1408 E MITCHELL PL 90033
Certificate Information: 1408 E MITCHELL PL 90033
- Application / Permit
- 22010-10000-02886
- Plan Check / Job No.
- B22LA11181
- Group
- Building
- Type
- Bldg-New
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Accessory Dwelling Unit
- Work Description
- NEW 21'-10 3/4" x 29'-9" TWO STORY DET. ACC. BLDG [1ST FLOOR 2-CAR GARAGE, 2ND FLOOR ACCESSORY DWELLING UNIT PER LAMC 12.22 A.33 (c)-(d)]
- Permit Issued
- Issued on 11/9/2022
- Issuing Office
- Current Status
- CofO Issued on 4/8/2024
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 6/9/2022 | APPLICANT |
| Assigned to Plan Check Engineer | 6/23/2022 | SEAN SHAHMIRI |
| Corrections Issued | 7/1/2022 | SEAN SHAHMIRI |
| Quality Review Completed | 7/5/2022 | OMID HEDAYAT |
| Applicant returned to address corrections | 10/27/2022 | SEAN SHAHMIRI |
| Plan Check Approved | 11/7/2022 | SEAN SHAHMIRI |
| Issued | 11/9/2022 | APPLICANT |
| CofO in Progress | 4/4/2024 | OSVALDO PARAMO |
| Permit Finaled | 4/8/2024 | DEROLD HAUFF |
| CofO Issued | 4/8/2024 | DEROLD HAUFF |
| Permit Finaled | 4/8/2024 | DEROLD HAUFF |
Permit Application Clearance Information
| Address approval | Cleared | 9/19/2022 | CINDY QI |
| ZI | Cleared | 9/19/2022 | RUBEN VASQUEZ |
| Eng Process Fee Ord 176,300 | Cleared | 9/26/2022 | CINDY QI |
| Sewer availability | Cleared | 9/26/2022 | CINDY QI |
| Grading Pre-Inspection | Cleared | 9/29/2022 | KIRK LINKLATER |
| Low Impact Development | Cleared | 10/19/2022 | DEBORA LEITE |
| Roof/Waste drainage to street | Cleared | 10/20/2022 | CINDY QI |
| Hydrant and Access approval | Cleared | 11/7/2022 | MATTHEW CRAIG |
Contact Information
| Contractor | L A Developing Inc; Lic. No.: 1083426-B | , |
| Engineer | Grigoryan,, Souren; Lic. No.: C93320 | 6506 TEESDALE AVE NORTH HOLLYWOOD, CA 91606 |
Inspector Information
| OSVALDO PARAMO, (213) 202-9854 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| PLUMBING-Rough | 11/30/2022 | Partial Approval | OSVALDO PARAMO |
| Excavation/Setback/Form/Re-Bar | 12/7/2022 | Corrections Issued | OSVALDO PARAMO |
| Footing/Foundation/Slab | 12/7/2022 | Not Ready for Inspection | OSVALDO PARAMO |
| METHANE-Barrier | 12/7/2022 | Not Ready for Inspection | OSVALDO PARAMO |
| METHANE-Subgrade | 12/7/2022 | Not Ready for Inspection | OSVALDO PARAMO |
| Excavation/Setback/Form/Re-Bar | 12/13/2022 | Approved | OSVALDO PARAMO |
| Floor/Roof Diaphrgm/Shear Wall | 12/27/2022 | Partial Approval | OSVALDO PARAMO |
| Deputy Wood Construction | 1/18/2023 | Conditional Approval | AMY COLIN |
| ELECTRICAL-Rough | 1/20/2023 | Not Ready for Inspection | OSVALDO PARAMO |
| Floor/Roof Diaphrgm/Shear Wall | 1/20/2023 | Approved | OSVALDO PARAMO |
