7754 N FARRALONE AVE 91304

Certificate Information: 7754 N FARRALONE AVE 91304

Application / Permit
22010-10000-02772
Plan Check / Job No.
B22LA10505
Group
Building
Type
Bldg-Addition
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Accessory Dwelling Unit
Work Description
NEW 2-STORY ADU OF 810.5 SQ.FT. (18'-2" X 36'-4") ATTACHED TO EXISTING GARAGE. THE FIRST FLOOR WILL BE 405.3 SQ.FT. AND THE 2ND FLOOR WILL BE 405.2 SQ.FT. WITH ROOF DECK. “The LID clearance has been deferred. Approval for LID requirements shall be obtained from LASAN prior to the issuance of the Certificate of Occupancy.”
Permit Issued
Issued on 2/14/2023
Issuing Office
Valley
Current Status
CofO Issued on 6/17/2024
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 6/1/2022 APPLICANT
Assigned to Plan Check Engineer 6/30/2022 NGHI SU
Corrections Issued 7/6/2022 NGHI SU
Quality Review Completed 7/6/2022 FARUK SEZER
Building Plans Picked Up 7/20/2022 APPLICANT
Applicant returned to address corrections 12/29/2022 NGHI SU
Plan Check Approved 2/9/2023 NGHI SU
Issued 2/14/2023 APPLICANT
CofO in Progress 1/9/2024 JEFFREY HARTLINE
Permit Finaled 6/17/2024 JOHN JANSON
CofO Issued 6/17/2024 JOHN JANSON
Permit Finaled 6/17/2024 JOHN JANSON

Permit Application Clearance Information

Address approval Cleared 7/28/2022 ROMAN GUTIERREZ
Roof/Waste drainage to street Cleared 7/28/2022 ROMAN GUTIERREZ
Construction near power lines Cleared 11/29/2022 RIDWAN HARDY
Construction within easement Cleared 11/29/2022 RIDWAN HARDY
Eng Process Fee Ord 176,300 Cleared 12/20/2022 MEGAN GODINEZ
Sewer availability Cleared 12/20/2022 MEGAN GODINEZ

Contact Information

Contractor Owner-Builder       ,

Inspector Information

JEFFREY HARTLINE, (818) 774-4320 Office Hours: 7:00-8:00 AM MON-FRI
CHRIS CHRISTENSEN, (818) 774-4320 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

PLUMBING-Rough 3/7/2023 Partial Approval KRISTEN CAUSEY
PLUMBING-Rough 3/8/2023 Partial Approval KRISTEN CAUSEY
Deputy Drilled-In Anchors 3/14/2023 Conditional Approval CHRIS CHRISTENSEN
Excavation/Setback/Form/Re-Bar 3/17/2023 Partial Approval KRISTEN CAUSEY
Floor/Roof Diaphrgm/Shear Wall 5/12/2023 Partial Approval JUSTIN HAWLEY
Footing/Foundation/Slab 6/13/2023 Approved CHRIS CHRISTENSEN
ELECTRICAL-Rough 7/11/2023 Not Ready for Inspection CHRIS CHRISTENSEN
PLUMBING-Rough 7/11/2023 Not Ready for Inspection CHRIS CHRISTENSEN
Wood Frame 7/11/2023 Corrections Issued CHRIS CHRISTENSEN
BUILDING-Rough-Frame 7/14/2023 Corrections Issued CHRIS CHRISTENSEN
ELECTRICAL-Rough 7/14/2023 Approved CHRIS CHRISTENSEN
Floor/Roof Diaphrgm/Shear Wall 7/14/2023 Conditional Approval CHRIS CHRISTENSEN
PLUMBING-Rough 7/14/2023 Approved CHRIS CHRISTENSEN
Wood Frame 7/14/2023 Conditional Approval CHRIS CHRISTENSEN
Interior/Exterior Lathing 8/7/2023 Partial Approval JOHN KIDWELL
Drywall Nailing 8/17/2023 Not Ready for Inspection CHRIS CHRISTENSEN
Green Building Rough 8/17/2023 Not Ready for Inspection CHRIS CHRISTENSEN
Insulation 8/17/2023 Corrections Issued CHRIS CHRISTENSEN
Drywall Nailing 8/22/2023 Approved CHRIS CHRISTENSEN
Green Building Rough 8/22/2023 Approved CHRIS CHRISTENSEN
Insulation 8/22/2023 Approved CHRIS CHRISTENSEN
Interior/Exterior Lathing 8/22/2023 Partial Approval CHRIS CHRISTENSEN
Wood Frame 8/22/2023 Approved CHRIS CHRISTENSEN
Interior/Exterior Lathing 9/18/2023 Approved CHRIS CHRISTENSEN
BUILDING-Rough-Frame 11/9/2023 Not Ready for Inspection JEFFREY HARTLINE
Final 11/9/2023 Corrections Issued JEFFREY HARTLINE
Green Building Final 11/9/2023 Approved JEFFREY HARTLINE
SGSOV-Seismic Gas S/O Valve 11/9/2023 SGSOV Approved JEFFREY HARTLINE
Smoke Detectors 11/9/2023 Approved JEFFREY HARTLINE
BUILDING-Rough-Frame 1/8/2024 Approved JEFFREY HARTLINE
Final 1/8/2024 OK to Issue CofO JEFFREY HARTLINE