- NEW 3 STORY 20 UNITS (100% AFFORDABLE HOUSING) APARTMENT TO INCLUDE 3 STORY TYPE VA APARTMENT, TIER 3 (TIER INCREASED TO 4 WITH 100% AFFORDABLE) TOC WITH BASE INCENTIVES ONLY
- Permit Issued
- Issued on 9/11/2023
- Issuing Office
- Current Status
- CofO Issued on 10/17/2025
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 6/6/2022 | APPLICANT |
| Assigned to Plan Check Engineer | 6/9/2022 | MANUEL MONTUFAR |
| Corrections Issued | 6/23/2022 | MANUEL MONTUFAR |
| Quality Review Completed | 6/27/2022 | EUGENE BARBEAU |
| Applicant returned to address corrections | 9/20/2022 | MANUEL MONTUFAR |
| Applicant returned to address corrections | 9/28/2022 | MANUEL MONTUFAR |
| Applicant returned to address corrections | 8/10/2023 | MANUEL MONTUFAR |
| Plan Check Approved | 8/18/2023 | MANUEL MONTUFAR |
| Issued | 9/11/2023 | APPLICANT |
| CofO in Progress | 10/17/2025 | RAFAEL ESPINOZA |
| Permit Finaled | 10/17/2025 | RAFAEL ESPINOZA |
| CofO Issued | 10/17/2025 | RAFAEL ESPINOZA |
| Permit Finaled | 10/17/2025 | RAFAEL ESPINOZA |
Permit Application Clearance Information
| Address approval | Cleared | 6/30/2022 | JEANETTE VONG |
| Permit | Cleared | 6/30/2022 | JEANETTE VONG |
| Trees in Parkway | Cleared | 7/6/2022 | ADALBERTO VERA |
| Hydrant and Access approval | Cleared | 10/1/2022 | RUEL COLE |
| Frnt yard landscape/Water mgmt | Cleared | 1/24/2023 | KENTON TRINH |
| Miscellaneous | Cleared | 1/24/2023 | KENTON TRINH |
| Opn space landscape/Water mgmt | Cleared | 1/24/2023 | KENTON TRINH |
| Low Impact Development | Cleared | 1/30/2023 | AMMAR ELTAWIL |
| Density Bonus 12.22.A.31 | Cleared | 2/22/2023 | KENNETH LE |
| SB8 RUD | Cleared | 2/22/2023 | KENNETH LE |
| Eng Process Fee Ord 176,300 | Cleared | 3/9/2023 | JEANETTE VONG |
| Sewer availability | Cleared | 3/9/2023 | JEANETTE VONG |
| Roof/Waste drainage to street | Cleared | 3/16/2023 | JEANETTE VONG |
| DAS Clearance | Cleared | 3/17/2023 | MANUEL MONTUFAR |
| Construction near power lines | Cleared | 4/20/2023 | RIDWAN HARDY |
| Green Code | Cleared | 5/18/2023 | MANUEL MONTUFAR |
| Fire Marshal Fire Life Safety | Cleared | 6/6/2023 | SARAH ZHANG |
Contact Information
| Contractor | Owner-Builder | , |
| Engineer | Chatsky,, German; Lic. No.: C84153 | 3876 HUNTERS GROVE CT MOORPARK, CA 93021 |
| Engineer | Smith,, Melvin Bruce; Lic. No.: GE2673 | 2165 N MARVEL AVE SIMI VALLEY, CA 93065 |
Inspector Information
| No Data Available. |
Pending Inspections
| No Data Available. |
Inspection Request History
| Excavation/Setback/Form/Re-Bar | 11/13/2023 | Partial Approval | JAMES POWERS |
| Footing/Foundation/Slab | 11/13/2023 | Partial Approval | JAMES POWERS |
| Floor/Roof Diaphrgm/Shear Wall | 1/23/2024 | Partial Approval | LARRY ARNICK |
| Floor/Roof Diaphrgm/Shear Wall | 2/21/2024 | Partial Approval | RICARDO ROBLES |
| Green Building Rough | 2/21/2024 | Not Ready for Inspection | RICARDO ROBLES |
| Verify Sprinkler Sign Off | 2/21/2024 | Not Ready for Inspection | RICARDO ROBLES |
| Floor/Roof Diaphrgm/Shear Wall | 3/12/2024 | Partial Approval | RAFAEL ESPINOZA |
| Wood Frame | 3/20/2024 | Partial Approval | RAFAEL ESPINOZA |
| Floor/Roof Diaphrgm/Shear Wall | 4/4/2024 | Partial Approval | JAMES POWERS |
