226 W 87TH ST 1-20 90003

Certificate Information: 226 W 87TH ST 1-20 90003

Application / Permit
22010-10000-02815
Plan Check / Job No.
B22LA10761
Group
Building
Type
Bldg-New
Sub-Type
Apartment
Primary Use
(5) Apartment
Work Description
NEW 3 STORY 20 UNITS (100% AFFORDABLE HOUSING) APARTMENT TO INCLUDE 3 STORY TYPE VA APARTMENT, TIER 3 (TIER INCREASED TO 4 WITH 100% AFFORDABLE) TOC WITH BASE INCENTIVES ONLY
Permit Issued
Issued on 9/11/2023
Issuing Office
Current Status
CofO Issued on 10/17/2025
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 6/6/2022 APPLICANT
Assigned to Plan Check Engineer 6/9/2022 MANUEL MONTUFAR
Corrections Issued 6/23/2022 MANUEL MONTUFAR
Quality Review Completed 6/27/2022 EUGENE BARBEAU
Applicant returned to address corrections 9/20/2022 MANUEL MONTUFAR
Applicant returned to address corrections 9/28/2022 MANUEL MONTUFAR
Applicant returned to address corrections 8/10/2023 MANUEL MONTUFAR
Plan Check Approved 8/18/2023 MANUEL MONTUFAR
Issued 9/11/2023 APPLICANT
CofO in Progress 10/17/2025 RAFAEL ESPINOZA
Permit Finaled 10/17/2025 RAFAEL ESPINOZA
CofO Issued 10/17/2025 RAFAEL ESPINOZA
Permit Finaled 10/17/2025 RAFAEL ESPINOZA

Permit Application Clearance Information

Address approval Cleared 6/30/2022 JEANETTE VONG
Permit Cleared 6/30/2022 JEANETTE VONG
Trees in Parkway Cleared 7/6/2022 ADALBERTO VERA
Hydrant and Access approval Cleared 10/1/2022 RUEL COLE
Frnt yard landscape/Water mgmt Cleared 1/24/2023 KENTON TRINH
Miscellaneous Cleared 1/24/2023 KENTON TRINH
Opn space landscape/Water mgmt Cleared 1/24/2023 KENTON TRINH
Low Impact Development Cleared 1/30/2023 AMMAR ELTAWIL
Density Bonus 12.22.A.31 Cleared 2/22/2023 KENNETH LE
SB8 RUD Cleared 2/22/2023 KENNETH LE
Eng Process Fee Ord 176,300 Cleared 3/9/2023 JEANETTE VONG
Sewer availability Cleared 3/9/2023 JEANETTE VONG
Roof/Waste drainage to street Cleared 3/16/2023 JEANETTE VONG
DAS Clearance Cleared 3/17/2023 MANUEL MONTUFAR
Construction near power lines Cleared 4/20/2023 RIDWAN HARDY
Green Code Cleared 5/18/2023 MANUEL MONTUFAR
Fire Marshal Fire Life Safety Cleared 6/6/2023 SARAH ZHANG

Contact Information

Contractor Owner-Builder       ,
Engineer Chatsky,, German; Lic. No.: C84153 3876 HUNTERS GROVE CT      MOORPARK, CA 93021
Engineer Smith,, Melvin Bruce; Lic. No.: GE2673 2165 N MARVEL AVE      SIMI VALLEY, CA 93065

Inspector Information

No Data Available.

Pending Inspections

No Data Available.