| HVAC-Rough | 1/20/2023 | Not Ready for Inspection | OSVALDO PARAMO |
| PLUMBING-Rough | 1/20/2023 | Corrections Issued | OSVALDO PARAMO |
| ELECTRICAL-Rough | 1/25/2023 | Corrections Issued | ALIZAH MAYAGOITIA |
| Floor/Roof Diaphrgm/Shear Wall | 1/25/2023 | Partial Approval | ALIZAH MAYAGOITIA |
| HVAC-Rough | 1/25/2023 | Not Ready for Inspection | ALIZAH MAYAGOITIA |
| PLUMBING-Rough | 1/25/2023 | Approved | ALIZAH MAYAGOITIA |
| BUILDING-Rough-Frame | 2/14/2023 | Approved | OSVALDO PARAMO |
| ELECTRICAL-Rough | 2/14/2023 | Approved | OSVALDO PARAMO |
| HVAC-Rough | 2/14/2023 | Approved | OSVALDO PARAMO |
| MERV13>=Rough | 2/14/2023 | Approved | OSVALDO PARAMO |
| METHANE-Rough | 2/14/2023 | Approved | OSVALDO PARAMO |
| Shower Pan | 2/14/2023 | Approved | OSVALDO PARAMO |
| Verify Sprinkler Sign Off | 2/14/2023 | Approved | OSVALDO PARAMO |
| Interior/Exterior Lathing | 2/17/2023 | Partial Approval | OSVALDO PARAMO |
| Insulation | 2/28/2023 | Approved | OSVALDO PARAMO |
| Interior/Exterior Lathing | 3/7/2023 | Not Ready for Inspection | OSVALDO PARAMO |
| Drywall Nailing | 3/9/2023 | Not Ready for Inspection | OSVALDO PARAMO |
| Interior/Exterior Lathing | 3/9/2023 | Not Ready for Inspection | OSVALDO PARAMO |
| Drywall Nailing | 3/13/2023 | Approved | OSVALDO PARAMO |
| Interior/Exterior Lathing | 3/13/2023 | Approved | OSVALDO PARAMO |
| Final | 8/29/2023 | No Access for Inspection | ALIZAH MAYAGOITIA |
| Footing/Foundation/Slab | 8/29/2023 | No Access for Inspection | ALIZAH MAYAGOITIA |
| MERV13>=Final | 8/29/2023 | No Access for Inspection | ALIZAH MAYAGOITIA |
| METHANE-Barrier | 8/29/2023 | No Access for Inspection | ALIZAH MAYAGOITIA |
| METHANE-Subgrade | 8/29/2023 | No Access for Inspection | ALIZAH MAYAGOITIA |
| SGSOV-Seismic Gas S/O Valve | 8/29/2023 | SGSOV Not Ready | ALIZAH MAYAGOITIA |
| Service/Power Release | 8/29/2023 | No Access for Inspection | ALIZAH MAYAGOITIA |
| Smoke Detectors | 8/29/2023 | No Access for Inspection | ALIZAH MAYAGOITIA |
| Final | 9/5/2023 | Corrections Issued | OSVALDO PARAMO |
| Footing/Foundation/Slab | 9/5/2023 | Approved | OSVALDO PARAMO |
| MERV13>=Final | 9/5/2023 | Approved | OSVALDO PARAMO |
| METHANE-Barrier | 9/5/2023 | Approved | OSVALDO PARAMO |
| METHANE-Subgrade | 9/5/2023 | Approved | OSVALDO PARAMO |
| SGSOV-Seismic Gas S/O Valve | 9/5/2023 | SGSOV Approved | OSVALDO PARAMO |
| Smoke Detectors | 9/5/2023 | Approved | OSVALDO PARAMO |
| Final | 12/20/2023 | Corrections Issued | OSVALDO PARAMO |
| Service/Power Release | 12/20/2023 | Not Ready for Inspection | OSVALDO PARAMO |
| Final | 1/8/2024 | Corrections Issued | OSVALDO PARAMO |
| Service/Power Release | 1/8/2024 | Approved | OSVALDO PARAMO |
| Final | 4/3/2024 | OK to Issue CofO | OSVALDO PARAMO |