2338 W RIVERSIDE DR 90039
Certificate Information: 2338 W RIVERSIDE DR 90039
- Application / Permit
- 22010-10000-02884
- Plan Check / Job No.
- B22LA11177
- Group
- Building
- Type
- Bldg-New
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Accessory Dwelling Unit
- Work Description
- eplan New 500 SF (25' X 20') detached ADU per GSC 65852.2(e)(1)(B) and LAMC 12.22 A.33(c),(d), AND (g)
- Permit Issued
- Issued on 2/26/2025
- Issuing Office
- Current Status
- CofO Issued on 9/28/2025
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 6/9/2022 | APPLICANT |
| Assigned to Plan Check Engineer | 7/14/2022 | NGHI SU |
| Corrections Issued | 7/18/2022 | NGHI SU |
| Quality Review Completed | 7/29/2022 | FARUK SEZER |
| Plan Check Approved | 5/10/2024 | NGHI SU |
| Plan Check Approved | 2/26/2025 | NGHI SU |
| Issued | 2/26/2025 | APPLICANT |
| CofO in Progress | 9/26/2025 | HAMIK HARTOUNIAN |
| Permit Finaled | 9/28/2025 | DEROLD HAUFF |
| CofO Issued | 9/28/2025 | DEROLD HAUFF |
| Permit Finaled | 9/28/2025 | DEROLD HAUFF |
Permit Application Clearance Information
| Address approval | Cleared | 8/2/2022 | ELAINE LEI |
| BHO/Hillside ordinance | Cleared | 8/2/2022 | ELAINE LEI |
| BHO/Hillside ordinance | Cleared | 8/2/2022 | ELAINE LEI |
| BHO/Hillside ordinance | Cleared | 8/2/2022 | ELAINE LEI |
| Roof/Waste drainage to street | Cleared | 8/2/2022 | ELAINE LEI |
| BHO/Hillside ordinance | Cleared | 8/4/2022 | ELAINE LEI |
| BHO/Hillside ordinance | Cleared | 8/4/2022 | ELAINE LEI |
| Eng Process Fee Ord 176,300 | Cleared | 8/4/2022 | ELAINE LEI |
| Sewer availability | Cleared | 8/4/2022 | ELAINE LEI |
| Hydrant and Access approval | Cleared | 9/24/2022 | GILBERT URREA |
| Grading Pre-Inspection | Cleared | 5/10/2024 | NGHI SU |
Contact Information
| Contractor | Masterpiece Construction; Lic. No.: 1008418-B | , |
| Engineer | Lee,, Jack; Lic. No.: GE2153 | 576 E LAMBERT RD BREA, CA 92821 |
| Engineer | Rhee,, Kyle; Lic. No.: C78215 | 2753 WAVERLY DR 403 LOS ANGELES, CA 90039 |
| Geologist | Aflakian,, Farzad; Lic. No.: EG2051 | 921 PENDIO IRVINE, CA 92620 |
Inspector Information
| HAMIK HARTOUNIAN, (213) 202-3275 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Excavation/Setback/Form/Re-Bar | 4/10/2025 | Corrections Issued | HAMIK HARTOUNIAN |
| Piling/Pier/Caisson | 4/10/2025 | Not Ready for Inspection | HAMIK HARTOUNIAN |
| Deputy Reinf. Concrete | 4/14/2025 | Approved | HAMIK HARTOUNIAN |
| Piling/Pier/Caisson | 4/14/2025 | Partial Approval | HAMIK HARTOUNIAN |
| Piling/Pier/Caisson | 4/16/2025 | Approved | JEFFREY MEAD |
| Footing/Foundation/Slab | 4/25/2025 | Partial Approval | HAMIK HARTOUNIAN |
| Deputy Drilled-In Anchors | 4/29/2025 | Conditional Approval | FREDDIE RIVERA |
| BUILDING-Rough-Frame | 5/5/2025 | Corrections Issued | ALIZAH MAYAGOITIA |
| Floor/Roof Diaphrgm/Shear Wall | 5/5/2025 | Partial Approval | ALIZAH MAYAGOITIA |
| MERV13>=Rough | 5/5/2025 | Not Ready for Inspection | ALIZAH MAYAGOITIA |
| Verify Sprinkler Sign Off | 5/5/2025 | Not Ready for Inspection | ALIZAH MAYAGOITIA |
| Floor/Roof Diaphrgm/Shear Wall | 5/7/2025 | Corrections Issued | NICHOLAS LOPEZ |
| Floor/Roof Diaphrgm/Shear Wall | 5/9/2025 | No Access for Inspection | HAMIK HARTOUNIAN |
| Floor/Roof Diaphrgm/Shear Wall | 5/16/2025 | Approved | WILLIAM SIERRA |
| Deputy Wood Construction | 5/19/2025 | Conditional Approval | HAMIK HARTOUNIAN |
| PLUMBING-Rough | 6/5/2025 | Approved | HAMIK HARTOUNIAN |
| ELECTRICAL-Rough | 6/10/2025 | Corrections Issued | HAMIK HARTOUNIAN |
| ELECTRICAL-Rough | 6/16/2025 | Corrections Issued | HAMIK HARTOUNIAN |
| Interior/Exterior Lathing | 6/16/2025 | Partial Approval | HAMIK HARTOUNIAN |
| Insulation | 6/17/2025 | Corrections Issued | WILLIAM SIERRA |
| BUILDING-Rough-Frame | 6/18/2025 | Partial Approval | HAMIK HARTOUNIAN |
| Green Building Rough | 6/18/2025 | Approved | HAMIK HARTOUNIAN |
| MERV13>=Rough | 6/18/2025 | Approved | HAMIK HARTOUNIAN |
| Shower Pan | 6/18/2025 | Conditional Approval | HAMIK HARTOUNIAN |
| Special/Order Compliance | 6/18/2025 | Partial Inspection | OSVALDO PARAMO |
| Verify Sprinkler Sign Off | 6/18/2025 | Approved | HAMIK HARTOUNIAN |
| Insulation | 6/20/2025 | No Access for Inspection | ALEX COLIN |
| Insulation | 7/7/2025 | Approved | BRENDAN MORELLI |
| Drywall Nailing | 7/14/2025 | Approved | ALEX COLIN |
| ELECTRICAL-Final | 9/5/2025 | Approved | HAMIK HARTOUNIAN |
| HVAC-Final | 9/5/2025 | Corrections Issued | HAMIK HARTOUNIAN |
| PLUMBING-Final | 9/5/2025 | Approved | HAMIK HARTOUNIAN |
| Smoke Detectors | 9/5/2025 | Approved | HAMIK HARTOUNIAN |
| BUILDING-Rough-Frame | 9/23/2025 | Approved | HAMIK HARTOUNIAN |
| Final | 9/23/2025 | Partial Inspection | HAMIK HARTOUNIAN |
| Footing/Foundation/Slab | 9/23/2025 | Approved | HAMIK HARTOUNIAN |
| Green Building Final | 9/23/2025 | Approved | HAMIK HARTOUNIAN |
| MERV13>=Final | 9/23/2025 | Approved | HAMIK HARTOUNIAN |
| SGSOV-Seismic Gas S/O Valve | 9/23/2025 | SGSOV Approved | HAMIK HARTOUNIAN |
| Service/Power Release | 9/23/2025 | Approved | HAMIK HARTOUNIAN |
| Special/Order Compliance | 9/23/2025 | Partial Inspection | OSVALDO PARAMO |
| Final | 9/26/2025 | OK to Issue CofO | HAMIK HARTOUNIAN |