1919 N WINMAR DR 90065

Certificate Information: 1919 N WINMAR DR 90065

Application / Permit
22010-10000-02883
Plan Check / Job No.
B22LA11175
Group
Building
Type
Bldg-New
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Accessory Dwelling Unit
Work Description
NEW IRR. SHAPED 27'-10" x 44'-4" ONE-STORY DET. ACCESSORY DWELLING UNIT PER LAMC 12.22 A.33 (c)-(d)
Permit Issued
Issued on 5/5/2023
Issuing Office
Current Status
CofO Issued on 4/18/2024
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 6/9/2022 APPLICANT
Assigned to Plan Check Engineer 6/23/2022 SEAN SHAHMIRI
Corrections Issued 6/30/2022 SEAN SHAHMIRI
Quality Review Completed 7/5/2022 OMID HEDAYAT
Plan Check Approved 4/13/2023 SEAN SHAHMIRI
Issued 5/5/2023 APPLICANT
CofO in Progress 4/18/2024 OSVALDO PARAMO
Permit Finaled 4/18/2024 DEROLD HAUFF
Permit Finaled 4/18/2024 DEROLD HAUFF
CofO Issued 4/18/2024 DEROLD HAUFF

Permit Application Clearance Information

Address approval Cleared 7/11/2022 CINDY QI
Sewer availability Cleared 7/11/2022 CINDY QI
Hydrant and Access approval Cleared 8/5/2022 RUEL COLE
Eng Process Fee Ord 176,300 Cleared 8/10/2022 CINDY QI
Specific Plan Cleared 8/10/2022 NASHYA JENSEN
Low Impact Development Cleared 2/6/2023 ROGELIO CORTES
Roof/Waste drainage to street Cleared 2/6/2023 CINDY QI
Construction near power lines Cleared 3/10/2023 RIDWAN HARDY
Grading Pre-Inspection Cleared 4/13/2023 SEAN SHAHMIRI

Contact Information

Contractor N A N D C O Llc; Lic. No.: 1044615-B       ,
Contractor Nandco Construction; Lic. No.: 1044615-B       ,
Engineer Standley,, Craig Erick; Lic. No.: C87675 60 VIA CARATAMA      SAN CLEMENTE, CA 92673

Inspector Information

OSVALDO PARAMO, (213) 202-9854 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Underground Mechanical 6/9/2023 Corrections Issued OSVALDO PARAMO
Excavation/Setback/Form/Re-Bar 6/26/2023 Corrections Issued OSVALDO PARAMO
PLUMBING-Rough 6/26/2023 Partial Approval OSVALDO PARAMO
Underground Mechanical 6/26/2023 Partial Approval OSVALDO PARAMO
Footing/Foundation/Slab 8/9/2023 Corrections Issued ALIZAH MAYAGOITIA
Deputy Reinf. Concrete 8/11/2023 Conditional Approval BRIAN SULLIVAN
Deputy Wood Construction 9/8/2023 Approved OSVALDO PARAMO
Floor/Roof Diaphrgm/Shear Wall 9/8/2023 Corrections Issued OSVALDO PARAMO
Rough-Elec/Plmb/HVAC 9/11/2023 Approved OSVALDO PARAMO
BUILDING-Rough-Frame 9/13/2023 Conditional Approval OSVALDO PARAMO
Floor/Roof Diaphrgm/Shear Wall 9/13/2023 Approved OSVALDO PARAMO
Verify Sprinkler Sign Off 9/13/2023 Approved OSVALDO PARAMO
Interior/Exterior Lathing 9/22/2023 Approved BRIAN SULLIVAN
Shower Pan 9/22/2023 Approved BRIAN SULLIVAN
Insulation 9/25/2023 Approved OSVALDO PARAMO
Interior/Exterior Lathing 9/25/2023 Approved OSVALDO PARAMO
Drywall Nailing 10/2/2023 Approved JOSH MEISTER
Underground Mechanical 10/31/2023 Partial Approval OSVALDO PARAMO
ELECTRICAL-Final 11/30/2023 Approved OSVALDO PARAMO
HVAC-Final 11/30/2023 Approved OSVALDO PARAMO
PLUMBING-Final 11/30/2023 Approved OSVALDO PARAMO
Gas Test 12/7/2023 Approved OSVALDO PARAMO
ELECTRICAL-Final 2/8/2024 Approved OSVALDO PARAMO
Service/Power Release 2/8/2024 Corrections Issued OSVALDO PARAMO
Service/Power Release 3/5/2024 Not Ready for Inspection OSVALDO PARAMO
Final 3/11/2024 Corrections Issued OSVALDO PARAMO
Service/Power Release 3/11/2024 Approved OSVALDO PARAMO
BUILDING-Rough-Frame 3/14/2024 Approved OSVALDO PARAMO
Final 3/14/2024 Conditional Approval OSVALDO PARAMO
Footing/Foundation/Slab 3/14/2024 Approved OSVALDO PARAMO
SGSOV-Seismic Gas S/O Valve 3/14/2024 SGSOV Approved OSVALDO PARAMO
Smoke Detectors 3/14/2024 Approved OSVALDO PARAMO
Final 4/1/2024 OK to Issue CofO OSVALDO PARAMO