2860 S SHENANDOAH ST 90034

Certificate Information: 2860 S SHENANDOAH ST 90034

Application / Permit
22010-10000-02797
Plan Check / Job No.
B22LA10598
Group
Building
Type
Bldg-Addition
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Accessory Dwelling Unit
Work Description
eplan CONVERT (E) DETACHED GARAGE TO ADU WITH ADDITION PER LAMC 12.22 A.33 (c)(d)
Permit Issued
Issued on 5/1/2023
Issuing Office
Current Status
CofO Issued on 6/7/2025
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 6/10/2022 APPLICANT
Assigned to Plan Check Engineer 6/17/2022 KHUONG TRUONG
Corrections Issued 6/19/2022 KHUONG TRUONG
Plan Check Approved 3/18/2023 KHUONG TRUONG
Issued 5/1/2023 APPLICANT
CofO in Progress 6/7/2025 MICHAEL PELHAM
Permit Finaled 6/7/2025 RICHARD STEINBACH
CofO Issued 6/7/2025 RICHARD STEINBACH
Permit Finaled 6/7/2025 RICHARD STEINBACH

Permit Application Clearance Information

Specific Plan Cleared 7/22/2022 ANACANY HURTADO
ZI Cleared 7/22/2022 ANACANY HURTADO
Address approval Cleared 7/28/2022 AMAAN MALIK
Eng Process Fee Ord 176,300 Cleared 8/2/2022 AMAAN MALIK
Sewer availability Cleared 8/2/2022 AMAAN MALIK
Miscellaneous Cleared 11/17/2022 DANIEL SCHNEIDEREIT
Low Impact Development Cleared 1/9/2023 LUIS LUVANO
Roof/Waste drainage to street Cleared 3/15/2023 TREVOR QUAN

Contact Information

Contractor Sk Renovation; Lic. No.: 1091484-B       ,
Engineer Park,, Juntae; Lic. No.: C65104 3055 WILSHIRE BLVD 880      LOS ANGELES, CA 90010
Engineer Park,, Juntae; Lic. No.: NA65104       ,

Inspector Information

WILBER ROSALES, (310) 914-3892 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

PLUMBING-Rough 7/26/2023 Partial Approval ARAM AVEDISIAN
Sewer 7/26/2023 Approved ARAM AVEDISIAN
BUILDING-Rough-Frame 3/7/2024 Not Ready for Inspection MEL KHACHATOURIAN
Green Building Rough 3/7/2024 Not Ready for Inspection MEL KHACHATOURIAN
MERV13>=Rough 3/7/2024 Approved MEL KHACHATOURIAN
Rough-Elec/Plmb/HVAC 3/7/2024 Partial Approval MEL KHACHATOURIAN
BUILDING-Rough-Frame 3/21/2024 Approved MEL KHACHATOURIAN
ELECTRICAL-Rough 3/21/2024 Approved MEL KHACHATOURIAN
Green Building Rough 3/21/2024 Approved MEL KHACHATOURIAN
PLUMBING-Rough 3/21/2024 Partial Approval MEL KHACHATOURIAN
Gas Test 4/9/2024 Corrections Issued ASHLEY THOMPSON
Insulation 4/9/2024 Corrections Issued ASHLEY THOMPSON
Interior/Exterior Lathing 4/9/2024 Partial Approval ASHLEY THOMPSON
Drywall Nailing 5/22/2024 Approved MEL KHACHATOURIAN
Interior/Exterior Lathing 5/30/2024 Approved MEL KHACHATOURIAN
ELECTRICAL-Final 12/13/2024 Corrections Issued BOBBY KEY
Final 12/13/2024 Corrections Issued BOBBY KEY
Footing/Foundation/Slab 12/13/2024 Approved BOBBY KEY
Green Building Final 12/13/2024 Approved BOBBY KEY
HVAC-Final 12/13/2024 Corrections Issued BOBBY KEY
MERV13>=Final 12/13/2024 Approved BOBBY KEY
PLUMBING-Final 12/13/2024 Corrections Issued BOBBY KEY
SGSOV-Seismic Gas S/O Valve 12/13/2024 SGSOV Not Ready BOBBY KEY
Smoke Detectors 12/13/2024 Approved BOBBY KEY
Final 1/27/2025 Partial Approval MEL KHACHATOURIAN
SGSOV-Seismic Gas S/O Valve 1/27/2025 SGSOV Approved MEL KHACHATOURIAN
Final 2/3/2025 Corrections Issued EVAN COOPER
Service/Power Release 2/3/2025 Approved EVAN COOPER
Deputy Drilled-In Anchors 2/6/2025 Conditional Approval MICHAEL PELHAM
Final 6/7/2025 OK to Issue CofO MICHAEL PELHAM