2344 E GATEWOOD ST 90031
Certificate Information: 2344 E GATEWOOD ST 90031
- Application / Permit
- 22010-10000-02726
- Plan Check / Job No.
- B22LA10316
- Group
- Building
- Type
- Bldg-New
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Accessory Dwelling Unit
- Work Description
- ePlan New 2-story detached ADU - 1,193 SF per ordinance
- Permit Issued
- Issued on 8/24/2023
- Issuing Office
- Current Status
- CofO Issued on 5/6/2025
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 5/31/2022 | APPLICANT |
| Assigned to Plan Check Engineer | 6/30/2022 | JAD BASMA |
| Corrections Issued | 7/6/2022 | JAD BASMA |
| Quality Review Completed | 7/8/2022 | GARO TELMI |
| Applicant returned to address corrections | 3/1/2023 | JAD BASMA |
| Applicant returned to address corrections | 4/7/2023 | JAD BASMA |
| Plan Check Approved | 8/2/2023 | JAD BASMA |
| No Progress | 8/16/2023 | JAD BASMA |
| Plan Check Approved | 8/16/2023 | JAD BASMA |
| Issued | 8/24/2023 | APPLICANT |
| CofO in Progress | 5/5/2025 | HAMIK HARTOUNIAN |
| Permit Finaled | 5/6/2025 | DEROLD HAUFF |
| CofO Issued | 5/6/2025 | DEROLD HAUFF |
| Permit Finaled | 5/6/2025 | DEROLD HAUFF |
Permit Application Clearance Information
| Construction near power lines | Cleared | 1/27/2023 | RIDWAN HARDY |
| Address approval | Cleared | 1/31/2023 | CINDY QI |
| Eng Process Fee Ord 176,300 | Cleared | 2/9/2023 | CINDY QI |
| Sewer availability | Cleared | 2/9/2023 | CINDY QI |
| Low Impact Development | Cleared | 7/13/2023 | SARAH YOUSSEF |
| Roof/Waste drainage to street | Cleared | 7/18/2023 | WALLIE JONG |
| ZI | Cleared | 7/18/2023 | ANACANY HURTADO |
Contact Information
| Architect | Tam,, Anthony G; Lic. No.: NA32145 | , |
| Contractor | C M G Development; Lic. No.: 1083438-B | , |
| Engineer | Phan,, Phillip Trung Tri; Lic. No.: C76425 | 641 S ALMIRANTE DR WEST COVINA, CA 91791 |
Inspector Information
| HAMIK HARTOUNIAN, (213) 202-3275 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Pre-Inspection | 9/1/2023 | Partial Inspection | THOMAS LOGRASSO |
| Footing/Foundation/Slab | 10/3/2023 | Not Ready for Inspection | ALIZAH MAYAGOITIA |
| Excavation/Setback/Form/Re-Bar | 10/4/2023 | Not Ready for Inspection | THOMAS LOGRASSO |
| Sewer | 10/4/2023 | Approved | THOMAS LOGRASSO |
| Excavation/Setback/Form/Re-Bar | 10/6/2023 | Corrections Issued | THOMAS LOGRASSO |
| Excavation/Setback/Form/Re-Bar | 10/11/2023 | Partial Approval | JEFFREY MEAD |
| Excavation/Setback/Form/Re-Bar | 10/25/2023 | Partial Approval | KATHRYN BUTTERWORTH |
| Floor/Roof Diaphrgm/Shear Wall | 11/14/2023 | Not Ready for Inspection | THOMAS LOGRASSO |
| Floor/Roof Diaphrgm/Shear Wall | 11/29/2023 | Partial Approval | THOMAS LOGRASSO |
| PLUMBING-Rough | 11/29/2023 | Partial Approval | THOMAS LOGRASSO |
| Floor/Roof Diaphrgm/Shear Wall | 12/1/2023 | Approved | RONNIE MINDANAO |
| Floor/Roof Diaphrgm/Shear Wall | 12/19/2023 | Corrections Issued | THOMAS LOGRASSO |
