11700 W EXPOSITION BLVD 90064
Certificate Information: 11700 W EXPOSITION BLVD 90064
- Application / Permit
- 22010-10000-02873
- Plan Check / Job No.
- B22LA11107
- Group
- Building
- Type
- Bldg-New
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Dwelling - Single Family
- Work Description
- ePlan NEW 2-STORY SFD WITH ATTACHED 2-CAR GARAGE
- Permit Issued
- Issued on 8/2/2023
- Issuing Office
- Current Status
- Issued on 8/2/2023
- Certificate of Occupancy
- Pending More Information
Permit Application Status History
| Submitted | 6/9/2022 | APPLICANT |
| Assigned to Plan Check Engineer | 7/14/2022 | ADRIANA LOPEZ |
| Corrections Issued | 8/2/2022 | ADRIANA LOPEZ |
| Quality Review Completed | 8/3/2022 | GARO TELMI |
| Applicant returned to address corrections | 6/4/2023 | ADRIANA LOPEZ |
| Applicant returned to address corrections | 7/5/2023 | ADRIANA LOPEZ |
| Applicant returned to address corrections | 7/19/2023 | ADRIANA LOPEZ |
| Plan Check Approved | 7/26/2023 | ADRIANA LOPEZ |
| Plan Check Approved | 8/1/2023 | ADRIANA LOPEZ |
| Issued | 8/2/2023 | APPLICANT |
Permit Application Clearance Information
| Address approval | Cleared | 9/17/2022 | STEVE MELGAR |
| Hydrant and Access approval | Cleared | 10/7/2022 | JOHN CONNEALLY |
| Eng Process Fee Ord 176,300 | Cleared | 11/3/2022 | STEVE MELGAR |
| Sewer availability | Cleared | 11/3/2022 | STEVE MELGAR |
| Frnt yard landscape/Water mgmt | Cleared | 11/17/2022 | ANACANY HURTADO |
| Miscellaneous | Cleared | 11/17/2022 | ANACANY HURTADO |
| Low Impact Development | Cleared | 12/2/2022 | ROGELIO CORTES |
| Roof/Waste drainage to street | Cleared | 12/8/2022 | STEVE MELGAR |
| Highway dedication | Cleared | 3/7/2023 | AHMED AMARRAGY |
| ZI | Cleared | 3/31/2023 | KYLE WINSTON |
| Specific Plan | Cleared | 4/13/2023 | FREDDY GARCIA |
| Specific Plan | Cleared | 4/13/2023 | FREDDY GARCIA |
Contact Information
| Contractor | Adu Rc Builders; Lic. No.: 1080967-B | , |
| Contractor | Ca Construction Group Inc; Lic. No.: 1080967-B | , |
| Engineer | Shahbaz,, Shant Pierre; Lic. No.: C93079 | 15445 VENTURA BLVD #63 SHERMAN OAKS, CA 91403 |
Inspector Information
| ANTHONY EGSON, (310) 914-3893 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Sewer | 9/20/2023 | Approved | BEN MOLSTAD |
| Excavation/Setback/Form/Re-Bar | 10/4/2023 | Corrections Issued | MICHAEL PELHAM |
| Excavation/Setback/Form/Re-Bar | 11/3/2023 | Approved | MICHAEL PELHAM |
| Footing/Foundation/Slab | 11/3/2023 | Approved | MICHAEL PELHAM |
| Wood Frame | 11/20/2023 | Partial Approval | BEN MOLSTAD |
| BUILDING-Rough-Frame | 1/23/2024 | Not Ready for Inspection | BEN MOLSTAD |
| Floor/Roof Diaphrgm/Shear Wall | 1/23/2024 | Approved | BEN MOLSTAD |
| Green Building Rough | 1/23/2024 | Not Ready for Inspection | BEN MOLSTAD |
| Verify Sprinkler Sign Off | 1/23/2024 | Not Ready for Inspection | BEN MOLSTAD |
| ELECTRICAL-Rough | 2/15/2024 | Corrections Issued | ASHLEY THOMPSON |
| Interior/Exterior Lathing | 2/15/2024 | Partial Approval | ASHLEY THOMPSON |
| PLUMBING-Rough | 2/15/2024 | Corrections Issued | ASHLEY THOMPSON |
| Underground Mechanical | 2/15/2024 | Partial Approval | ASHLEY THOMPSON |
| BUILDING-Rough-Frame | 3/6/2024 | Corrections Issued | ASHLEY THOMPSON |
| ELECTRICAL-Rough | 3/6/2024 | Approved | ASHLEY THOMPSON |
| Green Building Rough | 3/6/2024 | Not Ready for Inspection | ASHLEY THOMPSON |
| HVAC-Final | 3/6/2024 | Not Ready for Inspection | ASHLEY THOMPSON |
| HVAC-Rough | 3/6/2024 | Approved | ASHLEY THOMPSON |
| PLUMBING-Rough | 3/6/2024 | Approved | ASHLEY THOMPSON |
| Verify Sprinkler Sign Off | 3/6/2024 | Approved | ASHLEY THOMPSON |
| BUILDING-Rough-Frame | 3/13/2024 | Approved | TEMISTOCLES CAAL |
| Green Building Rough | 3/13/2024 | Approved | TEMISTOCLES CAAL |
| Insulation | 3/22/2024 | Approved | ASHLEY THOMPSON |
| Deputy Wood Construction | 3/27/2024 | Partial Approval | ASHLEY THOMPSON |
| Drywall Nailing | 4/2/2024 | Approved | ASHLEY THOMPSON |
| Shower Pan | 4/2/2024 | Approved | ASHLEY THOMPSON |
| Interior/Exterior Lathing | 4/23/2024 | Approved | OGANES TARAKHCHYAN |
| Final | 7/11/2024 | Corrections Issued | KIRK SANDERS |
| Underground Mechanical | 7/11/2024 | Conditional Approval | KIRK SANDERS |
| ELECTRICAL-Final | 9/20/2024 | Corrections Issued | KIRK SANDERS |
| Final | 9/20/2024 | Corrections Issued | KIRK SANDERS |
| Green Building Final | 9/20/2024 | Not Ready for Inspection | KIRK SANDERS |
| HVAC-Final | 9/20/2024 | Corrections Issued | KIRK SANDERS |
| PLUMBING-Final | 9/20/2024 | Corrections Issued | KIRK SANDERS |
| SGSOV-Seismic Gas S/O Valve | 9/20/2024 | SGSOV Not Ready | KIRK SANDERS |
| Service/Power Release | 9/20/2024 | Not Ready for Inspection | KIRK SANDERS |
| Smoke Detectors | 9/20/2024 | Corrections Issued | KIRK SANDERS |
| Special/Order Compliance | 4/4/2025 | Corrections Issued | KIRK SANDERS |
| ELECTRICAL-Final | 10/16/2025 | Approved | MICHAEL ALLEN |
| Service/Power Release | 10/16/2025 | Not Ready for Inspection | MICHAEL ALLEN |
| Service/Power Release | 12/2/2025 | Approved | ANDREW NAVE |