853 S MANSFIELD AVE 90036
Certificate Information: 853 S MANSFIELD AVE 90036
- Application / Permit
- 22010-10000-02774
- Plan Check / Job No.
- B22LA10511
- Group
- Building
- Type
- Bldg-New
- Sub-Type
- Apartment
- Primary Use
- (1) Accessory Dwelling Unit
- Work Description
- eplan: NEW 2-STORY ADU PER LAMC 12.22 A.33 (C)-(D)
- Permit Issued
- Issued on 3/16/2024
- Issuing Office
- Current Status
- CofO Issued on 12/16/2025
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 6/2/2022 | APPLICANT |
| Assigned to Plan Check Engineer | 7/7/2022 | HOOMAN HAJIZADEH |
| Corrections Issued | 7/21/2022 | TARIK SAOUD |
| Quality Review Completed | 8/2/2022 | CHIHARU SUZUKI |
| Applicant returned to address corrections | 11/14/2022 | HOOMAN HAJIZADEH |
| Applicant returned to address corrections | 3/22/2023 | HOOMAN HAJIZADEH |
| Applicant returned to address corrections | 11/9/2023 | HOOMAN HAJIZADEH |
| Applicant returned to address corrections | 11/27/2023 | HOOMAN HAJIZADEH |
| Plan Check Approved | 12/22/2023 | HOOMAN HAJIZADEH |
| Issued | 3/16/2024 | APPLICANT |
| Permit Finaled | 12/16/2025 | ERNESTO CORRAL |
| CofO Issued | 12/16/2025 | ERNESTO CORRAL |
| Permit Finaled | 12/16/2025 | ERNESTO CORRAL |
Permit Application Clearance Information
| Address approval | Cleared | 2/11/2023 | TREVOR QUAN |
| Construction near power lines | Cleared | 8/29/2023 | RIDWAN HARDY |
| Low Impact Development | Cleared | 10/13/2023 | ROGELIO CORTES |
| Roof/Waste drainage to street | Cleared | 10/24/2023 | TREVOR QUAN |
| Eng Process Fee Ord 176,300 | Cleared | 11/2/2023 | CHRISTINA BRACO |
| Sewer availability | Cleared | 11/2/2023 | CHRISTINA BRACO |
Contact Information
| Contractor | Cal - Quake Construction Inc; Lic. No.: 759817-B | , |
| Contractor | Perluss Sheldon K; Lic. No.: 759817-B | , |
| Engineer | Amoli,, Bahar Hosseini; Lic. No.: C94992 | 3221 CARTER AVE, APT 282 MARINA DEL REY, CA 90292 |
| Engineer | Ni,, Zhang Yuan; Lic. No.: C68149 | 8232 GARVEY AVE 203 ROSEMEAD, CA 91770 |
| Engineer | Qi,, Yibo; Lic. No.: M39581 | 140 CHORUS IRVINE, CA 92618 |
Inspector Information
| MARTIN TAVITIAN, (213) 482-7357 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Footing/Foundation/Slab | 3/27/2024 | Corrections Issued | RONNIE MINDANAO |
| METHANE-Barrier | 3/27/2024 | Not Ready for Inspection | RONNIE MINDANAO |
| METHANE-Subgrade | 3/27/2024 | Not Ready for Inspection | RONNIE MINDANAO |
| Excavation/Setback/Form/Re-Bar | 4/1/2024 | Partial Approval | AMIR NAZARIAN |
| Pre-Inspection | 6/20/2024 | Corrections Issued | RICHARD DOCKUS |
| Deputy Methane Barrier | 6/21/2024 | Conditional Approval | RICHARD DOCKUS |
| Deputy Steel/Welding | 6/27/2024 | Conditional Approval | RONNIE MINDANAO |
| Footing/Foundation/Slab | 6/27/2024 | Corrections Issued | RONNIE MINDANAO |
| METHANE-Barrier | 6/27/2024 | Approved | RONNIE MINDANAO |
| METHANE-Rough | 6/27/2024 | Not Ready for Inspection | RONNIE MINDANAO |
| METHANE-Subgrade | 6/27/2024 | Approved | RONNIE MINDANAO |
| Pre-Inspection | 6/27/2024 | Partial Inspection | RONNIE MINDANAO |
| Deputy Reinf. Concrete | 7/12/2024 | Conditional Approval | RONNIE MINDANAO |
| Deputy Steel/Welding | 7/24/2024 | Conditional Approval | RONNIE MINDANAO |
| Deputy Wood Construction | 8/8/2024 | Conditional Approval | RONNIE MINDANAO |
| Floor/Roof Diaphrgm/Shear Wall | 8/8/2024 | Partial Approval | RONNIE MINDANAO |
| Wood Frame | 8/8/2024 | Partial Approval | RONNIE MINDANAO |
| METHANE-Rough | 8/29/2024 | Not Ready for Inspection | RONNIE MINDANAO |
| Verify Sprinkler Sign Off | 8/29/2024 | Not Ready for Inspection | RONNIE MINDANAO |
| Wood Frame | 8/29/2024 | Corrections Issued | RONNIE MINDANAO |
| Deputy Wood Construction | 10/2/2024 | Conditional Approval | RONNIE MINDANAO |
| Floor/Roof Diaphrgm/Shear Wall | 10/16/2024 | Corrections Issued | RONNIE MINDANAO |
| METHANE-Rough | 10/16/2024 | Not Ready for Inspection | RONNIE MINDANAO |
| Verify Sprinkler Sign Off | 10/16/2024 | Approved | RONNIE MINDANAO |
| Special/Order Compliance | 2/19/2025 | Partial Approval | JOAQUIN GREENOUGH |
| Pre-Inspection | 5/15/2025 | Partial Inspection | RONNIE MINDANAO |
| METHANE-Rough | 7/9/2025 | Approved | EDWIN GREGORYONA |
| Wood Frame | 7/9/2025 | Not Ready for Inspection | EDWIN GREGORYONA |
| Wood Frame | 7/18/2025 | Partial Approval | CHRISTOPHER BLACKWOOD |
| Insulation | 7/22/2025 | Approved | CHRISTOPHER BLACKWOOD |
| Drywall Nailing | 7/25/2025 | Partial Approval | CHRISTOPHER BLACKWOOD |
| Interior/Exterior Lathing | 7/30/2025 | Partial Inspection | CHRISTOPHER BLACKWOOD |
| Interior/Exterior Lathing | 8/14/2025 | Approved | CHRISTOPHER BLACKWOOD |
| Final | 10/29/2025 | Partial Approval | CHRISTOPHER BLACKWOOD |
| Footing/Foundation/Slab | 10/29/2025 | Approved | CHRISTOPHER BLACKWOOD |
| SGSOV-Seismic Gas S/O Valve | 10/29/2025 | SGSOV No Gas | CHRISTOPHER BLACKWOOD |
| Smoke Detectors | 10/29/2025 | Approved | CHRISTOPHER BLACKWOOD |
| Wood Frame | 10/29/2025 | Approved | CHRISTOPHER BLACKWOOD |