7512 N DARBY AVE 91335

Certificate Information: 7512 N DARBY AVE 91335

Application / Permit
22010-10000-02659
Plan Check / Job No.
B22LA09908
Group
Building
Type
Bldg-New
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Accessory Dwelling Unit
Work Description
eplan: New detached ADU per CA Govt. Code 65852.2(e)(1)(B) and applicable part of LAMC 12.22 A.33 (c)-(d), (g).
Permit Issued
Issued on 3/3/2023
Issuing Office
Current Status
Issued on 3/3/2023
Certificate of Occupancy
Pending More Information

Permit Application Status History

Submitted 5/25/2022 APPLICANT
Assigned to Plan Check Engineer 5/27/2022 SAMUEL GONZALEZ
Corrections Issued 5/28/2022 SAMUEL GONZALEZ
Applicant returned to address corrections 1/17/2023 ADAM HEGAZI
Plan Check Approved 2/5/2023 RICARDO RAMIREZ
Issued 3/3/2023 APPLICANT

Permit Application Clearance Information

Address approval Cleared 7/29/2022 ROMAN GUTIERREZ
Eng Process Fee Ord 176,300 Cleared 8/1/2022 ROMAN GUTIERREZ
Low Impact Development Cleared 11/2/2022 MITESH PATEL
Sewer availability Cleared 12/29/2022 COLIN LOREDO
Roof/Waste drainage to street Cleared 1/3/2023 ROMAN GUTIERREZ

Contact Information

Contractor Owner-Builder       ,
Engineer Dominguez,, Refugio; Lic. No.: C50820 254 COTTONWOOD ST      ONTARIO, CA 91761

Inspector Information

ARUTYUN MADATYAN, (818) 774-4307 Office Hours: 7:00-8:00 AM MON-FRI
JUAN ALVARADO, (818) 774-4307 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

PLUMBING-Rough 4/19/2023 Partial Approval JEFFREY BULL
Sewer 4/19/2023 Not Ready for Inspection JEFFREY BULL
Underground Mechanical 4/19/2023 Approved JEFFREY BULL
Footing/Foundation/Slab 5/5/2023 Approved SEAN HAUPT
Special/Order Compliance 5/5/2023 Corrections Issued SEAN HAUPT
Floor/Roof Diaphrgm/Shear Wall 10/18/2023 Partial Approval JEFFREY BULL
Deputy Wood Construction 10/19/2023 Conditional Approval JEFFREY BULL
ELECTRICAL-Rough 12/8/2023 Approved JEFFREY BULL
Gas Test 12/8/2023 Approved JEFFREY BULL
HVAC-Rough 12/8/2023 Approved JEFFREY BULL
PLUMBING-Rough 12/8/2023 Approved JEFFREY BULL
Interior/Exterior Lathing 12/15/2023 Partial Approval JEFFREY BULL
Sewer 12/15/2023 Approved JEFFREY BULL
Insulation 1/26/2024 Approved KRISTEN CAUSEY
Gas Test 2/1/2024 Approved JEFFREY BULL
Underground Mechanical 2/1/2024 Approved JEFFREY BULL
Drywall Nailing 2/7/2024 Approved JEFFREY BULL
Shower Pan 2/27/2024 Approved JEFFREY PARD
BUILDING-Rough-Frame 1/27/2025 Not Ready for Inspection ARUTYUN MADATYAN
Final 1/27/2025 Not Ready for Inspection ARUTYUN MADATYAN
Interior/Exterior Lathing 1/27/2025 Not Ready for Inspection ARUTYUN MADATYAN
PLUMBING-Final 1/27/2025 Not Ready for Inspection ARUTYUN MADATYAN
SGSOV-Seismic Gas S/O Valve 1/27/2025 SGSOV Not Ready ARUTYUN MADATYAN
Service/Power Release 1/27/2025 Not Ready for Inspection ARUTYUN MADATYAN
Sewer 1/27/2025 Not Ready for Inspection ARUTYUN MADATYAN
Smoke Detectors 1/27/2025 Not Ready for Inspection ARUTYUN MADATYAN
Verify Sprinkler Sign Off 1/27/2025 Not Ready for Inspection ARUTYUN MADATYAN
BUILDING-Rough-Frame 4/14/2025 Approved ARUTYUN MADATYAN
Final 4/14/2025 Corrections Issued ARUTYUN MADATYAN
SGSOV-Seismic Gas S/O Valve 4/14/2025 SGSOV Approved ARUTYUN MADATYAN
Service/Power Release 4/14/2025 Not Ready for Inspection ARUTYUN MADATYAN
Smoke Detectors 4/14/2025 Approved ARUTYUN MADATYAN
Verify Sprinkler Sign Off 4/14/2025 Approved ARUTYUN MADATYAN
Final 7/25/2025 No Access for Inspection ARUTYUN MADATYAN
Service/Power Release 7/25/2025 Not Ready for Inspection ARUTYUN MADATYAN
ELECTRICAL-Final 7/30/2025 Approved JUAN ALVARADO
Final 7/30/2025 Corrections Issued JUAN ALVARADO
HVAC-Final 7/30/2025 Approved JUAN ALVARADO
PLUMBING-Final 7/30/2025 Approved JUAN ALVARADO
Service/Power Release 7/30/2025 Not Ready for Inspection JUAN ALVARADO