1344-1346 S MANSFIELD AVE 90019

Certificate Information: 1344-1346 S MANSFIELD AVE 90019

Application / Permit
22010-10000-02777
Plan Check / Job No.
B22LA10513
Group
Building
Type
Bldg-Addition
Sub-Type
1 or 2 Family Dwelling
Primary Use
(2) Duplex
Work Description
eplan ADDITION AND INTERIOR REMODEL TO (E) DUPLEX
Permit Issued
Issued on 11/15/2022
Issuing Office
Current Status
CofO Issued on 8/23/2023
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 6/3/2022 APPLICANT
Assigned to Plan Check Engineer 6/10/2022 ZAW HAN
Corrections Issued 6/13/2022 ZAW HAN
Applicant returned to address corrections 8/11/2022 FERNANDO FLORES
Plan Check Approved 11/14/2022 FERNANDO FLORES
Issued 11/15/2022 APPLICANT
CofO in Progress 5/16/2023 STUART CHAPMAN
No Progress 5/25/2023 CALEB MEISTER
CofO in Progress 8/22/2023 CALEB MEISTER
CofO Issued 8/23/2023 DEROLD HAUFF
Permit Finaled 8/23/2023 DEROLD HAUFF

Permit Application Clearance Information

Roof/Waste drainage to street Cleared 6/14/2022 JEANETTE VONG
Sewer availability Cleared 6/14/2022 JEANETTE VONG
Eng Process Fee Ord 176,300 Cleared 7/20/2022 JEANETTE VONG
Tenant Habitability Plan Cleared 11/8/2022 ISMAEL HERNANDEZ

Contact Information

Contractor Fort Multifamily Inc; Lic. No.: 1097435-B       ,

Inspector Information

JUSTIN HAWLEY, (213) 202-3432 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

ELECTRICAL-Rough 1/5/2023 Approved CALEB MEISTER
Footing/Foundation/Slab 1/17/2023 Approved CALEB MEISTER
METHANE-Barrier 1/17/2023 Approved CALEB MEISTER
METHANE-Subgrade 1/17/2023 Approved CALEB MEISTER
BUILDING-Rough-Frame 1/25/2023 Partial Approval CALEB MEISTER
Green Building Rough 1/25/2023 Not Ready for Inspection CALEB MEISTER
METHANE-Rough 1/25/2023 Not Ready for Inspection CALEB MEISTER
Insulation 1/31/2023 Approved CALEB MEISTER
Interior/Exterior Lathing 1/31/2023 Approved CALEB MEISTER
Rough-Elec/Plmb/HVAC 1/31/2023 Approved CALEB MEISTER
Drywall Nailing 2/3/2023 Approved CALEB MEISTER
Green Building Rough 2/3/2023 Approved CALEB MEISTER
BUILDING-Rough-Frame 4/20/2023 Approved STUART CHAPMAN
ELECTRICAL-Final 4/20/2023 Approved STUART CHAPMAN
Final 4/20/2023 Not Ready for Inspection STUART CHAPMAN
Green Building Final 4/20/2023 Approved STUART CHAPMAN
HVAC-Final 4/20/2023 Approved STUART CHAPMAN
METHANE-Final 4/20/2023 Approved STUART CHAPMAN
METHANE-Rough 4/20/2023 Approved STUART CHAPMAN
PLUMBING-Final 4/20/2023 Approved STUART CHAPMAN
SGSOV-Seismic Gas S/O Valve 4/20/2023 SGSOV Approved STUART CHAPMAN
Smoke Detectors 4/20/2023 Approved STUART CHAPMAN
Final 5/16/2023 OK to Issue CofO STUART CHAPMAN
Special/Order Compliance 5/25/2023 Corrections Issued CALEB MEISTER