9626 W CRESTA DR 90035

Certificate Information: 9626 W CRESTA DR 90035

Application / Permit
22010-10000-02745
Plan Check / Job No.
B22LA10403
Group
Building
Type
Bldg-Alter/Repair
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Accessory Dwelling Unit
Work Description
ePlan: CONVERT (E) GARAGE TO 1-STORY ACCESSORY DWELLING UNIT PER CA Govt. Code 65852.2(e)(1)(A)
Permit Issued
Issued on 11/17/2022
Issuing Office
Current Status
CofO Issued on 2/22/2024
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 5/31/2022 APPLICANT
Assigned to Plan Check Engineer 6/10/2022 DANIEL YIP
Corrections Issued 6/12/2022 DANIEL YIP
Quality Review Completed 7/1/2022 GARO TELMI
Applicant returned to address corrections 9/26/2022 DANIEL YIP
Plan Check Approved 10/20/2022 DANIEL YIP
No Progress 11/9/2022 DANIEL YIP
Plan Check Approved 11/9/2022 DANIEL YIP
Issued 11/17/2022 APPLICANT
CofO in Progress 2/12/2024 OGANES TARAKHCHYAN
Permit Finaled 2/22/2024 DANIEL ORRANTE
CofO Issued 2/22/2024 DANIEL ORRANTE
Permit Finaled 2/22/2024 DANIEL ORRANTE

Permit Application Clearance Information

Address approval Cleared 9/14/2022 HISASHI KOBAYAKAWA
Construction near power lines Cleared 9/14/2022 WALTER RAMIREZ
Sewer availability Cleared 9/14/2022 HISASHI KOBAYAKAWA
Eng Process Fee Ord 176,300 Cleared 9/19/2022 HISASHI KOBAYAKAWA

Contact Information

Contractor Nittay Inc; Lic. No.: 1033506-B       ,
Contractor P M A Renovations; Lic. No.: 1033506-B       ,
Engineer Dominguez,, Refugio; Lic. No.: C50820 254 COTTONWOOD ST      ONTARIO, CA 91761

