3003 N FINCH ST 90039

Certificate Information: 3003 N FINCH ST 90039

Application / Permit
22010-10000-02685
Plan Check / Job No.
B22LA10037
Group
Building
Type
Bldg-New
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Accessory Dwelling Unit
Work Description
NEW DETACHED ADU IN REAR PER CA GOVT CODE 65852.2(e)(1)(B) and LAMC 12.22A.33(c)-(d)
Permit Issued
Issued on 9/2/2022
Issuing Office
Metro
Current Status
Issued on 9/2/2022
Certificate of Occupancy
Pending More Information

Permit Application Status History

Submitted 5/25/2022 APPLICANT
Assigned to Plan Check Engineer 6/9/2022 ADRIANA LOPEZ
Corrections Issued 6/16/2022 ADRIANA LOPEZ
Quality Review Completed 6/24/2022 KEN GILL
Building Plans Picked Up 6/27/2022 APPLICANT
Plan Check Approved 8/25/2022 ADRIANA LOPEZ
Issued 9/2/2022 APPLICANT

Permit Application Clearance Information

Address approval Cleared 7/1/2022 JEANIE LAM
Roof/Waste drainage to street Cleared 7/1/2022 JEANIE LAM
Eng Process Fee Ord 176,300 Cleared 7/7/2022 JEANIE LAM
Sewer availability Cleared 7/7/2022 JEANIE LAM
Hydrant and Access approval Cleared 8/2/2022 KURT CORRAL
ZI Cleared 8/10/2022 NOAH MCCOY

Contact Information

Contractor Legacy Builders & Remodeling Inc; Lic. No.: 1046784-B 13506 ALANWOOD ROAD      LA PUENTE, CA 91746
Engineer Barakat,, Fouad Chafic; Lic. No.: C67449 11 CEDARWOOD DR      POMONA, CA 91766

Inspector Information

NICHOLAS LOPEZ, (213) 202-3224 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Excavation/Setback/Form/Re-Bar 9/28/2022 Not Ready for Inspection HAMIK HARTOUNIAN
PLUMBING-Rough 9/28/2022 Partial Approval HAMIK HARTOUNIAN
Excavation/Setback/Form/Re-Bar 10/3/2022 Approved HAMIK HARTOUNIAN
Footing/Foundation/Slab 10/3/2022 Approved HAMIK HARTOUNIAN
Wood Frame 10/17/2022 Not Ready for Inspection HAMIK HARTOUNIAN
Floor/Roof Diaphrgm/Shear Wall 10/24/2022 Partial Approval HAMIK HARTOUNIAN
Floor/Roof Diaphrgm/Shear Wall 11/21/2022 Corrections Issued STUART CHAPMAN
ELECTRICAL-Rough 11/30/2022 Approved HAMIK HARTOUNIAN
Floor/Roof Diaphrgm/Shear Wall 11/30/2022 No Access for Inspection HAMIK HARTOUNIAN
Green Building Rough 11/30/2022 Not Ready for Inspection HAMIK HARTOUNIAN
MERV13>=Rough 11/30/2022 Not Ready for Inspection HAMIK HARTOUNIAN
PLUMBING-Rough 11/30/2022 Approved HAMIK HARTOUNIAN
Verify Sprinkler Sign Off 11/30/2022 Not Ready for Inspection HAMIK HARTOUNIAN
Interior/Exterior Lathing 12/7/2022 Approved HAMIK HARTOUNIAN
Insulation 12/13/2022 Approved HAMIK HARTOUNIAN
Drywall Nailing 12/20/2022 Conditional Approval HAMIK HARTOUNIAN
Green Building Rough 12/20/2022 Corrections Issued HAMIK HARTOUNIAN
Interior/Exterior Lathing 12/20/2022 Partial Approval HAMIK HARTOUNIAN
Shower Pan 12/20/2022 Conditional Approval HAMIK HARTOUNIAN
BUILDING-Rough-Frame 4/21/2023 Approved SCOTT FINNILA
Drywall Nailing 4/21/2023 Approved SCOTT FINNILA
Final 4/21/2023 Corrections Issued SCOTT FINNILA
Green Building Final 4/21/2023 Approved SCOTT FINNILA
Green Building Rough 4/21/2023 Approved SCOTT FINNILA
MERV13>=Final 4/21/2023 Approved SCOTT FINNILA
MERV13>=Rough 4/21/2023 Approved SCOTT FINNILA
PLUMBING-Final 4/21/2023 Approved SCOTT FINNILA
SGSOV-Seismic Gas S/O Valve 4/21/2023 SGSOV Approved SCOTT FINNILA
Service/Power Release 4/21/2023 Corrections Issued SCOTT FINNILA
Smoke Detectors 4/21/2023 Approved SCOTT FINNILA
Verify Sprinkler Sign Off 4/21/2023 Approved SCOTT FINNILA
Final 5/4/2023 Not Ready for Inspection SCOTT FINNILA
Service/Power Release 5/4/2023 Not Ready for Inspection SCOTT FINNILA
Final 8/15/2023 Not Ready for Inspection HAMIK HARTOUNIAN
Final 8/23/2023 Corrections Issued HAMIK HARTOUNIAN
Service/Power Release 8/23/2023 Not Required HAMIK HARTOUNIAN
Pre-Inspection 2/19/2026 Corrections Issued NICHOLAS LOPEZ