5724 N NOBLE AVE 91411

Certificate Information: 5724 N NOBLE AVE 91411

Application / Permit
22010-10000-02666
Plan Check / Job No.
B22LA09947
Group
Building
Type
Bldg-Addition
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Accessory Dwelling Unit
Work Description
EPLAN: PROPOSED GARAGE CONVERSION TO AN ADU WITH 440 SF ADDITION PER LAMC 12.22A.33 (c)-(d). [1088 SQ FT TOTAL ADU AREA]
Permit Issued
Issued on 12/2/2023
Issuing Office
Current Status
CofO Issued on 3/18/2025
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 5/25/2022 APPLICANT
Assigned to Plan Check Engineer 5/26/2022 HANS SANTIAGO
Corrections Issued 5/27/2022 HANS SANTIAGO
Applicant returned to address corrections 9/22/2022 HANS SANTIAGO
Applicant returned to address corrections 9/25/2022 HANS SANTIAGO
Plan Check Approved 12/13/2022 ANDREW SANTIAGO
Issued 12/2/2023 APPLICANT
CofO in Progress 3/6/2025 RYAN SALAZAR
Permit Finaled 3/18/2025 RUBEN SALAS
CofO Issued 3/18/2025 RUBEN SALAS
Permit Finaled 3/18/2025 RUBEN SALAS

Permit Application Clearance Information

Address approval Cleared 6/8/2022 DAGOVERTO GUERRERO
Roof/Waste drainage to street Cleared 6/8/2022 DAGOVERTO GUERRERO
Eng Process Fee Ord 176,300 Cleared 6/13/2022 DAGOVERTO GUERRERO
Sewer availability Cleared 6/13/2022 DAGOVERTO GUERRERO
Construction near power lines Cleared 11/29/2022 RIDWAN HARDY

Contact Information

Contractor Nader Ghanaat; Lic. No.: 1020955-B       ,
Engineer Martirossyan,, Armen; Lic. No.: C64223 802 PORTOLA AVE      GLENDALE, CA 91206

Inspector Information

JOSE AVILA, (818) 374-1173 Office Hours: 7:00-8:00 AM MON-FRI
VINCENT HANLEY, (818) 374-1173 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Pre-Inspection 7/29/2024 Partial Inspection MICHEL ABAJAN
Deputy Drilled-In Anchors 8/15/2024 Conditional Approval RYAN SALAZAR
Footing/Foundation/Slab 8/15/2024 Corrections Issued RYAN SALAZAR
Excavation/Setback/Form/Re-Bar 8/23/2024 Partial Approval RYAN SALAZAR
Footing/Foundation/Slab 8/23/2024 Partial Approval RYAN SALAZAR
PLUMBING-Rough 8/23/2024 Partial Approval RYAN SALAZAR
Footing/Foundation/Slab 10/28/2024 Approved RYAN SALAZAR
PLUMBING-Rough 10/28/2024 Approved RYAN SALAZAR
ELECTRICAL-Rough 11/4/2024 Approved RYAN SALAZAR
BUILDING-Rough-Frame 11/19/2024 Approved RYAN SALAZAR
HVAC-Rough 11/19/2024 Approved RYAN SALAZAR
Insulation 12/3/2024 Approved RYAN SALAZAR
Interior/Exterior Lathing 12/3/2024 Partial Approval RYAN SALAZAR
Drywall Nailing 12/11/2024 Approved RYAN SALAZAR
Interior/Exterior Lathing 12/11/2024 Approved RYAN SALAZAR
Shower Pan 12/11/2024 Approved RYAN SALAZAR
Sewer 1/17/2025 Approved RYAN SALAZAR
Underground Mechanical 1/17/2025 Approved RYAN SALAZAR
PLUMBING-Final 2/14/2025 Not Ready for Inspection RYAN SALAZAR
Underground Mechanical 2/14/2025 Approved RYAN SALAZAR
ELECTRICAL-Final 3/5/2025 Approved RYAN SALAZAR
Final 3/5/2025 OK to Issue CofO RYAN SALAZAR
HVAC-Final 3/5/2025 Approved RYAN SALAZAR
PLUMBING-Final 3/5/2025 Approved RYAN SALAZAR
SGSOV-Seismic Gas S/O Valve 3/5/2025 SGSOV Not Required RYAN SALAZAR
Service/Power Release 3/5/2025 Approved RYAN SALAZAR
Smoke Detectors 3/5/2025 Approved RYAN SALAZAR