2860 S SHENANDOAH ST 90034
Certificate Information: 2860 S SHENANDOAH ST 90034
- Application / Permit
- 22010-10000-02797
- Plan Check / Job No.
- B22LA10598
- Group
- Building
- Type
- Bldg-Addition
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Accessory Dwelling Unit
- Work Description
- eplan CONVERT (E) DETACHED GARAGE TO ADU WITH ADDITION PER LAMC 12.22 A.33 (c)(d)
- Permit Issued
- Issued on 5/1/2023
- Issuing Office
- Current Status
- CofO Issued on 6/7/2025
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 6/10/2022 | APPLICANT |
| Assigned to Plan Check Engineer | 6/17/2022 | KHUONG TRUONG |
| Corrections Issued | 6/19/2022 | KHUONG TRUONG |
| Plan Check Approved | 3/18/2023 | KHUONG TRUONG |
| Issued | 5/1/2023 | APPLICANT |
| CofO in Progress | 6/7/2025 | MICHAEL PELHAM |
| Permit Finaled | 6/7/2025 | RICHARD STEINBACH |
| CofO Issued | 6/7/2025 | RICHARD STEINBACH |
| Permit Finaled | 6/7/2025 | RICHARD STEINBACH |
Permit Application Clearance Information
| Specific Plan | Cleared | 7/22/2022 | ANACANY HURTADO |
| ZI | Cleared | 7/22/2022 | ANACANY HURTADO |
| Address approval | Cleared | 7/28/2022 | AMAAN MALIK |
| Eng Process Fee Ord 176,300 | Cleared | 8/2/2022 | AMAAN MALIK |
| Sewer availability | Cleared | 8/2/2022 | AMAAN MALIK |
| Miscellaneous | Cleared | 11/17/2022 | DANIEL SCHNEIDEREIT |
| Low Impact Development | Cleared | 1/9/2023 | LUIS LUVANO |
| Roof/Waste drainage to street | Cleared | 3/15/2023 | TREVOR QUAN |
Contact Information
| Contractor | Sk Renovation; Lic. No.: 1091484-B | , |
| Engineer | Park,, Juntae; Lic. No.: C65104 | 3055 WILSHIRE BLVD 880 LOS ANGELES, CA 90010 |
| Engineer | Park,, Juntae; Lic. No.: NA65104 | , |
Inspector Information
| WILBER ROSALES, (310) 914-3892 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| PLUMBING-Rough | 7/26/2023 | Partial Approval | ARAM AVEDISIAN |
| Sewer | 7/26/2023 | Approved | ARAM AVEDISIAN |
| BUILDING-Rough-Frame | 3/7/2024 | Not Ready for Inspection | MEL KHACHATOURIAN |
| Green Building Rough | 3/7/2024 | Not Ready for Inspection | MEL KHACHATOURIAN |
| MERV13>=Rough | 3/7/2024 | Approved | MEL KHACHATOURIAN |
| Rough-Elec/Plmb/HVAC | 3/7/2024 | Partial Approval | MEL KHACHATOURIAN |
| BUILDING-Rough-Frame | 3/21/2024 | Approved | MEL KHACHATOURIAN |
| ELECTRICAL-Rough | 3/21/2024 | Approved | MEL KHACHATOURIAN |
| Green Building Rough | 3/21/2024 | Approved | MEL KHACHATOURIAN |
| PLUMBING-Rough | 3/21/2024 | Partial Approval | MEL KHACHATOURIAN |
| Gas Test | 4/9/2024 | Corrections Issued | ASHLEY THOMPSON |
| Insulation | 4/9/2024 | Corrections Issued | ASHLEY THOMPSON |
| Interior/Exterior Lathing | 4/9/2024 | Partial Approval | ASHLEY THOMPSON |
| Drywall Nailing | 5/22/2024 | Approved | MEL KHACHATOURIAN |
| Interior/Exterior Lathing | 5/30/2024 | Approved | MEL KHACHATOURIAN |
| ELECTRICAL-Final | 12/13/2024 | Corrections Issued | BOBBY KEY |
| Final | 12/13/2024 | Corrections Issued | BOBBY KEY |
| Footing/Foundation/Slab | 12/13/2024 | Approved | BOBBY KEY |
| Green Building Final | 12/13/2024 | Approved | BOBBY KEY |
| HVAC-Final | 12/13/2024 | Corrections Issued | BOBBY KEY |
| MERV13>=Final | 12/13/2024 | Approved | BOBBY KEY |
| PLUMBING-Final | 12/13/2024 | Corrections Issued | BOBBY KEY |
| SGSOV-Seismic Gas S/O Valve | 12/13/2024 | SGSOV Not Ready | BOBBY KEY |
| Smoke Detectors | 12/13/2024 | Approved | BOBBY KEY |
| Final | 1/27/2025 | Partial Approval | MEL KHACHATOURIAN |
| SGSOV-Seismic Gas S/O Valve | 1/27/2025 | SGSOV Approved | MEL KHACHATOURIAN |
| Final | 2/3/2025 | Corrections Issued | EVAN COOPER |
| Service/Power Release | 2/3/2025 | Approved | EVAN COOPER |
| Deputy Drilled-In Anchors | 2/6/2025 | Conditional Approval | MICHAEL PELHAM |
| Final | 6/7/2025 | OK to Issue CofO | MICHAEL PELHAM |