13145 W LAKE ST 90066

Certificate Information: 13145 W LAKE ST 90066

Application / Permit
22010-10000-02881
Plan Check / Job No.
B22LA11160
Group
Building
Type
Bldg-New
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Dwelling - Single Family
Work Description
NEW TWO STORY SINGLE FAMILY RESIDENCE WITH ATTACHED GARAGE
Permit Issued
Issued on 9/22/2022
Issuing Office
Current Status
CofO Issued on 12/24/2024
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 6/9/2022 APPLICANT
Assigned to Plan Check Engineer 6/24/2022 MAHNAZ NOURHASHEMI
Corrections Issued 6/29/2022 MAHNAZ NOURHASHEMI
Quality Review Completed 7/6/2022 TEODORO DIAZ RODRIGUEZ
Building Plans Picked Up 7/8/2022 APPLICANT
Plan Check Approved 8/19/2022 MAHNAZ NOURHASHEMI
Issued 9/22/2022 APPLICANT
Permit Finaled 12/24/2024 RICHARD STEINBACH
CofO Issued 12/24/2024 RICHARD STEINBACH
Permit Finaled 12/24/2024 RICHARD STEINBACH

Permit Application Clearance Information

Permit Cleared 7/19/2022 DINAH GARIN
Eng Process Fee Ord 176,300 Cleared 7/21/2022 DINAH GARIN
Sewer availability Cleared 7/21/2022 DINAH GARIN
Specific Plan Cleared 7/27/2022 VALERIA CEJA
Trees in Parkway Cleared 8/4/2022 ADALBERTO VERA
Hydrant and Access approval Cleared 8/5/2022 RUEL COLE
Low Impact Development Cleared 8/8/2022 TA ANH
Roof/Waste drainage to street Cleared 8/9/2022 ANTHONY MAINEZ
GPI Written Notices Cleared 8/19/2022 MAHNAZ NOURHASHEMI
Grading Pre-Inspection Cleared 8/19/2022 MAHNAZ NOURHASHEMI

Contact Information

Contractor Lemette Construction Design; Lic. No.: 1044314-B 107 N REINO RD #206      NEWBURY PARK, CA 91320

Inspector Information

DAKOTA LOW, (310) 914-3895 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Pre-Inspection 12/8/2022 Not Ready for Inspection JESUS RODRIGUEZ
PLUMBING-Rough 5/22/2023 Partial Approval JESUS RODRIGUEZ
Sewer 5/22/2023 Approved JESUS RODRIGUEZ
Footing/Foundation/Slab 5/31/2023 Partial Approval JESUS RODRIGUEZ
Deputy Reinf. Concrete 6/6/2023 Conditional Approval MICHAEL PELHAM
Excavation/Setback/Form/Re-Bar 6/8/2023 Approved JESUS RODRIGUEZ
Footing/Foundation/Slab 6/8/2023 Approved JESUS RODRIGUEZ
Deputy Reinf. Concrete 6/9/2023 Conditional Approval JESUS RODRIGUEZ
Floor/Roof Diaphrgm/Shear Wall 7/13/2023 Partial Approval JESUS RODRIGUEZ
Floor/Roof Diaphrgm/Shear Wall 10/25/2023 Corrections Issued ARAM AVEDISIAN
Floor/Roof Diaphrgm/Shear Wall 10/30/2023 Approved JESUS RODRIGUEZ
Green Building Rough 10/30/2023 Not Ready for Inspection JESUS RODRIGUEZ
Verify Sprinkler Sign Off 10/30/2023 Not Ready for Inspection JESUS RODRIGUEZ
ELECTRICAL-Rough 11/13/2023 Approved JESUS RODRIGUEZ
HVAC-Rough 11/13/2023 Approved JESUS RODRIGUEZ
PLUMBING-Rough 11/13/2023 Approved JESUS RODRIGUEZ
Verify Sprinkler Sign Off 11/13/2023 Approved JESUS RODRIGUEZ
Insulation 11/20/2023 Approved JESUS RODRIGUEZ
Interior/Exterior Lathing 11/20/2023 Approved JESUS RODRIGUEZ
Drywall Nailing 12/6/2023 Approved JESUS RODRIGUEZ
Shower Pan 12/28/2023 Approved JESUS PINEDA
Gas Test 6/12/2024 Approved JESUS RODRIGUEZ
Service/Power Release 6/12/2024 Not Ready for Inspection JESUS RODRIGUEZ
ELECTRICAL-Final 7/1/2024 Approved JESUS RODRIGUEZ
Service/Power Release 7/1/2024 Approved JESUS RODRIGUEZ
BUILDING-Rough-Frame 8/5/2024 Approved JESUS RODRIGUEZ
Final 8/5/2024 Corrections Issued JESUS RODRIGUEZ
Green Building Final 8/5/2024 Corrections Issued JESUS RODRIGUEZ
Green Building Rough 8/5/2024 Approved JESUS RODRIGUEZ
HVAC-Final 8/5/2024 Corrections Issued JESUS RODRIGUEZ
PLUMBING-Final 8/5/2024 Approved JESUS RODRIGUEZ
SGSOV-Seismic Gas S/O Valve 8/5/2024 SGSOV Approved JESUS RODRIGUEZ
Smoke Detectors 8/5/2024 Approved JESUS RODRIGUEZ
Final 12/18/2024 Conditional Approval JESUS RODRIGUEZ
Green Building Final 12/18/2024 Approved JESUS RODRIGUEZ
HVAC-Final 12/18/2024 Approved JESUS RODRIGUEZ