5724 N NOBLE AVE 91411
Certificate Information: 5724 N NOBLE AVE 91411
- Application / Permit
- 22010-10000-02666
- Plan Check / Job No.
- B22LA09947
- Group
- Building
- Type
- Bldg-Addition
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Accessory Dwelling Unit
- Work Description
- EPLAN: PROPOSED GARAGE CONVERSION TO AN ADU WITH 440 SF ADDITION PER LAMC 12.22A.33 (c)-(d). [1088 SQ FT TOTAL ADU AREA]
- Permit Issued
- Issued on 12/2/2023
- Issuing Office
- Current Status
- CofO Issued on 3/18/2025
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 5/25/2022 | APPLICANT |
| Assigned to Plan Check Engineer | 5/26/2022 | HANS SANTIAGO |
| Corrections Issued | 5/27/2022 | HANS SANTIAGO |
| Applicant returned to address corrections | 9/22/2022 | HANS SANTIAGO |
| Applicant returned to address corrections | 9/25/2022 | HANS SANTIAGO |
| Plan Check Approved | 12/13/2022 | ANDREW SANTIAGO |
| Issued | 12/2/2023 | APPLICANT |
| CofO in Progress | 3/6/2025 | RYAN SALAZAR |
| Permit Finaled | 3/18/2025 | RUBEN SALAS |
| CofO Issued | 3/18/2025 | RUBEN SALAS |
| Permit Finaled | 3/18/2025 | RUBEN SALAS |
Permit Application Clearance Information
| Address approval | Cleared | 6/8/2022 | DAGOVERTO GUERRERO |
| Roof/Waste drainage to street | Cleared | 6/8/2022 | DAGOVERTO GUERRERO |
| Eng Process Fee Ord 176,300 | Cleared | 6/13/2022 | DAGOVERTO GUERRERO |
| Sewer availability | Cleared | 6/13/2022 | DAGOVERTO GUERRERO |
| Construction near power lines | Cleared | 11/29/2022 | RIDWAN HARDY |
Contact Information
| Contractor | Nader Ghanaat; Lic. No.: 1020955-B | , |
| Engineer | Martirossyan,, Armen; Lic. No.: C64223 | 802 PORTOLA AVE GLENDALE, CA 91206 |
Inspector Information
| JOSE AVILA, (818) 374-1173 | Office Hours: 7:00-8:00 AM MON-FRI |
| VINCENT HANLEY, (818) 374-1173 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Pre-Inspection | 7/29/2024 | Partial Inspection | MICHEL ABAJAN |
| Deputy Drilled-In Anchors | 8/15/2024 | Conditional Approval | RYAN SALAZAR |
| Footing/Foundation/Slab | 8/15/2024 | Corrections Issued | RYAN SALAZAR |
| Excavation/Setback/Form/Re-Bar | 8/23/2024 | Partial Approval | RYAN SALAZAR |
| Footing/Foundation/Slab | 8/23/2024 | Partial Approval | RYAN SALAZAR |
| PLUMBING-Rough | 8/23/2024 | Partial Approval | RYAN SALAZAR |
| Footing/Foundation/Slab | 10/28/2024 | Approved | RYAN SALAZAR |
| PLUMBING-Rough | 10/28/2024 | Approved | RYAN SALAZAR |
| ELECTRICAL-Rough | 11/4/2024 | Approved | RYAN SALAZAR |
| BUILDING-Rough-Frame | 11/19/2024 | Approved | RYAN SALAZAR |
| HVAC-Rough | 11/19/2024 | Approved | RYAN SALAZAR |
| Insulation | 12/3/2024 | Approved | RYAN SALAZAR |
| Interior/Exterior Lathing | 12/3/2024 | Partial Approval | RYAN SALAZAR |
| Drywall Nailing | 12/11/2024 | Approved | RYAN SALAZAR |
| Interior/Exterior Lathing | 12/11/2024 | Approved | RYAN SALAZAR |
| Shower Pan | 12/11/2024 | Approved | RYAN SALAZAR |
| Sewer | 1/17/2025 | Approved | RYAN SALAZAR |
| Underground Mechanical | 1/17/2025 | Approved | RYAN SALAZAR |
| PLUMBING-Final | 2/14/2025 | Not Ready for Inspection | RYAN SALAZAR |
| Underground Mechanical | 2/14/2025 | Approved | RYAN SALAZAR |
| ELECTRICAL-Final | 3/5/2025 | Approved | RYAN SALAZAR |
| Final | 3/5/2025 | OK to Issue CofO | RYAN SALAZAR |
| HVAC-Final | 3/5/2025 | Approved | RYAN SALAZAR |
| PLUMBING-Final | 3/5/2025 | Approved | RYAN SALAZAR |
| SGSOV-Seismic Gas S/O Valve | 3/5/2025 | SGSOV Not Required | RYAN SALAZAR |
| Service/Power Release | 3/5/2025 | Approved | RYAN SALAZAR |
| Smoke Detectors | 3/5/2025 | Approved | RYAN SALAZAR |