3227 S FAY AVE 90034
Certificate Information: 3227 S FAY AVE 90034
- Application / Permit
- 22010-10000-02851
- Plan Check / Job No.
- B22LA10973
- Group
- Building
- Type
- Bldg-New
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Accessory Dwelling Unit
- Work Description
- ePlan PROPOSED NEW DETACHED 2-STORY ADU (1,192 SF, 32' X 24.25') WITH AN ENTRANCE PORCH (78SF) AND UNCOVERED BALCONY (75 SF)
- Permit Issued
- Issued on 3/18/2023
- Issuing Office
- Current Status
- CofO Issued on 11/4/2025
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 6/10/2022 | APPLICANT |
| Assigned to Plan Check Engineer | 7/14/2022 | NGHI SU |
| Corrections Issued | 7/20/2022 | NGHI SU |
| Quality Review Completed | 7/29/2022 | FARUK SEZER |
| Applicant returned to address corrections | 2/23/2023 | NGHI SU |
| Plan Check Approved | 3/14/2023 | NGHI SU |
| Issued | 3/18/2023 | APPLICANT |
| CofO in Progress | 10/24/2025 | EVAN COOPER |
| Permit Finaled | 11/4/2025 | RICHARD STEINBACH |
| CofO Issued | 11/4/2025 | RICHARD STEINBACH |
| Permit Finaled | 11/4/2025 | RICHARD STEINBACH |
Permit Application Clearance Information
| Address approval | Cleared | 9/8/2022 | AMAAN MALIK |
| Eng Process Fee Ord 176,300 | Cleared | 9/13/2022 | AMAAN MALIK |
| Sewer availability | Cleared | 9/13/2022 | AMAAN MALIK |
| Construction near power lines | Cleared | 10/1/2022 | RIDWAN HARDY |
| Zoning Information File | Cleared | 11/7/2022 | DANIEL SCHNEIDEREIT |
| Low Impact Development | Cleared | 11/9/2022 | ANTHONY VARGAS |
| Roof/Waste drainage to street | Cleared | 11/15/2022 | AMAAN MALIK |
Contact Information
| Contractor | Owner-Builder | , |
| Engineer | Dorta,, Michael Rohrs; Lic. No.: C72538 | 2445 VIA SONOMA PALOS VERDES ESTATES, CA 90274 |
Inspector Information
| WILBER ROSALES, (310) 914-3892 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Excavation/Setback/Form/Re-Bar | 4/1/2024 | Not Ready for Inspection | MEL KHACHATOURIAN |
| Footing/Foundation/Slab | 4/1/2024 | Not Ready for Inspection | MEL KHACHATOURIAN |
| Excavation/Setback/Form/Re-Bar | 4/3/2024 | Partial Approval | MEL KHACHATOURIAN |
| PLUMBING-Rough | 4/25/2024 | Partial Approval | MEL KHACHATOURIAN |
| Sewer | 4/25/2024 | Approved | MEL KHACHATOURIAN |
| Wood Frame | 4/30/2024 | Partial Approval | OGANES TARAKHCHYAN |
| Floor/Roof Diaphrgm/Shear Wall | 5/3/2024 | Partial Approval | MEL KHACHATOURIAN |
| Insulation | 5/3/2024 | Partial Approval | MEL KHACHATOURIAN |
| Light Gage Steel Frame | 5/3/2024 | Approved | MEL KHACHATOURIAN |
| Wood Frame | 5/3/2024 | Partial Approval | MEL KHACHATOURIAN |
| Floor/Roof Diaphrgm/Shear Wall | 5/29/2024 | Partial Approval | MEL KHACHATOURIAN |
| Deputy Wood Construction | 7/23/2024 | Approved | SEAN HAUPT |
| Floor/Roof Diaphrgm/Shear Wall | 7/29/2024 | Approved | MEL KHACHATOURIAN |
| ELECTRICAL-Rough | 9/20/2024 | Partial Approval | ARAM AVEDISIAN |
| PLUMBING-Rough | 9/20/2024 | Corrections Issued | ARAM AVEDISIAN |
| PLUMBING-Rough | 9/30/2024 | Approved | ARAM AVEDISIAN |
| Underground Mechanical | 9/30/2024 | Partial Approval | ARAM AVEDISIAN |
| Wood Frame | 9/30/2024 | Corrections Issued | ARAM AVEDISIAN |
| Wood Frame | 10/2/2024 | Partial Approval | MEL KHACHATOURIAN |
| BUILDING-Rough-Frame | 10/28/2024 | Approved | MEL KHACHATOURIAN |
| Green Building Rough | 10/28/2024 | Approved | MEL KHACHATOURIAN |
| HVAC-Rough | 10/28/2024 | Approved | MEL KHACHATOURIAN |
| Insulation | 11/13/2024 | Approved | MEL KHACHATOURIAN |
| Interior/Exterior Lathing | 11/13/2024 | Partial Approval | MEL KHACHATOURIAN |
| Shower Pan | 11/13/2024 | Approved | MEL KHACHATOURIAN |
| Drywall Nailing | 11/20/2024 | Approved | MEL KHACHATOURIAN |
| Interior/Exterior Lathing | 11/27/2024 | Approved | MEL KHACHATOURIAN |
| ELECTRICAL-Final | 10/15/2025 | Corrections Issued | EVAN COOPER |
| HVAC-Final | 10/15/2025 | Corrections Issued | EVAN COOPER |
| PLUMBING-Final | 10/15/2025 | Corrections Issued | EVAN COOPER |
| Service/Power Release | 10/15/2025 | Not Ready for Inspection | EVAN COOPER |
| ELECTRICAL-Final | 10/22/2025 | Corrections Issued | MICHAEL ALLEN |
| Final | 10/22/2025 | Not Ready for Inspection | MICHAEL ALLEN |
| Footing/Foundation/Slab | 10/22/2025 | Approved | MICHAEL ALLEN |
| Gas Test | 10/22/2025 | Approved | MICHAEL ALLEN |
| Green Building Final | 10/22/2025 | Approved | MICHAEL ALLEN |
| HVAC-Final | 10/22/2025 | Approved | MICHAEL ALLEN |
| PLUMBING-Final | 10/22/2025 | Approved | MICHAEL ALLEN |
| SGSOV-Seismic Gas S/O Valve | 10/22/2025 | SGSOV Approved | MICHAEL ALLEN |
| Service/Power Release | 10/22/2025 | Not Ready for Inspection | MICHAEL ALLEN |
| Smoke Detectors | 10/22/2025 | Approved | MICHAEL ALLEN |
| Final | 10/24/2025 | OK to Issue CofO | EVAN COOPER |
| Service/Power Release | 10/24/2025 | Approved | EVAN COOPER |