1408 E MITCHELL PL 90033

Certificate Information: 1408 E MITCHELL PL 90033

Application / Permit
22010-10000-02886
Plan Check / Job No.
B22LA11181
Group
Building
Type
Bldg-New
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Accessory Dwelling Unit
Work Description
NEW 21'-10 3/4" x 29'-9" TWO STORY DET. ACC. BLDG [1ST FLOOR 2-CAR GARAGE, 2ND FLOOR ACCESSORY DWELLING UNIT PER LAMC 12.22 A.33 (c)-(d)]
Permit Issued
Issued on 11/9/2022
Issuing Office
Current Status
CofO Issued on 4/8/2024
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 6/9/2022 APPLICANT
Assigned to Plan Check Engineer 6/23/2022 SEAN SHAHMIRI
Corrections Issued 7/1/2022 SEAN SHAHMIRI
Quality Review Completed 7/5/2022 OMID HEDAYAT
Applicant returned to address corrections 10/27/2022 SEAN SHAHMIRI
Plan Check Approved 11/7/2022 SEAN SHAHMIRI
Issued 11/9/2022 APPLICANT
CofO in Progress 4/4/2024 OSVALDO PARAMO
Permit Finaled 4/8/2024 DEROLD HAUFF
CofO Issued 4/8/2024 DEROLD HAUFF
Permit Finaled 4/8/2024 DEROLD HAUFF

Permit Application Clearance Information

Address approval Cleared 9/19/2022 CINDY QI
ZI Cleared 9/19/2022 RUBEN VASQUEZ
Eng Process Fee Ord 176,300 Cleared 9/26/2022 CINDY QI
Sewer availability Cleared 9/26/2022 CINDY QI
Grading Pre-Inspection Cleared 9/29/2022 KIRK LINKLATER
Low Impact Development Cleared 10/19/2022 DEBORA LEITE
Roof/Waste drainage to street Cleared 10/20/2022 CINDY QI
Hydrant and Access approval Cleared 11/7/2022 MATTHEW CRAIG

Contact Information

Contractor L A Developing Inc; Lic. No.: 1083426-B       ,
Engineer Grigoryan,, Souren; Lic. No.: C93320 6506 TEESDALE AVE      NORTH HOLLYWOOD, CA 91606

Inspector Information

OSVALDO PARAMO, (213) 202-9854 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

PLUMBING-Rough 11/30/2022 Partial Approval OSVALDO PARAMO
Excavation/Setback/Form/Re-Bar 12/7/2022 Corrections Issued OSVALDO PARAMO
Footing/Foundation/Slab 12/7/2022 Not Ready for Inspection OSVALDO PARAMO
METHANE-Barrier 12/7/2022 Not Ready for Inspection OSVALDO PARAMO
METHANE-Subgrade 12/7/2022 Not Ready for Inspection OSVALDO PARAMO
Excavation/Setback/Form/Re-Bar 12/13/2022 Approved OSVALDO PARAMO
Floor/Roof Diaphrgm/Shear Wall 12/27/2022 Partial Approval OSVALDO PARAMO
Deputy Wood Construction 1/18/2023 Conditional Approval AMY COLIN
ELECTRICAL-Rough 1/20/2023 Not Ready for Inspection OSVALDO PARAMO
Floor/Roof Diaphrgm/Shear Wall 1/20/2023 Approved OSVALDO PARAMO
HVAC-Rough 1/20/2023 Not Ready for Inspection OSVALDO PARAMO
PLUMBING-Rough 1/20/2023 Corrections Issued OSVALDO PARAMO
ELECTRICAL-Rough 1/25/2023 Corrections Issued ALIZAH MAYAGOITIA
Floor/Roof Diaphrgm/Shear Wall 1/25/2023 Partial Approval ALIZAH MAYAGOITIA
HVAC-Rough 1/25/2023 Not Ready for Inspection ALIZAH MAYAGOITIA
PLUMBING-Rough 1/25/2023 Approved ALIZAH MAYAGOITIA
BUILDING-Rough-Frame 2/14/2023 Approved OSVALDO PARAMO
ELECTRICAL-Rough 2/14/2023 Approved OSVALDO PARAMO
HVAC-Rough 2/14/2023 Approved OSVALDO PARAMO
MERV13>=Rough 2/14/2023 Approved OSVALDO PARAMO
METHANE-Rough 2/14/2023 Approved OSVALDO PARAMO
Shower Pan 2/14/2023 Approved OSVALDO PARAMO
Verify Sprinkler Sign Off 2/14/2023 Approved OSVALDO PARAMO
Interior/Exterior Lathing 2/17/2023 Partial Approval OSVALDO PARAMO
Insulation 2/28/2023 Approved OSVALDO PARAMO
Interior/Exterior Lathing 3/7/2023 Not Ready for Inspection OSVALDO PARAMO
Drywall Nailing 3/9/2023 Not Ready for Inspection OSVALDO PARAMO
Interior/Exterior Lathing 3/9/2023 Not Ready for Inspection OSVALDO PARAMO
Drywall Nailing 3/13/2023 Approved OSVALDO PARAMO
Interior/Exterior Lathing 3/13/2023 Approved OSVALDO PARAMO
Final 8/29/2023 No Access for Inspection ALIZAH MAYAGOITIA
Footing/Foundation/Slab 8/29/2023 No Access for Inspection ALIZAH MAYAGOITIA
MERV13>=Final 8/29/2023 No Access for Inspection ALIZAH MAYAGOITIA
METHANE-Barrier 8/29/2023 No Access for Inspection ALIZAH MAYAGOITIA
METHANE-Subgrade 8/29/2023 No Access for Inspection ALIZAH MAYAGOITIA
SGSOV-Seismic Gas S/O Valve 8/29/2023 SGSOV Not Ready ALIZAH MAYAGOITIA
Service/Power Release 8/29/2023 No Access for Inspection ALIZAH MAYAGOITIA
Smoke Detectors 8/29/2023 No Access for Inspection ALIZAH MAYAGOITIA
Final 9/5/2023 Corrections Issued OSVALDO PARAMO
Footing/Foundation/Slab 9/5/2023 Approved OSVALDO PARAMO
MERV13>=Final 9/5/2023 Approved OSVALDO PARAMO
METHANE-Barrier 9/5/2023 Approved OSVALDO PARAMO
METHANE-Subgrade 9/5/2023 Approved OSVALDO PARAMO
SGSOV-Seismic Gas S/O Valve 9/5/2023 SGSOV Approved OSVALDO PARAMO
Smoke Detectors 9/5/2023 Approved OSVALDO PARAMO
Final 12/20/2023 Corrections Issued OSVALDO PARAMO
Service/Power Release 12/20/2023 Not Ready for Inspection OSVALDO PARAMO
Final 1/8/2024 Corrections Issued OSVALDO PARAMO
Service/Power Release 1/8/2024 Approved OSVALDO PARAMO
Final 4/3/2024 OK to Issue CofO OSVALDO PARAMO