834 E 111TH DR 90059
Certificate Information: 834 E 111TH DR 90059
- Application / Permit
- 22010-10000-02887
- Plan Check / Job No.
- B22LA11182
- Group
- Building
- Type
- Bldg-Alter/Repair
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Accessory Dwelling Unit
- Work Description
- ePlan: CONVERT (E) GARAGE TO (N) 1-STORY ACCESSORY DWELLING UNIT PER CA Govt. Code 65852.2(e)(1)(A)
- Permit Issued
- Issued on 11/5/2022
- Issuing Office
- Current Status
- CofO Issued on 8/22/2023
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 6/23/2022 | APPLICANT |
| Assigned to Plan Check Engineer | 7/1/2022 | DANIEL YIP |
| Corrections Issued | 7/3/2022 | DANIEL YIP |
| Applicant returned to address corrections | 9/28/2022 | DANIEL YIP |
| Plan Check Approved | 10/19/2022 | DANIEL YIP |
| Issued | 11/5/2022 | APPLICANT |
| CofO in Progress | 8/15/2023 | JOHN KLARIN |
| CofO Issued | 8/22/2023 | ANSON MAGLASANG |
| Permit Finaled | 8/22/2023 | ANSON MAGLASANG |
Permit Application Clearance Information
| Sewer availability | Cleared | 8/24/2022 | JEANIE LAM |
| Address approval | Cleared | 8/25/2022 | JEANIE LAM |
| Eng Process Fee Ord 176,300 | Cleared | 8/25/2022 | JEANIE LAM |
Contact Information
| Contractor | Owner-Builder | , |
| Engineer | Cooke,, Conway Cecil; Lic. No.: NA5524 | , |
| Engineer | Cooke,, Conway Cecil; Lic. No.: S5524 | 34658 LINDA ROSEA RD TEMECULA, CA 92592 |
Inspector Information
| JOHN KLARIN, (310) 732-4558 | Office Hours: 7:00-8:00 AM MON-FRI |
| ARTHUR NEGRETE, (310) 732-4558 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Underground Mechanical | 2/7/2023 | Partial Approval | JOHN KLARIN |
| Interior/Exterior Lathing | 4/20/2023 | Not Ready for Inspection | JAMES CHAVEZ |
| Rough-Elec/Plmb/HVAC | 4/20/2023 | Partial Approval | JAMES CHAVEZ |
| Deputy Drilled-In Anchors | 4/21/2023 | Conditional Approval | JAMES CHAVEZ |
| Insulation | 4/28/2023 | Corrections Issued | JAMES CHAVEZ |
| ELECTRICAL-Rough | 5/5/2023 | Approved | JOHN KLARIN |
| Floor/Roof Diaphrgm/Shear Wall | 5/5/2023 | Approved | JOHN KLARIN |
| Gas Test | 5/5/2023 | Approved | JOHN KLARIN |
| Insulation | 5/9/2023 | Approved | JOHN KLARIN |
| Drywall Nailing | 5/15/2023 | Approved | JOHN KLARIN |
| BUILDING-Rough-Frame | 6/23/2023 | Approved | JOHN KLARIN |
| Final | 6/23/2023 | Corrections Issued | JOHN KLARIN |
| SGSOV-Seismic Gas S/O Valve | 6/23/2023 | SGSOV Not Ready | JOHN KLARIN |
| Smoke Detectors | 6/23/2023 | Approved | JOHN KLARIN |
| Final | 7/10/2023 | Corrections Issued | JOHN KLARIN |
| SGSOV-Seismic Gas S/O Valve | 7/10/2023 | SGSOV Approved | JOHN KLARIN |
| ELECTRICAL-Final | 8/14/2023 | Approved | JOHN KLARIN |
| Final | 8/14/2023 | OK to Issue CofO | JOHN KLARIN |
| HVAC-Final | 8/14/2023 | Order to Comply Issued | JOHN KLARIN |
| PLUMBING-Final | 8/14/2023 | Approved | JOHN KLARIN |