1234 W O'FARRELL ST 90732
Certificate Information: 1234 W O'FARRELL ST 90732
- Application / Permit
- 22010-10000-02725
- Plan Check / Job No.
- B22LA10315
- Group
- Building
- Type
- Bldg-Addition
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Accessory Dwelling Unit
- Work Description
- ePlan Addition of (E) garage (From 210 SF to 400SF) and adding a second story 1 bedroom ADU (400 SF)
- Permit Issued
- Issued on 6/23/2023
- Issuing Office
- Current Status
- CofO Issued on 4/15/2024
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 5/31/2022 | APPLICANT |
| Assigned to Plan Check Engineer | 6/30/2022 | JAD BASMA |
| Corrections Issued | 7/5/2022 | JAD BASMA |
| Quality Review Completed | 7/13/2022 | TEODORO DIAZ RODRIGUEZ |
| Applicant returned to address corrections | 1/30/2023 | JAD BASMA |
| Applicant returned to address corrections | 2/27/2023 | JAD BASMA |
| Applicant returned to address corrections | 3/17/2023 | JAD BASMA |
| Applicant returned to address corrections | 5/10/2023 | JAD BASMA |
| Applicant returned to address corrections | 6/1/2023 | JAD BASMA |
| Applicant returned to address corrections | 6/21/2023 | JAD BASMA |
| Plan Check Approved | 6/23/2023 | JAD BASMA |
| Issued | 6/23/2023 | APPLICANT |
| CofO in Progress | 4/14/2024 | EUGENE CASSIDY |
| Permit Finaled | 4/15/2024 | ANSON MAGLASANG |
| CofO Issued | 4/15/2024 | ANSON MAGLASANG |
| Permit Finaled | 4/15/2024 | ANSON MAGLASANG |
Permit Application Clearance Information
| Address approval | Cleared | 2/9/2023 | ANA SORIANO |
| Roof/Waste drainage to street | Cleared | 2/9/2023 | ANA SORIANO |
| Eng Process Fee Ord 176,300 | Cleared | 2/13/2023 | ANA SORIANO |
| Sewer availability | Cleared | 2/13/2023 | ANA SORIANO |
| Grading Pre-Inspection | Cleared | 5/23/2023 | SERGIO VALENZUELA |
Contact Information
| Contractor | Owner-Builder | , |
| Engineer | Sin,, John Paul; Lic. No.: C91162 | 122 N GRAMERCY PL LOS ANGELES, CA 90004 |
Inspector Information
| JOSEPH MCGARRY, (310) 732-4559 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Underground Mechanical | 7/21/2023 | Partial Approval | ANSON MAGLASANG |
| Footing/Foundation/Slab | 8/10/2023 | Corrections Issued | JAMES CHAVEZ |
| Footing/Foundation/Slab | 8/16/2023 | Approved | ANSON MAGLASANG |
| Floor/Roof Diaphrgm/Shear Wall | 9/7/2023 | Partial Approval | JAMES CHAVEZ |
| Wood Frame | 9/7/2023 | Partial Approval | JAMES CHAVEZ |
| Interior/Exterior Lathing | 9/11/2023 | Partial Approval | JAMES CHAVEZ |
| BUILDING-Rough-Frame | 10/2/2023 | Not Ready for Inspection | JAMES CHAVEZ |
| Floor/Roof Diaphrgm/Shear Wall | 10/2/2023 | Partial Approval | JAMES CHAVEZ |
| BUILDING-Rough-Frame | 10/26/2023 | Partial Approval | ANSON MAGLASANG |
| Rough-Elec/Plmb/HVAC | 10/26/2023 | Corrections Issued | ANSON MAGLASANG |
| BUILDING-Rough-Frame | 11/9/2023 | Corrections Issued | EUGENE CASSIDY |
| ELECTRICAL-Rough | 11/9/2023 | Approved | EUGENE CASSIDY |
| PLUMBING-Rough | 11/9/2023 | Approved | EUGENE CASSIDY |
| Rough-Elec/Plmb/HVAC | 11/9/2023 | Approved | EUGENE CASSIDY |
| BUILDING-Rough-Frame | 11/22/2023 | Approved | EUGENE CASSIDY |
| Insulation | 11/22/2023 | Approved | EUGENE CASSIDY |
| Interior/Exterior Lathing | 11/22/2023 | Partial Approval | EUGENE CASSIDY |
| Drywall Nailing | 12/1/2023 | Approved | ANSON MAGLASANG |
| Shower Pan | 12/1/2023 | Approved | ANSON MAGLASANG |
| Final | 2/2/2024 | Corrections Issued | JAMES CHAVEZ |
| Final | 2/14/2024 | Corrections Issued | ANSON MAGLASANG |
| SGSOV-Seismic Gas S/O Valve | 2/14/2024 | SGSOV Not Ready | ANSON MAGLASANG |
| Service/Power Release | 2/14/2024 | Not Ready for Inspection | ANSON MAGLASANG |
| Smoke Detectors | 2/14/2024 | Not Ready for Inspection | ANSON MAGLASANG |
| Final | 3/26/2024 | Corrections Issued | EUGENE CASSIDY |
| SGSOV-Seismic Gas S/O Valve | 3/26/2024 | SGSOV Approved | EUGENE CASSIDY |
| Service/Power Release | 3/26/2024 | Not Ready for Inspection | EUGENE CASSIDY |
| Smoke Detectors | 3/26/2024 | Approved | EUGENE CASSIDY |
| Final | 4/9/2024 | Corrections Issued | EUGENE CASSIDY |
| Service/Power Release | 4/9/2024 | Approved | EUGENE CASSIDY |
| ELECTRICAL-Final | 4/12/2024 | Approved | EUGENE CASSIDY |
| Final | 4/12/2024 | OK to Issue CofO | EUGENE CASSIDY |
| HVAC-Final | 4/12/2024 | Approved | EUGENE CASSIDY |
| PLUMBING-Final | 4/12/2024 | Approved | EUGENE CASSIDY |