1530 W 223RD ST 90501

Certificate Information: 1530 W 223RD ST 90501

Application / Permit
22010-10000-02727
Plan Check / Job No.
B22LA10317
Group
Building
Type
Bldg-New
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Accessory Dwelling Unit
Work Description
ePlan 1. NEW 495-SF DETACHED ACCESSORY DWELLING UNIT (ADU) IN THE BACK Per Ordinance and LAMC 12.22 A 33(c) &(d) . 2. NEW 100-AMP ELECTRICAL PANEL FOR THE NEW ADU.
Permit Issued
Issued on 5/1/2023
Issuing Office
Current Status
CofO Issued on 11/18/2024
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 5/31/2022 APPLICANT
Assigned to Plan Check Engineer 6/6/2022 ZAW HAN
Corrections Issued 6/9/2022 ZAW HAN
Plan Check Approved 2/8/2023 ZAW HAN
Issued 5/1/2023 APPLICANT
CofO in Progress 11/15/2024 EUGENE CASSIDY
Permit Finaled 11/18/2024 ANSON MAGLASANG
CofO Issued 11/18/2024 ANSON MAGLASANG
Permit Finaled 11/18/2024 ANSON MAGLASANG

Permit Application Clearance Information

Address approval Cleared 7/1/2022 HUGO LOPEZ
Eng Process Fee Ord 176,300 Cleared 7/6/2022 HUGO LOPEZ
Sewer availability Cleared 9/27/2022 HUGO LOPEZ
Low Impact Development Cleared 12/9/2022 MITESH PATEL
Roof/Waste drainage to street Cleared 2/7/2023 HUGO LOPEZ

Contact Information

Contractor Land Forever Construction Inc; Lic. No.: 1044254-B       ,
Engineer Wang,, Ting-Wei; Lic. No.: C91854 4541 MYRA AVE      CYPRESS, CA 90630
Engineer Wang,, Ting-Wei; Lic. No.: NA91854       ,

Inspector Information

EUGENE CASSIDY, (310) 548-2508 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Excavation/Setback/Form/Re-Bar 5/26/2023 Corrections Issued EUGENE CASSIDY
Excavation/Setback/Form/Re-Bar 6/1/2023 Corrections Issued EUGENE CASSIDY
Excavation/Setback/Form/Re-Bar 6/13/2023 Approved EUGENE CASSIDY
Underground Mechanical 6/30/2023 Partial Approval EUGENE CASSIDY
BUILDING-Rough-Frame 8/9/2023 Partial Approval EUGENE CASSIDY
METHANE-Rough 8/9/2023 Approved EUGENE CASSIDY
Verify Sprinkler Sign Off 8/9/2023 Approved EUGENE CASSIDY
PLUMBING-Rough 8/22/2023 Partial Approval EUGENE CASSIDY
BUILDING-Rough-Frame 8/28/2023 Partial Approval EUGENE CASSIDY
BUILDING-Rough-Frame 9/7/2023 Partial Approval EUGENE CASSIDY
BUILDING-Rough-Frame 10/26/2023 Corrections Issued EUGENE CASSIDY
Rough-Elec/Plmb/HVAC 10/26/2023 Approved EUGENE CASSIDY
BUILDING-Rough-Frame 11/2/2023 Approved EUGENE CASSIDY
Deputy Wood Construction 11/2/2023 Approved EUGENE CASSIDY
Insulation 11/2/2023 Approved EUGENE CASSIDY
Drywall Nailing 11/13/2023 Approved EUGENE CASSIDY
Interior/Exterior Lathing 11/13/2023 Approved EUGENE CASSIDY
ELECTRICAL-Final 6/13/2024 Not Ready for Inspection EUGENE CASSIDY
Final 6/13/2024 Corrections Issued EUGENE CASSIDY
Footing/Foundation/Slab 6/13/2024 Approved EUGENE CASSIDY
HVAC-Final 6/13/2024 Not Ready for Inspection EUGENE CASSIDY
METHANE-Barrier 6/13/2024 Approved EUGENE CASSIDY
METHANE-Subgrade 6/13/2024 Approved EUGENE CASSIDY
PLUMBING-Final 6/13/2024 Approved EUGENE CASSIDY
SGSOV-Seismic Gas S/O Valve 6/13/2024 SGSOV Not Ready EUGENE CASSIDY
Service/Power Release 6/13/2024 Not Required EUGENE CASSIDY
Smoke Detectors 6/13/2024 Not Ready for Inspection EUGENE CASSIDY
Final 9/19/2024 Not Ready for Inspection JOSEPH MCGARRY
Smoke Detectors 9/19/2024 Approved JOSEPH MCGARRY
ELECTRICAL-Final 11/8/2024 Not Ready for Inspection EUGENE CASSIDY
Final 11/8/2024 Corrections Issued EUGENE CASSIDY
SGSOV-Seismic Gas S/O Valve 11/8/2024 SGSOV Approved EUGENE CASSIDY
Service/Power Release 11/8/2024 Not Required EUGENE CASSIDY
ELECTRICAL-Final 11/14/2024 Approved EUGENE CASSIDY
Final 11/14/2024 OK to Issue CofO EUGENE CASSIDY
HVAC-Final 11/14/2024 Approved EUGENE CASSIDY
Service/Power Release 11/14/2024 Not Required EUGENE CASSIDY