1415 W 35TH PL 90018

Certificate Information: 1415 W 35TH PL 90018

Application / Permit
22010-10000-02755
Plan Check / Job No.
B22LA10422
Group
Building
Type
Bldg-Addition
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Dwelling - Single Family
Work Description
EPLAN ADDITION AND MAJOR REMODEL TO (E) 2 STORY SINGLE FAMILY AT FRONT OF LOT TO BECOME 4 STORIES
Permit Issued
Issued on 6/12/2023
Issuing Office
Current Status
CofO Issued on 8/3/2025
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 6/3/2022 APPLICANT
Assigned to Plan Check Engineer 7/7/2022 JAD BASMA
Corrections Issued 7/14/2022 JAD BASMA
Quality Review Completed 7/22/2022 TEODORO DIAZ RODRIGUEZ
Applicant returned to address corrections 10/27/2022 JAD BASMA
Applicant returned to address corrections 3/11/2023 JAD BASMA
Plan Check Approved 5/16/2023 JAD BASMA
Issued 6/12/2023 APPLICANT
CofO in Progress 7/30/2025 SABAS ALONSO
Permit Finaled 8/3/2025 DEROLD HAUFF
Permit Finaled 8/3/2025 DEROLD HAUFF
CofO Issued 8/3/2025 DEROLD HAUFF

Permit Application Clearance Information

Address approval Cleared 4/25/2023 WALLIE JONG
Eng Process Fee Ord 176,300 Cleared 4/25/2023 WALLIE JONG
Hydrant and Access approval Cleared 4/27/2023 JOHN CONNEALLY
Sewer availability Cleared 4/27/2023 WALLIE JONG
Low Impact Development Cleared 5/10/2023 ANTHONY VARGAS
Roof/Waste drainage to street Cleared 5/10/2023 JEANIE LAM

Contact Information

Contractor Owner-Builder       ,

Inspector Information

SABAS ALONSO, (213) 202-3468 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Excavation/Setback/Form/Re-Bar 11/13/2023 Partial Approval SABAS ALONSO
Excavation/Setback/Form/Re-Bar 12/6/2023 Corrections Issued SABAS ALONSO
Sewer 12/6/2023 Approved SABAS ALONSO
Underground Mechanical 12/6/2023 Partial Approval SABAS ALONSO
Footing/Foundation/Slab 12/19/2023 Partial Approval SABAS ALONSO
METHANE-Subgrade 12/19/2023 Not Ready for Inspection SABAS ALONSO
METHANE-Subgrade 1/17/2024 Approved SABAS ALONSO
Footing/Foundation/Slab 1/23/2024 Approved SABAS ALONSO
METHANE-Barrier 1/23/2024 Approved SABAS ALONSO
Floor/Roof Diaphrgm/Shear Wall 3/19/2024 Partial Approval SABAS ALONSO
Floor/Roof Diaphrgm/Shear Wall 4/16/2024 Partial Approval SABAS ALONSO
Floor/Roof Diaphrgm/Shear Wall 5/9/2024 Partial Approval SABAS ALONSO
Deputy Wood Construction 8/19/2024 Conditional Approval ALEX COLIN
Floor/Roof Diaphrgm/Shear Wall 8/20/2024 Corrections Issued CRAIG DAVIS
Floor/Roof Diaphrgm/Shear Wall 9/19/2024 Approved SABAS ALONSO
PLUMBING-Rough 10/18/2024 Corrections Issued SABAS ALONSO
BUILDING-Rough-Frame 11/14/2024 Not Ready for Inspection SABAS ALONSO
ELECTRICAL-Rough 11/14/2024 Not Ready for Inspection SABAS ALONSO
Green Building Rough 11/14/2024 Not Ready for Inspection SABAS ALONSO
HVAC-Rough 11/14/2024 Not Ready for Inspection SABAS ALONSO
METHANE-Rough 11/14/2024 Not Ready for Inspection SABAS ALONSO
ELECTRICAL-Rough 11/15/2024 Approved SABAS ALONSO
Green Building Rough 11/15/2024 Approved SABAS ALONSO
METHANE-Rough 11/15/2024 Approved SABAS ALONSO
BUILDING-Rough-Frame 11/22/2024 Approved SABAS ALONSO
ELECTRICAL-Rough 11/22/2024 Approved SABAS ALONSO
HVAC-Rough 11/22/2024 Approved SABAS ALONSO
Interior/Exterior Lathing 11/22/2024 Partial Approval SABAS ALONSO
Insulation 11/26/2024 Approved SABAS ALONSO
Drywall Nailing 12/12/2024 Approved SABAS ALONSO
Shower Pan 12/12/2024 Partial Approval SABAS ALONSO
Interior/Exterior Lathing 7/17/2025 Approved SABAS ALONSO
Shower Pan 7/17/2025 Approved SABAS ALONSO
Underground Mechanical 7/17/2025 Approved SABAS ALONSO
Green Building Final 7/24/2025 Approved SABAS ALONSO
SGSOV-Seismic Gas S/O Valve 7/24/2025 SGSOV Approved SABAS ALONSO
Smoke Detectors 7/24/2025 Approved SABAS ALONSO
Final 7/25/2025 Corrections Issued SABAS ALONSO
Final 7/30/2025 OK to Issue CofO SABAS ALONSO