2641 S MILITARY AVE 90064

Certificate Information: 2641 S MILITARY AVE 90064

Application / Permit
22010-10000-02853
Plan Check / Job No.
B22LA10994
Group
Building
Type
Bldg-Alter/Repair
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Accessory Dwelling Unit
Work Description
ePlan : Conversion of existing 460 SF Garage to a new Accessory Dwelling Unit per CA Govt Code 65852.2(e)(1)(A)
Permit Issued
Issued on 9/8/2022
Issuing Office
Current Status
CofO Issued on 11/18/2022
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 6/9/2022 APPLICANT
Assigned to Plan Check Engineer 6/14/2022 HANS SANTIAGO
Plan Check Approved 9/7/2022 ANDREW SANTIAGO
Issued 9/8/2022 APPLICANT
CofO in Progress 11/16/2022 JOHNNY MIRANDA
Permit Finaled 11/18/2022 DANIEL ORRANTE
CofO Issued 11/18/2022 DANIEL ORRANTE
Permit Finaled 11/18/2022 DANIEL ORRANTE

Permit Application Clearance Information

Specific Plan Cleared 7/13/2022 CONNIE CHAUV
Address approval Cleared 7/14/2022 DINAH GARIN
Sewer availability Cleared 7/14/2022 DINAH GARIN
Eng Process Fee Ord 176,300 Cleared 7/19/2022 DINAH GARIN
Specific Plan Cleared 8/8/2022 PEDRO AYALA
Grading Pre-Inspection Cleared 9/7/2022 ANDREW SANTIAGO

Contact Information

Contractor Owner-Builder       ,

Inspector Information

KIRK SANDERS, (310) 914-3896 Office Hours: 7:00-8:00 AM MON-FRI
ARAM AVEDISIAN, (310) 914-3896 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

BUILDING-Rough-Frame 9/14/2022 Approved JOHNNY MIRANDA
ELECTRICAL-Rough 9/14/2022 Approved JOHNNY MIRANDA
Floor/Roof Diaphrgm/Shear Wall 9/14/2022 Approved JOHNNY MIRANDA
HVAC-Rough 9/14/2022 Approved JOHNNY MIRANDA
MERV13>=Rough 9/14/2022 Approved JOHNNY MIRANDA
PLUMBING-Rough 9/14/2022 Approved JOHNNY MIRANDA
Drywall Nailing 9/16/2022 Approved JOHNNY MIRANDA
ELECTRICAL-Final 10/11/2022 Approved JOHNNY MIRANDA
Final 10/11/2022 Corrections Issued JOHNNY MIRANDA
HVAC-Final 10/11/2022 Corrections Issued JOHNNY MIRANDA
MERV13>=Final 10/11/2022 Approved JOHNNY MIRANDA
PLUMBING-Final 10/11/2022 Approved JOHNNY MIRANDA
SGSOV-Seismic Gas S/O Valve 10/11/2022 SGSOV Approved JOHNNY MIRANDA
Smoke Detectors 10/11/2022 Approved JOHNNY MIRANDA
Final 11/16/2022 OK to Issue CofO JOHNNY MIRANDA