| Green Building Rough | 4/4/2024 | Approved | JAMES POWERS |
| Interior/Exterior Lathing | 4/4/2024 | Not Ready for Inspection | JAMES POWERS |
| Verify Sprinkler Sign Off | 4/4/2024 | Not Ready for Inspection | JAMES POWERS |
| Wood Frame | 4/4/2024 | Not Ready for Inspection | JAMES POWERS |
| Drywall Nailing | 5/23/2024 | Partial Inspection | RAFAEL ESPINOZA |
| Pre-Inspection | 6/17/2024 | Partial Inspection | RAFAEL ESPINOZA |
| Wood Frame | 6/20/2024 | Corrections Issued | RAFAEL ESPINOZA |
| Wood Frame | 6/21/2024 | Partial Approval | RAFAEL ESPINOZA |
| Insulation | 6/27/2024 | Partial Approval | RAFAEL ESPINOZA |
| Verify Sprinkler Sign Off | 7/18/2024 | Not Ready for Inspection | RAFAEL ESPINOZA |
| Wood Frame | 7/18/2024 | Corrections Issued | RAFAEL ESPINOZA |
| Interior/Exterior Lathing | 7/22/2024 | Partial Approval | RAFAEL ESPINOZA |
| Verify Sprinkler Sign Off | 7/22/2024 | Not Ready for Inspection | RAFAEL ESPINOZA |
| Wood Frame | 7/26/2024 | Partial Approval | DANIEL VARNUM |
| Insulation | 7/29/2024 | Partial Approval | RAFAEL ESPINOZA |
| Interior/Exterior Lathing | 7/29/2024 | Partial Approval | RAFAEL ESPINOZA |
| Insulation | 8/12/2024 | Partial Approval | RAFAEL ESPINOZA |
| Wood Frame | 8/12/2024 | Partial Approval | RAFAEL ESPINOZA |
| Insulation | 8/16/2024 | Partial Approval | RAFAEL ESPINOZA |
| Special/Order Compliance | 8/16/2024 | Partial Inspection | RAFAEL ESPINOZA |
| Wood Frame | 8/16/2024 | Partial Approval | RAFAEL ESPINOZA |
| Deputy Wood Construction | 8/26/2024 | Conditional Approval | RAFAEL ESPINOZA |
| Floor/Roof Diaphrgm/Shear Wall | 8/26/2024 | Partial Approval | RAFAEL ESPINOZA |
| Verify Sprinkler Sign Off | 8/26/2024 | Not Ready for Inspection | RAFAEL ESPINOZA |
| Interior/Exterior Lathing | 9/6/2024 | Approved | JAMES POWERS |
| Insulation | 9/13/2024 | Partial Approval | RAFAEL ESPINOZA |
| Drywall Nailing | 10/18/2024 | Partial Approval | RAFAEL ESPINOZA |
| Interior/Exterior Lathing | 10/18/2024 | Corrections Issued | RAFAEL ESPINOZA |
| Drywall Nailing | 10/31/2024 | Partial Approval | RAFAEL CORTES |
| Drywall Nailing | 11/6/2024 | Not Ready for Inspection | RAFAEL CORTES |
| Drywall Nailing | 11/8/2024 | Partial Approval | RAFAEL CORTES |
| Pre-Inspection | 1/13/2025 | Approved | RAFAEL CORTES |
| Pre-Inspection | 3/26/2025 | Partial Inspection | RAFAEL ESPINOZA |
| Special/Order Compliance | 3/26/2025 | Partial Approval | RAFAEL ESPINOZA |
| Pre-Inspection | 4/4/2025 | Corrections Issued | RAFAEL ESPINOZA |
| Final | 8/15/2025 | Partial Inspection | RAFAEL ESPINOZA |
| Footing/Foundation/Slab | 8/15/2025 | Not Ready for Inspection | RAFAEL ESPINOZA |
| Green Building Final | 8/15/2025 | Approved | RAFAEL ESPINOZA |
| SGSOV-Seismic Gas S/O Valve | 8/15/2025 | SGSOV Approved | RAFAEL ESPINOZA |
| Smoke Detectors | 8/15/2025 | Approved | RAFAEL ESPINOZA |
| Verify Sprinkler Sign Off | 8/15/2025 | Approved | RAFAEL ESPINOZA |
| Wood Frame | 8/15/2025 | Not Ready for Inspection | RAFAEL ESPINOZA |
| Final | 10/17/2025 | OK to Issue CofO | RAFAEL ESPINOZA |
| Footing/Foundation/Slab | 10/17/2025 | Approved | RAFAEL ESPINOZA |
| Wood Frame | 10/17/2025 | Approved | RAFAEL ESPINOZA |