| Floor/Roof Diaphrgm/Shear Wall | 2/9/2024 | Corrections Issued | THOMAS LOGRASSO |
| HVAC-Rough | 2/26/2024 | Not Ready for Inspection | THOMAS LOGRASSO |
| PLUMBING-Rough | 2/26/2024 | Approved | THOMAS LOGRASSO |
| BUILDING-Rough-Frame | 3/19/2024 | Corrections Issued | THOMAS LOGRASSO |
| ELECTRICAL-Rough | 3/19/2024 | Approved | THOMAS LOGRASSO |
| HVAC-Rough | 3/19/2024 | Corrections Issued | THOMAS LOGRASSO |
| MERV13>=Rough | 3/19/2024 | Approved | THOMAS LOGRASSO |
| BUILDING-Rough-Frame | 4/1/2024 | Partial Approval | THOMAS LOGRASSO |
| HVAC-Rough | 4/1/2024 | Approved | THOMAS LOGRASSO |
| Insulation | 4/1/2024 | Conditional Approval | THOMAS LOGRASSO |
| Interior/Exterior Lathing | 4/1/2024 | Partial Approval | THOMAS LOGRASSO |
| Drywall Nailing | 4/15/2024 | Conditional Approval | THOMAS LOGRASSO |
| Interior/Exterior Lathing | 5/20/2024 | Partial Approval | HAMIK HARTOUNIAN |
| Underground Mechanical | 7/15/2024 | Approved | HAMIK HARTOUNIAN |
| Excavation/Setback/Form/Re-Bar | 7/18/2024 | Approved | HAMIK HARTOUNIAN |
| Pre-Inspection | 7/18/2024 | Partial Inspection | HAMIK HARTOUNIAN |
| BUILDING-Rough-Frame | 8/1/2024 | Approved | SCOTT FINNILA |
| Service/Power Release | 10/7/2024 | Not Ready for Inspection | HAMIK HARTOUNIAN |
| Final | 11/26/2024 | Not Ready for Inspection | JOHN QUINTANILLA |
| Footing/Foundation/Slab | 11/26/2024 | Approved | JOHN QUINTANILLA |
| MERV13>=Final | 11/26/2024 | No Access for Inspection | JOHN QUINTANILLA |
| SGSOV-Seismic Gas S/O Valve | 11/26/2024 | SGSOV Approved | JOHN QUINTANILLA |
| Service/Power Release | 11/26/2024 | Not Ready for Inspection | JOHN QUINTANILLA |
| Smoke Detectors | 11/26/2024 | Approved | JOHN QUINTANILLA |
| Final | 12/2/2024 | Corrections Issued | LUIS CASTRO |
| MERV13>=Final | 12/2/2024 | Corrections Issued | LUIS CASTRO |
| Service/Power Release | 12/2/2024 | Corrections Issued | LUIS CASTRO |
| Final | 12/12/2024 | Corrections Issued | HAMIK HARTOUNIAN |
| MERV13>=Final | 12/12/2024 | Not Ready for Inspection | HAMIK HARTOUNIAN |
| Service/Power Release | 12/12/2024 | Not Ready for Inspection | HAMIK HARTOUNIAN |
| Final | 12/17/2024 | Not Ready for Inspection | HAMIK HARTOUNIAN |
| MERV13>=Final | 12/17/2024 | Not Ready for Inspection | HAMIK HARTOUNIAN |
| Service/Power Release | 12/17/2024 | Not Ready for Inspection | HAMIK HARTOUNIAN |
| Final | 12/20/2024 | Corrections Issued | OSVALDO PARAMO |
| MERV13>=Final | 12/20/2024 | Approved | OSVALDO PARAMO |
| Service/Power Release | 12/20/2024 | Not Ready for Inspection | OSVALDO PARAMO |
| Final | 1/17/2025 | Corrections Issued | OSVALDO PARAMO |
| Service/Power Release | 1/17/2025 | Approved | OSVALDO PARAMO |
| Final | 1/23/2025 | Corrections Issued | HAMIK HARTOUNIAN |
| Final | 4/25/2025 | Partial Inspection | HAMIK HARTOUNIAN |
| Final | 5/5/2025 | OK to Issue CofO | HAMIK HARTOUNIAN |