18654 W RUNNYMEDE ST 91335
Certificate Information: 18654 W RUNNYMEDE ST 91335
- Application / Permit
- 22010-10000-02867
- Plan Check / Job No.
- B22LA11043
- Group
- Building
- Type
- Bldg-New
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Dwelling - Single Family
- Work Description
- 2-STORY SFD Per SB9 Second-Unit Development. Sprinklered.
- Permit Issued
- Issued on 7/18/2024
- Issuing Office
- Metro
- Current Status
- CofO Issued on 7/18/2025
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 6/8/2022 | APPLICANT |
| Assigned to Plan Check Engineer | 6/24/2022 | KHEDER ALRAZAA |
| Plans on Hold | 6/28/2022 | ALBERT SERVIN |
| Hold Released | 8/24/2022 | ALBERT SERVIN |
| Corrections Issued | 8/24/2022 | ALBERT SERVIN |
| Quality Review Completed | 9/2/2022 | KEN GILL |
| Building Plans Picked Up | 9/20/2022 | APPLICANT |
| Plan Check Approved | 7/12/2024 | KHEDER ALRAZAA |
| Issued | 7/18/2024 | APPLICANT |
| CofO in Progress | 6/9/2025 | ARUTYUN MADATYAN |
| CofO Issued | 7/18/2025 | DANIEL ORRANTE |
| Permit Finaled | 7/18/2025 | DANIEL ORRANTE |
Permit Application Clearance Information
| Hydrant and Access approval | Cleared | 1/22/2023 | KURT CORRAL |
| Address approval | Cleared | 7/12/2023 | TAL SHEMEN |
| Eng Process Fee Ord 176,300 | Cleared | 7/26/2023 | TAL SHEMEN |
| Sewer availability | Cleared | 7/26/2023 | TAL SHEMEN |
| Construction near power lines | Cleared | 2/14/2024 | OSCAR CASTRO |
| Senate Bill 9 | Cleared | 5/8/2024 | SPENCER WEJROWSKI |
| Low Impact Development | Cleared | 6/25/2024 | MARCO SANCHEZ |
| Roof/Waste drainage to street | Cleared | 6/28/2024 | BRYAN GODINEZ |
Contact Information
| Contractor | Owner-Builder | , |
| Engineer | Castillo,, Margarito; Lic. No.: S4808 | 1205 PINE AVE SUITE 201 LONG BEACH, CA 90813 |
Inspector Information
| ARUTYUN MADATYAN, (818) 774-4307 | Office Hours: 7:00-8:00 AM MON-FRI |
| JUAN ALVARADO, (818) 774-4307 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Pre-Inspection | 9/16/2024 | Approved | JEFFREY BULL |
| PLUMBING-Rough | 11/8/2024 | Partial Approval | ARUTYUN MADATYAN |
| Excavation/Setback/Form/Re-Bar | 11/15/2024 | Approved | ARUTYUN MADATYAN |
| Floor/Roof Diaphrgm/Shear Wall | 12/9/2024 | Corrections Issued | ARUTYUN MADATYAN |
| Floor/Roof Diaphrgm/Shear Wall | 12/13/2024 | Partial Approval | ARUTYUN MADATYAN |
| BUILDING-Rough-Frame | 1/14/2025 | Not Ready for Inspection | JEFFREY HARTLINE |
| ELECTRICAL-Rough | 1/14/2025 | Approved | JEFFREY HARTLINE |
| Floor/Roof Diaphrgm/Shear Wall | 1/14/2025 | Partial Approval | JEFFREY HARTLINE |
| Green Building Rough | 1/14/2025 | Not Ready for Inspection | JEFFREY HARTLINE |
| HVAC-Rough | 1/14/2025 | Approved | JEFFREY HARTLINE |
| PLUMBING-Rough | 1/14/2025 | Approved | JEFFREY HARTLINE |
| Verify Sprinkler Sign Off | 1/14/2025 | Not Ready for Inspection | JEFFREY HARTLINE |
| Interior/Exterior Lathing | 1/27/2025 | Not Ready for Inspection | ARUTYUN MADATYAN |
| BUILDING-Rough-Frame | 2/3/2025 | Approved | ARUTYUN MADATYAN |
| Floor/Roof Diaphrgm/Shear Wall | 2/3/2025 | Approved | ARUTYUN MADATYAN |
| Green Building Rough | 2/3/2025 | Approved | ARUTYUN MADATYAN |
| Interior/Exterior Lathing | 2/3/2025 | Partial Approval | ARUTYUN MADATYAN |
| Verify Sprinkler Sign Off | 2/3/2025 | Approved | ARUTYUN MADATYAN |
| Insulation | 2/6/2025 | Approved | ARUTYUN MADATYAN |
| Interior/Exterior Lathing | 2/10/2025 | Approved | JUAN ALVARADO |
| Shower Pan | 2/10/2025 | Approved | JUAN ALVARADO |
| Drywall Nailing | 2/12/2025 | Approved | ARUTYUN MADATYAN |
| Underground Mechanical | 3/10/2025 | Partial Approval | ARUTYUN MADATYAN |
| ELECTRICAL-Final | 5/29/2025 | Approved | ARUTYUN MADATYAN |
| Final | 5/29/2025 | Corrections Issued | ARUTYUN MADATYAN |
| Footing/Foundation/Slab | 5/29/2025 | Approved | ARUTYUN MADATYAN |
| Green Building Final | 5/29/2025 | Not Ready for Inspection | ARUTYUN MADATYAN |
| HVAC-Final | 5/29/2025 | Approved | ARUTYUN MADATYAN |
| PLUMBING-Final | 5/29/2025 | Approved | ARUTYUN MADATYAN |
| SGSOV-Seismic Gas S/O Valve | 5/29/2025 | SGSOV Approved | ARUTYUN MADATYAN |
| Service/Power Release | 5/29/2025 | Not Ready for Inspection | ARUTYUN MADATYAN |
| Smoke Detectors | 5/29/2025 | Approved | ARUTYUN MADATYAN |
| Final | 6/3/2025 | Not Ready for Inspection | ARUTYUN MADATYAN |
| Green Building Final | 6/3/2025 | Approved | ARUTYUN MADATYAN |
| Service/Power Release | 6/3/2025 | Approved | ARUTYUN MADATYAN |
| Final | 6/9/2025 | OK to Issue CofO | ARUTYUN MADATYAN |