1515 S REEVES ST 90035

Certificate Information: 1515 S REEVES ST 90035

Application / Permit
22010-10000-02678
Plan Check / Job No.
B22LA10003
Group
Building
Type
Bldg-New
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Dwelling - Single Family
Work Description
NEW 2-STORY SFD WITH ATTACHED 2-CAR GARAGE
Permit Issued
Issued on 7/12/2023
Issuing Office
Current Status
CofO Issued on 5/20/2025
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 5/25/2022 APPLICANT
Assigned to Plan Check Engineer 6/9/2022 MAHNAZ NOURHASHEMI
Corrections Issued 6/14/2022 MAHNAZ NOURHASHEMI
Quality Review Completed 6/14/2022 SAI KHUM
Building Plans Picked Up 6/15/2022 APPLICANT
Plan Check Approved 7/11/2023 MAHNAZ NOURHASHEMI
Issued 7/12/2023 APPLICANT
CofO in Progress 5/16/2025 EVAN COOPER
Permit Finaled 5/20/2025 RICHARD STEINBACH
CofO Issued 5/20/2025 RICHARD STEINBACH
Permit Finaled 5/20/2025 RICHARD STEINBACH

Permit Application Clearance Information

Permit Cleared 8/8/2022 CATHERINE ADROVER
Sewer availability Cleared 8/8/2022 CATHERINE ADROVER
Low Impact Development Cleared 9/8/2022 MITESH PATEL
Eng Process Fee Ord 176,300 Cleared 9/12/2022 CATHERINE ADROVER
Roof/Waste drainage to street Cleared 9/12/2022 CATHERINE ADROVER
Miscellaneous Cleared 9/15/2022 DALIA MOKAYED
Trees in Parkway Cleared 9/16/2022 ADALBERTO VERA
Hydrant and Access approval Cleared 9/17/2022 RUEL COLE
GPI Written Notices Cleared 9/30/2022 MAHNAZ NOURHASHEMI
Grading Pre-Inspection Cleared 9/30/2022 MAHNAZ NOURHASHEMI

Contact Information

Contractor Owner-Builder       ,
Engineer Yuzon,, Benigno Sari; Lic. No.: S3454 2511 PEACHWOOD PLACE      WESTLAKE VILLAGE, CA 91361

