18654 W RUNNYMEDE ST 91335

Certificate Information: 18654 W RUNNYMEDE ST 91335

Application / Permit
22010-10000-02867
Plan Check / Job No.
B22LA11043
Group
Building
Type
Bldg-New
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Dwelling - Single Family
Work Description
2-STORY SFD Per SB9 Second-Unit Development. Sprinklered.
Permit Issued
Issued on 7/18/2024
Issuing Office
Metro
Current Status
CofO Issued on 7/18/2025
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 6/8/2022 APPLICANT
Assigned to Plan Check Engineer 6/24/2022 KHEDER ALRAZAA
Plans on Hold 6/28/2022 ALBERT SERVIN
Hold Released 8/24/2022 ALBERT SERVIN
Corrections Issued 8/24/2022 ALBERT SERVIN
Quality Review Completed 9/2/2022 KEN GILL
Building Plans Picked Up 9/20/2022 APPLICANT
Plan Check Approved 7/12/2024 KHEDER ALRAZAA
Issued 7/18/2024 APPLICANT
CofO in Progress 6/9/2025 ARUTYUN MADATYAN
CofO Issued 7/18/2025 DANIEL ORRANTE
Permit Finaled 7/18/2025 DANIEL ORRANTE

Permit Application Clearance Information

Hydrant and Access approval Cleared 1/22/2023 KURT CORRAL
Address approval Cleared 7/12/2023 TAL SHEMEN
Eng Process Fee Ord 176,300 Cleared 7/26/2023 TAL SHEMEN
Sewer availability Cleared 7/26/2023 TAL SHEMEN
Construction near power lines Cleared 2/14/2024 OSCAR CASTRO
Senate Bill 9 Cleared 5/8/2024 SPENCER WEJROWSKI
Low Impact Development Cleared 6/25/2024 MARCO SANCHEZ
Roof/Waste drainage to street Cleared 6/28/2024 BRYAN GODINEZ

Contact Information

Contractor Owner-Builder       ,
Engineer Castillo,, Margarito; Lic. No.: S4808 1205 PINE AVE   SUITE 201    LONG BEACH, CA 90813

Inspector Information

ARUTYUN MADATYAN, (818) 774-4307 Office Hours: 7:00-8:00 AM MON-FRI
JUAN ALVARADO, (818) 774-4307 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Pre-Inspection 9/16/2024 Approved JEFFREY BULL
PLUMBING-Rough 11/8/2024 Partial Approval ARUTYUN MADATYAN
Excavation/Setback/Form/Re-Bar 11/15/2024 Approved ARUTYUN MADATYAN
Floor/Roof Diaphrgm/Shear Wall 12/9/2024 Corrections Issued ARUTYUN MADATYAN
Floor/Roof Diaphrgm/Shear Wall 12/13/2024 Partial Approval ARUTYUN MADATYAN
BUILDING-Rough-Frame 1/14/2025 Not Ready for Inspection JEFFREY HARTLINE
ELECTRICAL-Rough 1/14/2025 Approved JEFFREY HARTLINE
Floor/Roof Diaphrgm/Shear Wall 1/14/2025 Partial Approval JEFFREY HARTLINE
Green Building Rough 1/14/2025 Not Ready for Inspection JEFFREY HARTLINE
HVAC-Rough 1/14/2025 Approved JEFFREY HARTLINE
PLUMBING-Rough 1/14/2025 Approved JEFFREY HARTLINE
Verify Sprinkler Sign Off 1/14/2025 Not Ready for Inspection JEFFREY HARTLINE
Interior/Exterior Lathing 1/27/2025 Not Ready for Inspection ARUTYUN MADATYAN
BUILDING-Rough-Frame 2/3/2025 Approved ARUTYUN MADATYAN
Floor/Roof Diaphrgm/Shear Wall 2/3/2025 Approved ARUTYUN MADATYAN
Green Building Rough 2/3/2025 Approved ARUTYUN MADATYAN
Interior/Exterior Lathing 2/3/2025 Partial Approval ARUTYUN MADATYAN
Verify Sprinkler Sign Off 2/3/2025 Approved ARUTYUN MADATYAN
Insulation 2/6/2025 Approved ARUTYUN MADATYAN
Interior/Exterior Lathing 2/10/2025 Approved JUAN ALVARADO
Shower Pan 2/10/2025 Approved JUAN ALVARADO
Drywall Nailing 2/12/2025 Approved ARUTYUN MADATYAN
Underground Mechanical 3/10/2025 Partial Approval ARUTYUN MADATYAN
ELECTRICAL-Final 5/29/2025 Approved ARUTYUN MADATYAN
Final 5/29/2025 Corrections Issued ARUTYUN MADATYAN
Footing/Foundation/Slab 5/29/2025 Approved ARUTYUN MADATYAN
Green Building Final 5/29/2025 Not Ready for Inspection ARUTYUN MADATYAN
HVAC-Final 5/29/2025 Approved ARUTYUN MADATYAN
PLUMBING-Final 5/29/2025 Approved ARUTYUN MADATYAN
SGSOV-Seismic Gas S/O Valve 5/29/2025 SGSOV Approved ARUTYUN MADATYAN
Service/Power Release 5/29/2025 Not Ready for Inspection ARUTYUN MADATYAN
Smoke Detectors 5/29/2025 Approved ARUTYUN MADATYAN
Final 6/3/2025 Not Ready for Inspection ARUTYUN MADATYAN
Green Building Final 6/3/2025 Approved ARUTYUN MADATYAN
Service/Power Release 6/3/2025 Approved ARUTYUN MADATYAN
Final 6/9/2025 OK to Issue CofO ARUTYUN MADATYAN