1422 W 29TH ST 90007
Certificate Information: 1422 W 29TH ST 90007
- Application / Permit
- 22010-10000-02874
- Plan Check / Job No.
- B22LA11108
- Group
- Building
- Type
- Bldg-New
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (7) Garage - Private
- Work Description
- **EPLAN** New Detached Garage **CofO pending demo permit for garage built under 1922LA29851** COMPLY WITH DEPARTMENT ORDER effective date 09/25/2007. PERMIT WILL EXPIRE 30 DAYS FROM ISSUANCE DATE.
- Permit Issued
- Issued on 9/13/2022
- Issuing Office
- Current Status
- CofO Issued on 2/27/2023
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 7/11/2022 | APPLICANT |
| Assigned to Plan Check Engineer | 7/12/2022 | JOSEPH RAFOLS |
| Corrections Issued | 7/12/2022 | JOSEPH RAFOLS |
| Applicant returned to address corrections | 8/24/2022 | MINA HABILI |
| Applicant returned to address corrections | 8/31/2022 | JOSEPH RAFOLS |
| Applicant returned to address corrections | 9/3/2022 | GEORGE ALVAREZ |
| Plan Check Approved | 9/7/2022 | GEORGE ALVAREZ |
| Issued | 9/13/2022 | APPLICANT |
| CofO in Progress | 2/25/2023 | ALEJANDRO DE ARTOLA |
| Permit Finaled | 2/27/2023 | DEROLD HAUFF |
| CofO Issued | 2/27/2023 | DEROLD HAUFF |
| Permit Finaled | 2/27/2023 | DEROLD HAUFF |
Permit Application Clearance Information
| CPC | Cleared | 8/17/2022 | LYDIA CHAPMAN |
| HPOZ | Cleared | 8/17/2022 | LYDIA CHAPMAN |
| Roof/Waste drainage to street | Cleared | 8/19/2022 | JEANETTE VONG |
| Eng Process Fee Ord 176,300 | Cleared | 8/22/2022 | JEANETTE VONG |
Contact Information
| Contractor | Owner-Builder | , |
| Engineer | Hwang,, Junho; Lic. No.: S5592 | 815 FAIRVIEW AVE #205 SOUTH PASADENA, CA 91030 |
Inspector Information
| SABAS ALONSO, (213) 202-3468 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Footing/Foundation/Slab | 12/27/2022 | Approved | ALEJANDRO DE ARTOLA |
| METHANE-Barrier | 12/27/2022 | Approved | ALEJANDRO DE ARTOLA |
| METHANE-Barrier | 12/27/2022 | No Access for Inspection | SABAS ALONSO |
| METHANE-Subgrade | 12/27/2022 | Approved | ALEJANDRO DE ARTOLA |
| METHANE-Subgrade | 12/27/2022 | No Access for Inspection | SABAS ALONSO |
| BUILDING-Rough-Frame | 1/5/2023 | Approved | ALEJANDRO DE ARTOLA |
| Green Building Rough | 1/5/2023 | Approved | ALEJANDRO DE ARTOLA |
| METHANE-Rough | 1/5/2023 | Approved | ALEJANDRO DE ARTOLA |
| Drywall Nailing | 1/9/2023 | Approved | ALEJANDRO DE ARTOLA |
| Interior/Exterior Lathing | 1/23/2023 | Approved | ALEJANDRO DE ARTOLA |
| Final | 2/16/2023 | Corrections Issued | ALEJANDRO DE ARTOLA |
| Green Building Final | 2/16/2023 | Approved | ALEJANDRO DE ARTOLA |
| HVAC-Rough | 2/16/2023 | Approved | ALEJANDRO DE ARTOLA |
| SGSOV-Seismic Gas S/O Valve | 2/16/2023 | SGSOV Not Required | ALEJANDRO DE ARTOLA |
| Service/Power Release | 2/16/2023 | Approved | ALEJANDRO DE ARTOLA |
| Smoke Detectors | 2/16/2023 | Approved | ALEJANDRO DE ARTOLA |
| Wood Frame | 2/16/2023 | Approved | ALEJANDRO DE ARTOLA |
| ELECTRICAL-Final | 2/22/2023 | Approved | ALEJANDRO DE ARTOLA |
| Final | 2/22/2023 | Corrections Issued | ALEJANDRO DE ARTOLA |
| HVAC-Final | 2/22/2023 | Approved | ALEJANDRO DE ARTOLA |
| PLUMBING-Final | 2/22/2023 | Approved | ALEJANDRO DE ARTOLA |
| Final | 2/24/2023 | OK to Issue CofO | ALEJANDRO DE ARTOLA |