Inspector Information

ASHLEY THOMPSON, (310) 914-3897 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Footing/Foundation/Slab 10/16/2023 Not Ready for Inspection MEL KHACHATOURIAN
METHANE-Barrier 10/16/2023 Not Ready for Inspection MEL KHACHATOURIAN
METHANE-Subgrade 10/16/2023 Not Ready for Inspection MEL KHACHATOURIAN
Excavation/Setback/Form/Re-Bar 10/20/2023 Not Ready for Inspection MEL KHACHATOURIAN
Footing/Foundation/Slab 10/30/2023 Partial Approval CLAYTON GRAHAM
METHANE-Subgrade 10/30/2023 Corrections Issued CLAYTON GRAHAM
Underground Mechanical 10/30/2023 Corrections Issued CLAYTON GRAHAM
METHANE-Rough 11/1/2023 Partial Approval KENNETH NAGLE
PLUMBING-Rough 11/1/2023 Partial Approval KENNETH NAGLE
Excavation/Setback/Form/Re-Bar 11/13/2023 Approved MEL KHACHATOURIAN
Footing/Foundation/Slab 11/13/2023 Approved MEL KHACHATOURIAN
METHANE-Barrier 11/13/2023 Approved MEL KHACHATOURIAN
METHANE-Subgrade 11/13/2023 Approved MEL KHACHATOURIAN
Piling/Pier/Caisson 11/13/2023 Approved MEL KHACHATOURIAN
BUILDING-Rough-Frame 12/11/2023 Not Ready for Inspection MEL KHACHATOURIAN
Floor/Roof Diaphrgm/Shear Wall 12/11/2023 Partial Approval MEL KHACHATOURIAN
Green Building Rough 12/11/2023 Not Ready for Inspection MEL KHACHATOURIAN
METHANE-Rough 12/11/2023 Not Ready for Inspection MEL KHACHATOURIAN
Verify Sprinkler Sign Off 12/11/2023 Not Ready for Inspection MEL KHACHATOURIAN
Floor/Roof Diaphrgm/Shear Wall 1/18/2024 Not Ready for Inspection OGANES TARAKHCHYAN
HVAC-Rough 3/1/2024 Corrections Issued OGANES TARAKHCHYAN
PLUMBING-Rough 3/1/2024 Approved OGANES TARAKHCHYAN
ELECTRICAL-Rough 3/11/2024 Corrections Issued OGANES TARAKHCHYAN
HVAC-Rough 3/11/2024 Approved OGANES TARAKHCHYAN
ELECTRICAL-Rough 3/14/2024 Approved OGANES TARAKHCHYAN
BUILDING-Rough-Frame 3/19/2024 Not Ready for Inspection MEL KHACHATOURIAN
HVAC-Rough 3/19/2024 Approved MEL KHACHATOURIAN
Floor/Roof Diaphrgm/Shear Wall 4/12/2024 Partial Approval OGANES TARAKHCHYAN
METHANE-Rough 4/12/2024 Approved OGANES TARAKHCHYAN
Green Building Rough 4/26/2024 Not Ready for Inspection OGANES TARAKHCHYAN
BUILDING-Rough-Frame 5/9/2024 Not Ready for Inspection MEL KHACHATOURIAN
Green Building Rough 5/9/2024 Not Ready for Inspection MEL KHACHATOURIAN
Verify Sprinkler Sign Off 5/9/2024 Not Ready for Inspection MEL KHACHATOURIAN
Underground Mechanical 5/10/2024 Approved OGANES TARAKHCHYAN
BUILDING-Rough-Frame 5/14/2024 Corrections Issued MEL KHACHATOURIAN
Green Building Rough 5/14/2024 Approved MEL KHACHATOURIAN
Verify Sprinkler Sign Off 5/14/2024 Approved MEL KHACHATOURIAN
Insulation 5/20/2024 Partial Approval MEL KHACHATOURIAN
Drywall Nailing 5/30/2024 Approved ASHLEY THOMPSON
Shower Pan 7/1/2024 Approved ASHLEY THOMPSON
PLUMBING-Final 12/2/2024 Corrections Issued ASHLEY THOMPSON
ELECTRICAL-Final 12/4/2024 Corrections Issued STEPHANIE SWANSON
PLUMBING-Final 12/4/2024 Corrections Issued STEPHANIE SWANSON
ELECTRICAL-Final 12/10/2024 Approved ARAM AVEDISIAN
Smoke Detectors 12/10/2024 Approved ARAM AVEDISIAN
HVAC-Final 12/20/2024 Corrections Issued SEAN HAUPT
HVAC-Final 12/24/2024 Corrections Issued ARAM AVEDISIAN
PLUMBING-Final 12/24/2024 Not Ready for Inspection ARAM AVEDISIAN
HVAC-Final 1/24/2025 Approved ARAM AVEDISIAN
PLUMBING-Final 1/24/2025 Approved ARAM AVEDISIAN
BUILDING-Rough-Frame 5/13/2025 Approved EVAN COOPER
Final 5/13/2025 Corrections Issued EVAN COOPER
Green Building Final 5/13/2025 Approved EVAN COOPER
SGSOV-Seismic Gas S/O Valve 5/13/2025 SGSOV Approved EVAN COOPER
Service/Power Release 5/13/2025 Not Ready for Inspection EVAN COOPER
Final 5/16/2025 OK to Issue CofO EVAN COOPER
Service/Power Release 5/16/2025 Approved EVAN COOPER