16767 W MARQUEZ TER 90272

Certificate Information: 16767 W MARQUEZ TER 90272

Application / Permit
22010-10000-02903
Plan Check / Job No.
B22LA11212
Group
Building
Type
Bldg-New
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Dwelling - Single Family
Work Description
NEW 3-STORY SINGLE FAMILY DWELLING WITH ATTACHED GARAGE. 1 of 3 See Comment.
Permit Issued
Issued on 6/14/2024
Issuing Office
Metro
Current Status
Issued on 6/14/2024
Certificate of Occupancy
Pending More Information

Permit Application Status History

Submitted 6/9/2022 APPLICANT
Assigned to Plan Check Engineer 6/30/2022 TSE MING HUANG
Corrections Issued 7/6/2022 TSE MING HUANG
Quality Review Completed 7/8/2022 EUGENE BARBEAU
Building Plans Picked Up 7/13/2022 APPLICANT
Applicant returned to address corrections 7/13/2023 TSE MING HUANG
Applicant returned to address corrections 9/19/2023 TSE MING HUANG
Applicant returned to address corrections 10/13/2023 TSE MING HUANG
Applicant returned to address corrections 10/25/2023 TSE MING HUANG
Applicant returned to address corrections 11/2/2023 TSE MING HUANG
Applicant returned to address corrections 11/16/2023 TSE MING HUANG
Applicant returned to address corrections 1/17/2024 TSE MING HUANG
Plan Check Approved 1/31/2024 TSE MING HUANG
Issued 6/14/2024 APPLICANT

Permit Application Clearance Information

Hydrant and Access approval Cleared 9/2/2022 RUEL COLE
Miscellaneous Cleared 9/2/2022 RUEL COLE
BHO/Hillside ordinance Cleared 10/4/2022 ANTHONY MAINEZ
BHO/Hillside ordinance Cleared 10/4/2022 ANTHONY MAINEZ
BHO/Hillside ordinance Cleared 10/4/2022 ANTHONY MAINEZ
BHO/Hillside ordinance Cleared 10/4/2022 ANTHONY MAINEZ
BHO/Hillside ordinance Cleared 10/4/2022 ANTHONY MAINEZ
Eng Process Fee Ord 176,300 Cleared 10/4/2022 ANTHONY MAINEZ
Permit Cleared 10/4/2022 ANTHONY MAINEZ
Sewer availability Cleared 10/6/2022 ANTHONY MAINEZ
ZI Cleared 2/23/2023 JAZMIN ROQUE
Coastal Zone Cleared 6/6/2023 JAZMIN ROQUE
Encroachment in public way Cleared 6/29/2023 SAUL GARCIA
GPI Written Notices Cleared 10/25/2023 TSE MING HUANG
Grading Pre-Inspection Cleared 10/25/2023 TSE MING HUANG
Low Impact Development Cleared 11/27/2023 MITESH PATEL
Roof/Waste drainage to street Cleared 11/30/2023 ANDREA SAINT-ANTONIN
Building over 36-ft Cleared 1/31/2024 CALOSHA APPROVED
Excavation more than 5-ft deep Cleared 6/14/2024 CALOSHA APPROVED

Contact Information

Contractor J R Construction Adviser Inc; Lic. No.: 1105688-B 18711 SHERMAN WAY UNIT 110      RESEDA, CA 91335
Engineer Berkoz,, Ertunga; Lic. No.: S2504 4665 ELLENITA AVE      TARZANA, CA 91356
Engineer Kamboj,, Naresh Chande; Lic. No.: C21893 7838 QUIMBY AVE      CANOGA PARK, CA 91304
Geologist Bovenizer,, Ernest; Lic. No.: EG2515 7622 GODDARD AVENUE      LOS ANGELES, CA 90045

Inspector Information

DANIEL VERA, (213) 577-9924 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Excavation/Setback/Form/Re-Bar 9/20/2024 Partial Approval EVAN COOPER
PLUMBING-Rough 9/20/2024 Partial Approval EVAN COOPER
Deputy Reinf. Concrete 9/23/2024 Conditional Approval EVAN COOPER
Deputy Reinf. Concrete 9/30/2024 Conditional Approval EVAN COOPER
Deputy Reinf. Concrete 10/1/2024 Conditional Approval EVAN COOPER
Reinforced Concrete Frame 10/3/2024 Partial Approval ARAM AVEDISIAN
Deputy Shotcrete 10/4/2024 Conditional Approval ARAM AVEDISIAN
Footing/Foundation/Slab 10/16/2024 Partial Approval EVAN COOPER
Deputy Shotcrete 12/19/2024 Approved EVAN COOPER
Footing/Foundation/Slab 12/19/2024 Corrections Issued EVAN COOPER
Deputy Shotcrete 12/23/2024 Conditional Approval EVAN COOPER
PLUMBING-Rough 12/31/2024 Partial Approval EVAN COOPER
Excavation/Setback/Form/Re-Bar 7/29/2025 Corrections Issued STEPHANIE SWANSON