2205 E SHERIDAN ST 90033

Certificate Information: 2205 E SHERIDAN ST 90033

Application / Permit
22010-10000-02776
Plan Check / Job No.
B22LA10512
Group
Building
Type
Bldg-New
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Accessory Dwelling Unit
Work Description
ePlan: (N) 1-STORY ACCESSORY DWELLING UNIT PER LAMC 12.22.A.33.(c)-(d)
Permit Issued
Issued on 3/19/2024
Issuing Office
Current Status
CofO Issued on 5/10/2025
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 6/1/2022 APPLICANT
Assigned to Plan Check Engineer 6/13/2022 DANIEL YIP
Corrections Issued 6/14/2022 DANIEL YIP
Quality Review Completed 7/5/2022 MICHAEL PEREZ
Plan Check Approved 8/18/2022 DANIEL YIP
No Progress 2/21/2024 DANIEL YIP
Plan Check Approved 2/21/2024 DANIEL YIP
Issued 3/19/2024 APPLICANT
CofO in Progress 5/8/2025 ALIZAH MAYAGOITIA
Permit Finaled 5/10/2025 DEROLD HAUFF
CofO Issued 5/10/2025 DEROLD HAUFF
Permit Finaled 5/10/2025 DEROLD HAUFF

Permit Application Clearance Information

Clean Up Green Up Cleared 7/14/2022 BRENNEN OBETO
Grading Pre-Inspection Cleared 7/18/2022 VASIL MIHALEV
Address approval Cleared 7/19/2022 JEANETTE VONG
Low Impact Development Cleared 7/25/2022 ROGELIO CORTES
Eng Process Fee Ord 176,300 Cleared 7/28/2022 JEANETTE VONG
Sewer availability Cleared 7/28/2022 JEANETTE VONG
Roof/Waste drainage to street Cleared 7/29/2022 JEANETTE VONG
GPI Written Notices Cleared 8/18/2022 DANIEL YIP

Contact Information

Contractor R S Carpentry Design & Remodeling Inc; Lic. No.: 1023757-B       ,
Engineer Wu,, Harold Ping-Hung; Lic. No.: C35693 1168 SAN GABRIEL BLVD NO N      ROSEMEAD, CA 91770

Inspector Information

OSVALDO PARAMO, (213) 202-9854 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Excavation/Setback/Form/Re-Bar 4/12/2024 Corrections Issued OSVALDO PARAMO
Underground Mechanical 4/12/2024 Partial Approval OSVALDO PARAMO
Excavation/Setback/Form/Re-Bar 4/18/2024 Corrections Issued OSVALDO PARAMO
Excavation/Setback/Form/Re-Bar 4/19/2024 Approved OSVALDO PARAMO
ELECTRICAL-Rough 6/10/2024 Approved OSVALDO PARAMO
Floor/Roof Diaphrgm/Shear Wall 6/10/2024 Approved OSVALDO PARAMO
HVAC-Rough 6/10/2024 Approved OSVALDO PARAMO
PLUMBING-Rough 6/10/2024 Approved OSVALDO PARAMO
Interior/Exterior Lathing 6/20/2024 Partial Approval OSVALDO PARAMO
Underground Mechanical 6/20/2024 Partial Approval OSVALDO PARAMO
BUILDING-Rough-Frame 7/1/2024 Conditional Approval LILIANA PORTILLO
Insulation 7/3/2024 Approved OSVALDO PARAMO
Drywall Nailing 7/16/2024 Approved BRENDAN MORELLI
Green Building Rough 7/16/2024 Approved BRENDAN MORELLI
Interior/Exterior Lathing 7/16/2024 Approved BRENDAN MORELLI
Shower Pan 7/16/2024 Approved BRENDAN MORELLI
Final 9/20/2024 Corrections Issued LUIS CASTRO
Footing/Foundation/Slab 9/20/2024 Not Ready for Inspection LUIS CASTRO
BUILDING-Rough-Frame 10/1/2024 Approved OSVALDO PARAMO
Final 10/1/2024 Corrections Issued OSVALDO PARAMO
Footing/Foundation/Slab 10/1/2024 Approved OSVALDO PARAMO
Green Building Final 10/1/2024 Approved OSVALDO PARAMO
MERV13>=Final 10/1/2024 Approved OSVALDO PARAMO
MERV13>=Rough 10/1/2024 Approved OSVALDO PARAMO
SGSOV-Seismic Gas S/O Valve 10/1/2024 SGSOV Approved OSVALDO PARAMO
Service/Power Release 10/1/2024 Not Ready for Inspection OSVALDO PARAMO
Smoke Detectors 10/1/2024 Approved OSVALDO PARAMO
Verify Sprinkler Sign Off 10/1/2024 Approved OSVALDO PARAMO
Final 10/31/2024 Not Ready for Inspection RUBEN SALAS
Service/Power Release 10/31/2024 Not Ready for Inspection RUBEN SALAS
Final 11/7/2024 Corrections Issued OSVALDO PARAMO
Service/Power Release 11/7/2024 Not Ready for Inspection OSVALDO PARAMO
Final 3/10/2025 Corrections Issued ALIZAH MAYAGOITIA
Service/Power Release 3/10/2025 Approved ALIZAH MAYAGOITIA
PLUMBING-Final 3/26/2025 Approved OSVALDO PARAMO
Final 5/7/2025 OK to Issue CofO ALIZAH MAYAGOITIA