | Approved | ENRIQUE MIRELES |
| Interior/Exterior Lathing | 1/8/2024 | Approved | ENRIQUE MIRELES |
| Drywall Nailing | 1/19/2024 | Approved | ALIZAH MAYAGOITIA |
| Interior/Exterior Lathing | 2/9/2024 | Approved | ENRIQUE MIRELES |
| ELECTRICAL-Final | 4/24/2024 | Corrections Issued | JOSE MACIAS |
| Final | 4/24/2024 | Corrections Issued | JOSE MACIAS |
| Green Building Final | 4/24/2024 | Approved | JOSE MACIAS |
| HVAC-Final | 4/24/2024 | Corrections Issued | JOSE MACIAS |
| PLUMBING-Final | 4/24/2024 | Approved | JOSE MACIAS |
| SGSOV-Seismic Gas S/O Valve | 4/24/2024 | SGSOV Not Ready | JOSE MACIAS |
| Service/Power Release | 4/24/2024 | Not Ready for Inspection | JOSE MACIAS |
| Smoke Detectors | 4/24/2024 | Not Ready for Inspection | JOSE MACIAS |
| Final | 5/3/2024 | No Access for Inspection | JOSE MACIAS |
| SGSOV-Seismic Gas S/O Valve | 5/3/2024 | SGSOV Not Ready | JOSE MACIAS |
| Service/Power Release | 5/3/2024 | No Access for Inspection | JOSE MACIAS |
| Smoke Detectors | 5/3/2024 | No Access for Inspection | JOSE MACIAS |
| ELECTRICAL-Final | 5/13/2024 | Corrections Issued | JOSE MACIAS |
| Final | 5/13/2024 | Corrections Issued | JOSE MACIAS |
| SGSOV-Seismic Gas S/O Valve | 5/13/2024 | SGSOV Not Ready | JOSE MACIAS |
| Smoke Detectors | 5/13/2024 | Approved | JOSE MACIAS |
| ELECTRICAL-Final | 5/30/2024 | Not Ready for Inspection | JOSE MACIAS |
| Final | 5/30/2024 | Corrections Issued | JOSE MACIAS |
| SGSOV-Seismic Gas S/O Valve | 5/30/2024 | SGSOV Not Ready | JOSE MACIAS |
| Service/Power Release | 5/30/2024 | Not Ready for Inspection | JOSE MACIAS |
| SGSOV-Seismic Gas S/O Valve | 6/3/2024 | SGSOV Not Ready | JOSE MACIAS |
| Final | 6/4/2024 | Corrections Issued | JOSE MACIAS |
| Final | 6/6/2024 | Corrections Issued | JOSE MACIAS |
| SGSOV-Seismic Gas S/O Valve | 6/6/2024 | SGSOV Not Ready | JOSE MACIAS |
| Service/Power Release | 6/6/2024 | Corrections Issued | JOSE MACIAS |
| Final | 6/13/2024 | Corrections Issued | JOSE MACIAS |
| SGSOV-Seismic Gas S/O Valve | 6/13/2024 | SGSOV Not Ready | JOSE MACIAS |
| Service/Power Release | 6/13/2024 | Not Ready for Inspection | JOSE MACIAS |
| Final | 7/15/2024 | Corrections Issued | JOSE MACIAS |
| SGSOV-Seismic Gas S/O Valve | 7/15/2024 | SGSOV Approved | JOSE MACIAS |
| Service/Power Release | 7/15/2024 | Not Ready for Inspection | JOSE MACIAS |
| Final | 8/5/2024 | Corrections Issued | JOSE MACIAS |
| Service/Power Release | 8/5/2024 | Corrections Issued | JOSE MACIAS |
| Final | 8/7/2024 | Conditional Approval | JOSE MACIAS |
| Service/Power Release | 8/7/2024 | Approved | JOSE MACIAS |
| Final | 8/13/2024 | OK to Issue CofO | JOSE MACIAS |