8418 W 4TH ST 90048

Certificate Information: 8418 W 4TH ST 90048

Application / Permit
22010-10000-02771
Plan Check / Job No.
B22LA10499
Group
Building
Type
Bldg-New
Sub-Type
1 or 2 Family Dwelling
Primary Use
(23) Miscellaneous Bldg/Structure
Work Description
CONSTRUCTION OF NEW CABANA
Permit Issued
Issued on 8/5/2022
Issuing Office
Current Status
CofO Issued on 4/2/2024
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 6/1/2022 APPLICANT
Assigned to Plan Check Engineer 6/9/2022 JAD BASMA
Corrections Issued 6/11/2022 JAD BASMA
Quality Review Completed 6/17/2022 TEODORO DIAZ RODRIGUEZ
Plan Check Approved 7/12/2022 JAD BASMA
Issued 8/5/2022 APPLICANT
Building Plans Picked Up 8/8/2022 APPLICANT
CofO in Progress 4/2/2024 MEL KHACHATOURIAN
Permit Finaled 4/2/2024 DANIEL ORRANTE
CofO Issued 4/2/2024 DANIEL ORRANTE
Permit Finaled 4/2/2024 DANIEL ORRANTE

Permit Application Clearance Information

Roof/Waste drainage to street Cleared 7/1/2022 WALLIE JONG
Construction near power lines Cleared 7/6/2022 WALTER RAMIREZ
Eng Process Fee Ord 176,300 Cleared 7/11/2022 WALLIE JONG

Contact Information

Contractor Owner-Builder       ,

Inspector Information

WILBER ROSALES, (310) 914-3892 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Excavation/Setback/Form/Re-Bar 9/8/2022 Approved EVAN COOPER
BUILDING-Rough-Frame 6/5/2023 Approved JEREMY TODD
Floor/Roof Diaphrgm/Shear Wall 6/5/2023 Approved JEREMY TODD
Green Building Rough 6/5/2023 Approved JEREMY TODD
METHANE-Rough 6/5/2023 Approved JEREMY TODD
Verify Sprinkler Sign Off 6/5/2023 Approved JEREMY TODD
ELECTRICAL-Rough 6/23/2023 Approved JEREMY TODD
ELECTRICAL-Final 1/17/2024 Partial Approval MEL KHACHATOURIAN
ELECTRICAL-Final 3/12/2024 Approved MEL KHACHATOURIAN
Final 3/12/2024 OK to Issue CofO MEL KHACHATOURIAN
Footing/Foundation/Slab 3/12/2024 Approved MEL KHACHATOURIAN
Green Building Final 3/12/2024 Approved MEL KHACHATOURIAN
METHANE-Barrier 3/12/2024 Approved MEL KHACHATOURIAN
METHANE-Subgrade 3/12/2024 Approved MEL KHACHATOURIAN
SGSOV-Seismic Gas S/O Valve 3/12/2024 SGSOV Approved MEL KHACHATOURIAN
Service/Power Release 3/12/2024 Approved MEL KHACHATOURIAN
Smoke Detectors 3/12/2024 Approved MEL KHACHATOURIAN