1655 S HAYWORTH AVE 90035
Certificate Information: 1655 S HAYWORTH AVE 90035
- Application / Permit
- 22010-10000-02664
- Plan Check / Job No.
- B22LA09945
- Group
- Building
- Type
- Bldg-New
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Accessory Dwelling Unit
- Work Description
- eplan New garage with attached two-story A.D.U. Per ADU PER LAMC 12.22 A.33 (c) & (d)
- Permit Issued
- Issued on 7/17/2023
- Issuing Office
- Current Status
- CofO Issued on 1/19/2025
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 5/24/2022 | APPLICANT |
| Assigned to Plan Check Engineer | 6/24/2022 | ADRIANA LOPEZ |
| Corrections Issued | 6/26/2022 | ADRIANA LOPEZ |
| Quality Review Completed | 7/12/2022 | FARUK SEZER |
| Applicant returned to address corrections | 6/6/2023 | ADRIANA LOPEZ |
| Applicant returned to address corrections | 6/13/2023 | ADRIANA LOPEZ |
| Applicant returned to address corrections | 7/12/2023 | ADRIANA LOPEZ |
| Plan Check Approved | 7/17/2023 | ADRIANA LOPEZ |
| Issued | 7/17/2023 | APPLICANT |
| CofO in Progress | 12/30/2024 | ARTHUR NEGRETE |
| Permit Finaled | 1/19/2025 | DEROLD HAUFF |
| Permit Finaled | 1/19/2025 | DEROLD HAUFF |
| CofO Issued | 1/19/2025 | DEROLD HAUFF |
Permit Application Clearance Information
| Low Impact Development | Cleared | 12/20/2022 | MITESH PATEL |
| Address approval | Cleared | 12/23/2022 | AMAAN MALIK |
| Roof/Waste drainage to street | Cleared | 12/23/2022 | AMAAN MALIK |
| Eng Process Fee Ord 176,300 | Cleared | 1/6/2023 | AMAAN MALIK |
| Sewer availability | Cleared | 1/6/2023 | AMAAN MALIK |
| Construction near power lines | Cleared | 1/24/2023 | TINA MIRANDA |
| Construction within easement | Cleared | 1/24/2023 | TINA MIRANDA |
Contact Information
| Contractor | Owner-Builder | , |
| Engineer | Maalouf,, Sami; Lic. No.: NA53210 | , |
Inspector Information
| DAVID WILLIAMS, (213) 202-3126 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Excavation/Setback/Form/Re-Bar | 7/24/2023 | Approved | MICHAEL LEWIS |
| Footing/Foundation/Slab | 7/24/2023 | Partial Approval | MICHAEL LEWIS |
| METHANE-Barrier | 7/24/2023 | Approved | MICHAEL LEWIS |
| METHANE-Subgrade | 7/24/2023 | Approved | MICHAEL LEWIS |
| BUILDING-Rough-Frame | 8/3/2023 | Partial Approval | LILIANA PORTILLO |
| PLUMBING-Rough | 8/3/2023 | Partial Approval | LILIANA PORTILLO |
| Floor/Roof Diaphrgm/Shear Wall | 8/9/2023 | Partial Approval | BRENDAN MORELLI |
| Footing/Foundation/Slab | 8/9/2023 | Corrections Issued | BRENDAN MORELLI |
| Floor/Roof Diaphrgm/Shear Wall | 8/16/2023 | Partial Approval | ALIZAH MAYAGOITIA |
| Footing/Foundation/Slab | 8/16/2023 | Approved | ALIZAH MAYAGOITIA |
| Deputy Wood Construction | 9/14/2023 | Conditional Approval | JOSE AVILA |
| Floor/Roof Diaphrgm/Shear Wall | 9/18/2023 | Partial Approval | LILIANA PORTILLO |
| ELECTRICAL-Rough | 9/28/2023 | Corrections Issued | JOSE AVILA |
| PLUMBING-Rough | 9/28/2023 | Corrections Issued | JOSE AVILA |
| ELECTRICAL-Rough | 10/31/2023 | Approved | JOSE AVILA |
| PLUMBING-Rough | 10/31/2023 | Approved | JOSE AVILA |
| HVAC-Rough | 11/6/2023 | Corrections Issued | RONNIE MINDANAO |
| HVAC-Rough | 11/15/2023 | Corrections Issued | LILIANA PORTILLO |
| HVAC-Rough | 11/22/2023 | Not Ready for Inspection | LILIANA PORTILLO |
| Insulation | 11/22/2023 | Partial Approval | LILIANA PORTILLO |
| Interior/Exterior Lathing | 12/6/2023 | Approved | RONNIE MINDANAO |
| Insulation | 12/15/2023 | Partial Inspection | RONNIE MINDANAO |
| BUILDING-Rough-Frame | 12/21/2023 | Partial Approval | SCOTT FINNILA |
| Green Building Rough | 12/21/2023 | Not Ready for Inspection | SCOTT FINNILA |
| Insulation | 12/21/2023 | Conditional Approval | SCOTT FINNILA |
| METHANE-Rough | 12/21/2023 | Corrections Issued | SCOTT FINNILA |
| Verify Sprinkler Sign Off | 12/21/2023 | Partial Inspection | SCOTT FINNILA |
| Insulation | 1/3/2024 | Approved | RONNIE MINDANAO |
| Special/Order Compliance | 1/3/2024 | Corrections Issued | RONNIE MINDANAO |
| Drywall Nailing | 1/9/2024 | Approved | ALIZAH MAYAGOITIA |
| Green Building Rough | 1/9/2024 | Approved | ALIZAH MAYAGOITIA |
| Shower Pan | 1/18/2024 | Approved | LILIANA PORTILLO |
| ELECTRICAL-Final | 5/1/2024 | Corrections Issued | JEFFREY MEAD |
| PLUMBING-Final | 5/1/2024 | Approved | JEFFREY MEAD |
| Final | 6/6/2024 | Corrections Issued | ENRIQUE MIRELES |
| Service/Power Release | 6/6/2024 | Approved | ENRIQUE MIRELES |
| Service/Power Release | 8/15/2024 | Approved | ARTHUR NEGRETE |
| BUILDING-Rough-Frame | 9/23/2024 | Approved | LUIS CASTRO |
| ELECTRICAL-Final | 9/23/2024 | Corrections Issued | LUIS CASTRO |
| Final | 9/23/2024 | Not Ready for Inspection | LUIS CASTRO |
| Green Building Final | 9/23/2024 | Approved | LUIS CASTRO |
| HVAC-Final | 9/23/2024 | Approved | LUIS CASTRO |
| METHANE-Final | 9/23/2024 | Approved | LUIS CASTRO |
| METHANE-Rough | 9/23/2024 | Approved | LUIS CASTRO |
| PLUMBING-Final | 9/23/2024 | Approved | LUIS CASTRO |
| SGSOV-Seismic Gas S/O Valve | 9/23/2024 | SGSOV No Gas | LUIS CASTRO |
| Smoke Detectors | 9/23/2024 | Approved | LUIS CASTRO |
| Verify Sprinkler Sign Off | 9/23/2024 | Approved | LUIS CASTRO |
| Final | 9/27/2024 | Corrections Issued | WILLIAM SIERRA |
| ELECTRICAL-Final | 12/27/2024 | Approved | ARTHUR NEGRETE |
| Final | 12/27/2024 | OK to Issue CofO | ARTHUR NEGRETE |