Inspection Request History

Excavation/Setback/Form/Re-Bar 11/13/2023 Partial Approval JAMES POWERS
Footing/Foundation/Slab 11/13/2023 Partial Approval JAMES POWERS
Floor/Roof Diaphrgm/Shear Wall 1/23/2024 Partial Approval LARRY ARNICK
Floor/Roof Diaphrgm/Shear Wall 2/21/2024 Partial Approval RICARDO ROBLES
Green Building Rough 2/21/2024 Not Ready for Inspection RICARDO ROBLES
Verify Sprinkler Sign Off 2/21/2024 Not Ready for Inspection RICARDO ROBLES
Floor/Roof Diaphrgm/Shear Wall 3/12/2024 Partial Approval RAFAEL ESPINOZA
Wood Frame 3/20/2024 Partial Approval RAFAEL ESPINOZA
Floor/Roof Diaphrgm/Shear Wall 4/4/2024 Partial Approval JAMES POWERS
Green Building Rough 4/4/2024 Approved JAMES POWERS
Interior/Exterior Lathing 4/4/2024 Not Ready for Inspection JAMES POWERS
Verify Sprinkler Sign Off 4/4/2024 Not Ready for Inspection JAMES POWERS
Wood Frame 4/4/2024 Not Ready for Inspection JAMES POWERS
Drywall Nailing 5/23/2024 Partial Inspection RAFAEL ESPINOZA
Pre-Inspection 6/17/2024 Partial Inspection RAFAEL ESPINOZA
Wood Frame 6/20/2024 Corrections Issued RAFAEL ESPINOZA
Wood Frame 6/21/2024 Partial Approval RAFAEL ESPINOZA
Insulation 6/27/2024 Partial Approval RAFAEL ESPINOZA
Verify Sprinkler Sign Off 7/18/2024 Not Ready for Inspection RAFAEL ESPINOZA
Wood Frame 7/18/2024 Corrections Issued RAFAEL ESPINOZA
Interior/Exterior Lathing 7/22/2024 Partial Approval RAFAEL ESPINOZA
Verify Sprinkler Sign Off 7/22/2024 Not Ready for Inspection RAFAEL ESPINOZA
Wood Frame 7/26/2024 Partial Approval DANIEL VARNUM
Insulation 7/29/2024 Partial Approval RAFAEL ESPINOZA
Interior/Exterior Lathing 7/29/2024 Partial Approval RAFAEL ESPINOZA
Insulation 8/12/2024 Partial Approval RAFAEL ESPINOZA
Wood Frame 8/12/2024 Partial Approval RAFAEL ESPINOZA
Insulation 8/16/2024 Partial Approval RAFAEL ESPINOZA
Special/Order Compliance 8/16/2024 Partial Inspection RAFAEL ESPINOZA
Wood Frame 8/16/2024 Partial Approval RAFAEL ESPINOZA
Deputy Wood Construction 8/26/2024 Conditional Approval RAFAEL ESPINOZA
Floor/Roof Diaphrgm/Shear Wall 8/26/2024 Partial Approval RAFAEL ESPINOZA
Verify Sprinkler Sign Off 8/26/2024 Not Ready for Inspection RAFAEL ESPINOZA
Interior/Exterior Lathing 9/6/2024 Approved JAMES POWERS
Insulation 9/13/2024 Partial Approval RAFAEL ESPINOZA
Drywall Nailing 10/18/2024 Partial Approval RAFAEL ESPINOZA
Interior/Exterior Lathing 10/18/2024 Corrections Issued RAFAEL ESPINOZA
Drywall Nailing 10/31/2024 Partial Approval RAFAEL CORTES
Drywall Nailing 11/6/2024 Not Ready for Inspection RAFAEL CORTES
Drywall Nailing 11/8/2024 Partial Approval RAFAEL CORTES
Pre-Inspection 1/13/2025 Approved RAFAEL CORTES
Pre-Inspection 3/26/2025 Partial Inspection RAFAEL ESPINOZA
Special/Order Compliance 3/26/2025 Partial Approval RAFAEL ESPINOZA
Pre-Inspection 4/4/2025 Corrections Issued RAFAEL ESPINOZA
Final 8/15/2025 Partial Inspection RAFAEL ESPINOZA
Footing/Foundation/Slab 8/15/2025 Not Ready for Inspection RAFAEL ESPINOZA
Green Building Final 8/15/2025 Approved RAFAEL ESPINOZA
SGSOV-Seismic Gas S/O Valve 8/15/2025 SGSOV Approved RAFAEL ESPINOZA
Smoke Detectors 8/15/2025 Approved RAFAEL ESPINOZA
Verify Sprinkler Sign Off 8/15/2025 Approved RAFAEL ESPINOZA
Wood Frame 8/15/2025 Not Ready for Inspection RAFAEL ESPINOZA
Final 10/17/2025 OK to Issue CofO RAFAEL ESPINOZA
Footing/Foundation/Slab 10/17/2025 Approved RAFAEL ESPINOZA
Wood Frame 10/17/2025 Approved RAFAEL ESPINOZA