2915 N ROSANNA ST 90039
Certificate Information: 2915 N ROSANNA ST 90039
- Application / Permit
- 22010-10000-02757
- Plan Check / Job No.
- B22LA10432
- Group
- Building
- Type
- Bldg-Addition
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Accessory Dwelling Unit
- Work Description
- ePLAN. NEW ATTACHED ACCESSORY DWELLING UNIT TO (E) DETACHED GARAGE.
- Permit Issued
- Issued on 10/31/2022
- Issuing Office
- Current Status
- Issued on 10/31/2022
- Certificate of Occupancy
- Pending More Information
Permit Application Status History
| Submitted | 6/1/2022 | APPLICANT |
| Assigned to Plan Check Engineer | 6/10/2022 | KEVIN MORALES |
| Corrections Issued | 6/13/2022 | KEVIN MORALES |
| Quality Review Completed | 6/15/2022 | EUGENE BARBEAU |
| Applicant returned to address corrections | 9/27/2022 | KEVIN MORALES |
| Plan Check Approved | 10/4/2022 | KEVIN MORALES |
| Issued | 10/31/2022 | APPLICANT |
Permit Application Clearance Information
| Address approval | Cleared | 6/17/2022 | CHRISTOPHER ROCHA |
| Eng Process Fee Ord 176,300 | Cleared | 6/21/2022 | CHRISTOPHER ROCHA |
| Sewer availability | Cleared | 6/21/2022 | CHRISTOPHER ROCHA |
| ZI | Cleared | 7/26/2022 | STEVEN WECHSLER |
| Low Impact Development | Cleared | 9/16/2022 | LONDY ALVARADO |
| Roof/Waste drainage to street | Cleared | 9/16/2022 | CHRISTOPHER ROCHA |
Contact Information
| Contractor | Owner-Builder | , |
Inspector Information
| HAMIK HARTOUNIAN, (213) 202-3275 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Excavation/Setback/Form/Re-Bar | 12/9/2022 | Not Ready for Inspection | THOMAS LOGRASSO |
| Pre-Inspection | 12/9/2022 | Corrections Issued | THOMAS LOGRASSO |
| Underground Mechanical | 12/9/2022 | Not Ready for Inspection | THOMAS LOGRASSO |
| Footing/Foundation/Slab | 2/3/2023 | Approved | THOMAS LOGRASSO |
| PLUMBING-Rough | 2/3/2023 | Partial Approval | THOMAS LOGRASSO |
| Special/Order Compliance | 2/3/2023 | Corrections Issued | THOMAS LOGRASSO |
| Floor/Roof Diaphrgm/Shear Wall | 2/27/2023 | Partial Approval | THOMAS LOGRASSO |
| Floor/Roof Diaphrgm/Shear Wall | 3/10/2023 | Not Ready for Inspection | THOMAS LOGRASSO |
| Floor/Roof Diaphrgm/Shear Wall | 3/16/2023 | Corrections Issued | THOMAS LOGRASSO |
| Deputy Wood Construction | 3/28/2023 | Partial Approval | SCOTT FINNILA |
| ELECTRICAL-Rough | 3/29/2023 | Corrections Issued | THOMAS LOGRASSO |
| Floor/Roof Diaphrgm/Shear Wall | 3/29/2023 | Corrections Issued | THOMAS LOGRASSO |
| Green Building Rough | 3/29/2023 | Not Ready for Inspection | THOMAS LOGRASSO |
| HVAC-Rough | 3/29/2023 | Corrections Issued | THOMAS LOGRASSO |
| MERV13>=Rough | 3/29/2023 | Approved | THOMAS LOGRASSO |
| PLUMBING-Rough | 3/29/2023 | Corrections Issued | THOMAS LOGRASSO |
| BUILDING-Rough-Frame | 4/4/2023 | Not Ready for Inspection | THOMAS LOGRASSO |
| Green Building Rough | 4/4/2023 | Not Ready for Inspection | THOMAS LOGRASSO |
| BUILDING-Rough-Frame | 4/10/2023 | Corrections Issued | THOMAS LOGRASSO |
| Green Building Rough | 4/10/2023 | Approved | THOMAS LOGRASSO |
| Insulation | 4/10/2023 | Corrections Issued | THOMAS LOGRASSO |
| BUILDING-Rough-Frame | 4/19/2023 | Conditional Approval | SCOTT FINNILA |
| Deputy Wood Construction | 4/19/2023 | Conditional Approval | THOMAS LOGRASSO |
| Rough-Elec/Plmb/HVAC | 4/19/2023 | Approved | SCOTT FINNILA |
| Drywall Nailing | 5/1/2023 | Partial Approval | THOMAS LOGRASSO |
| Gas Test | 5/1/2023 | Partial Approval | THOMAS LOGRASSO |
| Interior/Exterior Lathing | 5/1/2023 | Partial Approval | THOMAS LOGRASSO |
| Sewer | 7/19/2023 | Approved | THOMAS LOGRASSO |
| Underground Mechanical | 7/19/2023 | Approved | THOMAS LOGRASSO |