7431 N WHITE OAK AVE 91335
Certificate Information: 7431 N WHITE OAK AVE 91335
- Application / Permit
- 22010-10000-02750
- Plan Check / Job No.
- B22LA10407
- Group
- Building
- Type
- Bldg-New
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Accessory Dwelling Unit
- Work Description
- eplan NEW DET. 2-STORY ADU PER LAMC 12.22 A.33 (c)-(d)
- Permit Issued
- Issued on 9/18/2023
- Issuing Office
- Current Status
- Issued on 9/18/2023
- Certificate of Occupancy
- Pending More Information
Permit Application Status History
| Submitted | 6/1/2022 | APPLICANT |
| Assigned to Plan Check Engineer | 6/30/2022 | MAHNAZ NOURHASHEMI |
| Corrections Issued | 7/8/2022 | MAHNAZ NOURHASHEMI |
| Quality Review Completed | 7/19/2022 | TEODORO DIAZ RODRIGUEZ |
| Plan Check Approved | 12/15/2022 | MAHNAZ NOURHASHEMI |
| Issued | 9/18/2023 | APPLICANT |
Permit Application Clearance Information
| Address approval | Cleared | 7/20/2022 | MEGAN GODINEZ |
| Eng Process Fee Ord 176,300 | Cleared | 8/2/2022 | MEGAN GODINEZ |
| Sewer availability | Cleared | 8/2/2022 | MEGAN GODINEZ |
| Hydrant and Access approval | Cleared | 8/26/2022 | MATTHEW CRAIG |
| Miscellaneous | Cleared | 9/6/2022 | CLAUDE GOODING |
| Roof/Waste drainage to street | Cleared | 9/29/2022 | ROMAN GUTIERREZ |
| Low Impact Development | Cleared | 10/19/2022 | DEBORA LEITE |
Contact Information
| Contractor | Owner-Builder | , |
| Engineer | Le,, Thang Huu; Lic. No.: NA4978 | , |
Inspector Information
| ARUTYUN MADATYAN, (818) 774-4307 | Office Hours: 7:00-8:00 AM MON-FRI |
| JUAN ALVARADO, (818) 774-4307 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| PLUMBING-Rough | 11/9/2023 | Partial Approval | ALEXANDER HANDY |
| Excavation/Setback/Form/Re-Bar | 11/13/2023 | Approved | JEFFREY BULL |
| Deputy Drilled-In Anchors | 11/28/2023 | Approved | JEFFREY BULL |
| Deputy Wood Construction | 11/28/2023 | Approved | JEFFREY BULL |
| Floor/Roof Diaphrgm/Shear Wall | 11/29/2023 | Partial Approval | JEFFREY BULL |
| Deputy Wood Construction | 12/20/2023 | Conditional Approval | JEFFREY BULL |
| ELECTRICAL-Rough | 3/20/2024 | Approved | JEFFREY BULL |
| HVAC-Rough | 3/20/2024 | Approved | JEFFREY BULL |
| PLUMBING-Rough | 3/20/2024 | Approved | JEFFREY BULL |
| Interior/Exterior Lathing | 4/15/2024 | Partial Approval | JEFFREY BULL |
| Insulation | 4/29/2024 | Approved | JEFFREY BULL |
| Drywall Nailing | 5/16/2024 | Approved | JEFFREY BULL |
| Interior/Exterior Lathing | 5/16/2024 | Approved | JEFFREY BULL |
| Underground Mechanical | 9/20/2024 | Partial Approval | JEFFREY BULL |
| Underground Mechanical | 10/3/2024 | Approved | JEFFREY BULL |