1655 S HAYWORTH AVE 90035

Certificate Information: 1655 S HAYWORTH AVE 90035

Application / Permit
22010-10000-02664
Plan Check / Job No.
B22LA09945
Group
Building
Type
Bldg-New
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Accessory Dwelling Unit
Work Description
eplan New garage with attached two-story A.D.U. Per ADU PER LAMC 12.22 A.33 (c) & (d)
Permit Issued
Issued on 7/17/2023
Issuing Office
Current Status
CofO Issued on 1/19/2025
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 5/24/2022 APPLICANT
Assigned to Plan Check Engineer 6/24/2022 ADRIANA LOPEZ
Corrections Issued 6/26/2022 ADRIANA LOPEZ
Quality Review Completed 7/12/2022 FARUK SEZER
Applicant returned to address corrections 6/6/2023 ADRIANA LOPEZ
Applicant returned to address corrections 6/13/2023 ADRIANA LOPEZ
Applicant returned to address corrections 7/12/2023 ADRIANA LOPEZ
Plan Check Approved 7/17/2023 ADRIANA LOPEZ
Issued 7/17/2023 APPLICANT
CofO in Progress 12/30/2024 ARTHUR NEGRETE
Permit Finaled 1/19/2025 DEROLD HAUFF
Permit Finaled 1/19/2025 DEROLD HAUFF
CofO Issued 1/19/2025 DEROLD HAUFF

Permit Application Clearance Information

Low Impact Development Cleared 12/20/2022 MITESH PATEL
Address approval Cleared 12/23/2022 AMAAN MALIK
Roof/Waste drainage to street Cleared 12/23/2022 AMAAN MALIK
Eng Process Fee Ord 176,300 Cleared 1/6/2023 AMAAN MALIK
Sewer availability Cleared 1/6/2023 AMAAN MALIK
Construction near power lines Cleared 1/24/2023 TINA MIRANDA
Construction within easement Cleared 1/24/2023 TINA MIRANDA

Contact Information

Contractor Owner-Builder       ,
Engineer Maalouf,, Sami; Lic. No.: NA53210       ,

Inspector Information

DAVID WILLIAMS, (213) 202-3126 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Excavation/Setback/Form/Re-Bar 7/24/2023 Approved MICHAEL LEWIS
Footing/Foundation/Slab 7/24/2023 Partial Approval MICHAEL LEWIS
METHANE-Barrier 7/24/2023 Approved MICHAEL LEWIS
METHANE-Subgrade 7/24/2023 Approved MICHAEL LEWIS
BUILDING-Rough-Frame 8/3/2023 Partial Approval LILIANA PORTILLO
PLUMBING-Rough 8/3/2023 Partial Approval LILIANA PORTILLO
Floor/Roof Diaphrgm/Shear Wall 8/9/2023 Partial Approval BRENDAN MORELLI
Footing/Foundation/Slab 8/9/2023 Corrections Issued BRENDAN MORELLI
Floor/Roof Diaphrgm/Shear Wall 8/16/2023 Partial Approval ALIZAH MAYAGOITIA
Footing/Foundation/Slab 8/16/2023 Approved ALIZAH MAYAGOITIA
Deputy Wood Construction 9/14/2023 Conditional Approval JOSE AVILA
Floor/Roof Diaphrgm/Shear Wall 9/18/2023 Partial Approval LILIANA PORTILLO
ELECTRICAL-Rough 9/28/2023 Corrections Issued JOSE AVILA
PLUMBING-Rough 9/28/2023 Corrections Issued JOSE AVILA
ELECTRICAL-Rough 10/31/2023 Approved JOSE AVILA
PLUMBING-Rough 10/31/2023 Approved JOSE AVILA
HVAC-Rough 11/6/2023 Corrections Issued RONNIE MINDANAO
HVAC-Rough 11/15/2023 Corrections Issued LILIANA PORTILLO
HVAC-Rough 11/22/2023 Not Ready for Inspection LILIANA PORTILLO
Insulation 11/22/2023 Partial Approval LILIANA PORTILLO
Interior/Exterior Lathing 12/6/2023 Approved RONNIE MINDANAO
Insulation 12/15/2023 Partial Inspection RONNIE MINDANAO
BUILDING-Rough-Frame 12/21/2023 Partial Approval SCOTT FINNILA
Green Building Rough 12/21/2023 Not Ready for Inspection SCOTT FINNILA
Insulation 12/21/2023 Conditional Approval SCOTT FINNILA
METHANE-Rough 12/21/2023 Corrections Issued SCOTT FINNILA
Verify Sprinkler Sign Off 12/21/2023 Partial Inspection SCOTT FINNILA
Insulation 1/3/2024 Approved RONNIE MINDANAO
Special/Order Compliance 1/3/2024 Corrections Issued RONNIE MINDANAO
Drywall Nailing 1/9/2024 Approved ALIZAH MAYAGOITIA
Green Building Rough 1/9/2024 Approved ALIZAH MAYAGOITIA
Shower Pan 1/18/2024 Approved LILIANA PORTILLO
ELECTRICAL-Final 5/1/2024 Corrections Issued JEFFREY MEAD
PLUMBING-Final 5/1/2024 Approved JEFFREY MEAD
Final 6/6/2024 Corrections Issued ENRIQUE MIRELES
Service/Power Release 6/6/2024 Approved ENRIQUE MIRELES
Service/Power Release 8/15/2024 Approved ARTHUR NEGRETE
BUILDING-Rough-Frame 9/23/2024 Approved LUIS CASTRO
ELECTRICAL-Final 9/23/2024 Corrections Issued LUIS CASTRO
Final 9/23/2024 Not Ready for Inspection LUIS CASTRO
Green Building Final 9/23/2024 Approved LUIS CASTRO
HVAC-Final 9/23/2024 Approved LUIS CASTRO
METHANE-Final 9/23/2024 Approved LUIS CASTRO
METHANE-Rough 9/23/2024 Approved LUIS CASTRO
PLUMBING-Final 9/23/2024 Approved LUIS CASTRO
SGSOV-Seismic Gas S/O Valve 9/23/2024 SGSOV No Gas LUIS CASTRO
Smoke Detectors 9/23/2024 Approved LUIS CASTRO
Verify Sprinkler Sign Off 9/23/2024 Approved LUIS CASTRO
Final 9/27/2024 Corrections Issued WILLIAM SIERRA
ELECTRICAL-Final 12/27/2024 Approved ARTHUR NEGRETE
Final 12/27/2024 OK to Issue CofO ARTHUR NEGRETE