853 S MANSFIELD AVE 90036

Certificate Information: 853 S MANSFIELD AVE 90036

Application / Permit
22010-10000-02774
Plan Check / Job No.
B22LA10511
Group
Building
Type
Bldg-New
Sub-Type
Apartment
Primary Use
(1) Accessory Dwelling Unit
Work Description
eplan: NEW 2-STORY ADU PER LAMC 12.22 A.33 (C)-(D)
Permit Issued
Issued on 3/16/2024
Issuing Office
Current Status
CofO Issued on 12/16/2025
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 6/2/2022 APPLICANT
Assigned to Plan Check Engineer 7/7/2022 HOOMAN HAJIZADEH
Corrections Issued 7/21/2022 TARIK SAOUD
Quality Review Completed 8/2/2022 CHIHARU SUZUKI
Applicant returned to address corrections 11/14/2022 HOOMAN HAJIZADEH
Applicant returned to address corrections 3/22/2023 HOOMAN HAJIZADEH
Applicant returned to address corrections 11/9/2023 HOOMAN HAJIZADEH
Applicant returned to address corrections 11/27/2023 HOOMAN HAJIZADEH
Plan Check Approved 12/22/2023 HOOMAN HAJIZADEH
Issued 3/16/2024 APPLICANT
Permit Finaled 12/16/2025 ERNESTO CORRAL
CofO Issued 12/16/2025 ERNESTO CORRAL
Permit Finaled 12/16/2025 ERNESTO CORRAL

Permit Application Clearance Information

Address approval Cleared 2/11/2023 TREVOR QUAN
Construction near power lines Cleared 8/29/2023 RIDWAN HARDY
Low Impact Development Cleared 10/13/2023 ROGELIO CORTES
Roof/Waste drainage to street Cleared 10/24/2023 TREVOR QUAN
Eng Process Fee Ord 176,300 Cleared 11/2/2023 CHRISTINA BRACO
Sewer availability Cleared 11/2/2023 CHRISTINA BRACO

Contact Information

Contractor Cal - Quake Construction Inc; Lic. No.: 759817-B       ,
Contractor Perluss Sheldon K; Lic. No.: 759817-B       ,
Engineer Amoli,, Bahar Hosseini; Lic. No.: C94992 3221 CARTER AVE, APT 282      MARINA DEL REY, CA 90292
Engineer Ni,, Zhang Yuan; Lic. No.: C68149 8232 GARVEY AVE 203      ROSEMEAD, CA 91770
Engineer Qi,, Yibo; Lic. No.: M39581 140 CHORUS      IRVINE, CA 92618

Inspector Information

MARTIN TAVITIAN, (213) 482-7357 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Footing/Foundation/Slab 3/27/2024 Corrections Issued RONNIE MINDANAO
METHANE-Barrier 3/27/2024 Not Ready for Inspection RONNIE MINDANAO
METHANE-Subgrade 3/27/2024 Not Ready for Inspection RONNIE MINDANAO
Excavation/Setback/Form/Re-Bar 4/1/2024 Partial Approval AMIR NAZARIAN
Pre-Inspection 6/20/2024 Corrections Issued RICHARD DOCKUS
Deputy Methane Barrier 6/21/2024 Conditional Approval RICHARD DOCKUS
Deputy Steel/Welding 6/27/2024 Conditional Approval RONNIE MINDANAO
Footing/Foundation/Slab 6/27/2024 Corrections Issued RONNIE MINDANAO
METHANE-Barrier 6/27/2024 Approved RONNIE MINDANAO
METHANE-Rough 6/27/2024 Not Ready for Inspection RONNIE MINDANAO
METHANE-Subgrade 6/27/2024 Approved RONNIE MINDANAO
Pre-Inspection 6/27/2024 Partial Inspection RONNIE MINDANAO
Deputy Reinf. Concrete 7/12/2024 Conditional Approval RONNIE MINDANAO
Deputy Steel/Welding 7/24/2024 Conditional Approval RONNIE MINDANAO
Deputy Wood Construction 8/8/2024 Conditional Approval RONNIE MINDANAO
Floor/Roof Diaphrgm/Shear Wall 8/8/2024 Partial Approval RONNIE MINDANAO
Wood Frame 8/8/2024 Partial Approval RONNIE MINDANAO
METHANE-Rough 8/29/2024 Not Ready for Inspection RONNIE MINDANAO
Verify Sprinkler Sign Off 8/29/2024 Not Ready for Inspection RONNIE MINDANAO
Wood Frame 8/29/2024 Corrections Issued RONNIE MINDANAO
Deputy Wood Construction 10/2/2024 Conditional Approval RONNIE MINDANAO
Floor/Roof Diaphrgm/Shear Wall 10/16/2024 Corrections Issued RONNIE MINDANAO
METHANE-Rough 10/16/2024 Not Ready for Inspection RONNIE MINDANAO
Verify Sprinkler Sign Off 10/16/2024 Approved RONNIE MINDANAO
Special/Order Compliance 2/19/2025 Partial Approval JOAQUIN GREENOUGH
Pre-Inspection 5/15/2025 Partial Inspection RONNIE MINDANAO
METHANE-Rough 7/9/2025 Approved EDWIN GREGORYONA
Wood Frame 7/9/2025 Not Ready for Inspection EDWIN GREGORYONA
Wood Frame 7/18/2025 Partial Approval CHRISTOPHER BLACKWOOD
Insulation 7/22/2025 Approved CHRISTOPHER BLACKWOOD
Drywall Nailing 7/25/2025 Partial Approval CHRISTOPHER BLACKWOOD
Interior/Exterior Lathing 7/30/2025 Partial Inspection CHRISTOPHER BLACKWOOD
Interior/Exterior Lathing 8/14/2025 Approved CHRISTOPHER BLACKWOOD
Final 10/29/2025 Partial Approval CHRISTOPHER BLACKWOOD
Footing/Foundation/Slab 10/29/2025 Approved CHRISTOPHER BLACKWOOD
SGSOV-Seismic Gas S/O Valve 10/29/2025 SGSOV No Gas CHRISTOPHER BLACKWOOD
Smoke Detectors 10/29/2025 Approved CHRISTOPHER BLACKWOOD
Wood Frame 10/29/2025 Approved CHRISTOPHER BLACKWOOD