Inspector Information

ASHLEY THOMPSON, (310) 914-3897 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Footing/Foundation/Slab 11/21/2022 Corrections Issued OGANES TARAKHCHYAN
Footing/Foundation/Slab 11/28/2022 Approved OGANES TARAKHCHYAN
Underground Mechanical 11/28/2022 Partial Approval OGANES TARAKHCHYAN
HVAC-Rough 3/21/2023 Corrections Issued ASHLEY THOMPSON
PLUMBING-Rough 3/21/2023 Corrections Issued ASHLEY THOMPSON
Floor/Roof Diaphrgm/Shear Wall 3/24/2023 Approved ASHLEY THOMPSON
HVAC-Rough 3/24/2023 Corrections Issued ASHLEY THOMPSON
PLUMBING-Rough 3/24/2023 Not Ready for Inspection ASHLEY THOMPSON
HVAC-Rough 3/31/2023 Not Ready for Inspection JEREMY TODD
PLUMBING-Rough 3/31/2023 Corrections Issued JEREMY TODD
Shower Pan 4/14/2023 Approved CLAYTON GRAHAM
HVAC-Rough 4/24/2023 Conditional Approval JEREMY TODD
Interior/Exterior Lathing 4/24/2023 Approved JEREMY TODD
PLUMBING-Rough 4/24/2023 Conditional Approval JEREMY TODD
Interior/Exterior Lathing 5/1/2023 Not Ready for Inspection CLAYTON GRAHAM
Interior/Exterior Lathing 5/4/2023 Approved JEREMY TODD
ELECTRICAL-Rough 5/19/2023 Approved CLAYTON GRAHAM
HVAC-Rough 6/5/2023 Not Ready for Inspection CHRISTOPHER WILSON
Insulation 6/5/2023 Corrections Issued CHRISTOPHER WILSON
PLUMBING-Rough 6/5/2023 Not Ready for Inspection CHRISTOPHER WILSON
BUILDING-Rough-Frame 6/7/2023 Not Ready for Inspection CLAYTON GRAHAM
Floor/Roof Diaphrgm/Shear Wall 6/7/2023 Corrections Issued CLAYTON GRAHAM
Wood Frame 6/7/2023 Corrections Issued CLAYTON GRAHAM
Insulation 6/9/2023 Not Ready for Inspection CLAYTON GRAHAM
Insulation 6/13/2023 Approved CLAYTON GRAHAM
Floor/Roof Diaphrgm/Shear Wall 6/20/2023 Partial Approval JEREMY TODD
Wood Frame 6/20/2023 Corrections Issued JEREMY TODD
Deputy Wood Construction 6/23/2023 Conditional Approval DAVID FEILER
Drywall Nailing 6/23/2023 Not Ready for Inspection JESUS PINEDA
Deputy Drilled-In Anchors 6/30/2023 Approved JEREMY TODD
Floor/Roof Diaphrgm/Shear Wall 6/30/2023 Not Ready for Inspection JEREMY TODD
Wood Frame 7/7/2023 Not Ready for Inspection ARAM AVEDISIAN
ELECTRICAL-Rough 7/25/2023 Corrections Issued CLAYTON GRAHAM
Wood Frame 7/25/2023 Corrections Issued CLAYTON GRAHAM
Floor/Roof Diaphrgm/Shear Wall 7/28/2023 Not Ready for Inspection CLAYTON GRAHAM
Special/Order Compliance 8/1/2023 Corrections Issued CLAYTON GRAHAM
BUILDING-Rough-Frame 8/2/2023 Partial Approval CLAYTON GRAHAM
Green Building Rough 8/2/2023 Not Ready for Inspection CLAYTON GRAHAM
HVAC-Rough 8/22/2023 Approved CLAYTON GRAHAM
PLUMBING-Rough 8/22/2023 Approved CLAYTON GRAHAM
Insulation 8/23/2023 Not Ready for Inspection BRENDAN LOONEY
Wood Frame 8/23/2023 Corrections Issued BRENDAN LOONEY
BUILDING-Rough-Frame 8/29/2023 Partial Approval CLAYTON GRAHAM
Green Building Rough 8/29/2023 Approved CLAYTON GRAHAM
Insulation 8/29/2023 Approved CLAYTON GRAHAM
Drywall Nailing 9/5/2023 Corrections Issued CLAYTON GRAHAM
BUILDING-Rough-Frame 12/26/2023 Approved MEL KHACHATOURIAN
Drywall Nailing 12/26/2023 Not Ready for Inspection MEL KHACHATOURIAN
Final 12/26/2023 Not Ready for Inspection MEL KHACHATOURIAN
METHANE-Final 12/26/2023 Not Ready for Inspection MEL KHACHATOURIAN
SGSOV-Seismic Gas S/O Valve 12/26/2023 SGSOV Not Ready MEL KHACHATOURIAN
Smoke Detectors 12/26/2023 Not Ready for Inspection MEL KHACHATOURIAN
SGSOV-Seismic Gas S/O Valve 1/3/2024 SGSOV Not Ready OGANES TARAKHCHYAN
HVAC-Final 1/10/2024 Approved OGANES TARAKHCHYAN
PLUMBING-Final 1/10/2024 Approved OGANES TARAKHCHYAN
ELECTRICAL-Final 1/12/2024 Approved OGANES TARAKHCHYAN
Smoke Detectors 1/12/2024 Not Ready for Inspection OGANES TARAKHCHYAN
Drywall Nailing 1/30/2024 Approved OGANES TARAKHCHYAN
Final 1/30/2024 Corrections Issued OGANES TARAKHCHYAN
METHANE-Final 1/30/2024 Approved OGANES TARAKHCHYAN
SGSOV-Seismic Gas S/O Valve 1/30/2024 SGSOV Approved OGANES TARAKHCHYAN
Smoke Detectors 1/30/2024 Approved OGANES TARAKHCHYAN
Final 2/2/2024 Not Ready for Inspection OGANES TARAKHCHYAN
Final 2/9/2024 OK to Issue CofO OGANES TARAKHCHYAN