8350 N LANGDON AVE 91343
Certificate Information: 8350 N LANGDON AVE 91343
- Application / Permit
- 22010-10000-02651
- Plan Check / Job No.
- B22LA09886
- Group
- Building
- Type
- Bldg-New
- Sub-Type
- Commercial
- Primary Use
- (8) Automobile Sales - new
- Work Description
- NEW ONE STORY AUTO DEALERSHIP WITH SHOWROOM AND SERVICE DRIVE
- Permit Issued
- Issued on 8/4/2023
- Issuing Office
- Metro
- Current Status
- Issued on 8/4/2023
- Certificate of Occupancy
- Pending More Information
Permit Application Status History
| Submitted | 5/24/2022 | APPLICANT |
| Assigned to Plan Check Engineer | 6/9/2022 | TSE MING HUANG |
| Corrections Issued | 6/11/2022 | ERIC WONG |
| Quality Review Completed | 6/23/2022 | KEN GILL |
| Building Plans Picked Up | 6/29/2022 | APPLICANT |
| Green Plans Picked Up | 6/29/2022 | APPLICANT |
| Disabled Access Plans Picked Up | 8/3/2022 | APPLICANT |
| Applicant returned to address corrections | 8/31/2022 | ERIC WONG |
| Applicant returned to address corrections | 11/2/2022 | ERIC WONG |
| Applicant returned to address corrections | 12/6/2022 | ERIC WONG |
| Plan Check Approved | 7/19/2023 | TSE MING HUANG |
| Issued | 8/4/2023 | APPLICANT |
| TCO Issued (Expire Date: 01-14-2026) | 7/18/2025 | JEFFREY DURAN |
| TCO Issued (Expire Date: 07-08-2026) | 1/9/2026 | JEFFREY DURAN |
Permit Application Clearance Information
| Hydrant and Access approval | Cleared | 10/14/2022 | GILBERT URREA |
| ZA Case | Cleared | 1/9/2023 | DANIEL CORONADO |
| Internal circulation | Cleared | 1/10/2023 | DURRE SHAMSI |
| Prkng lot landscape/Water mgmt | Cleared | 1/19/2023 | DANIEL CORONADO |
| CPC | Cleared | 1/27/2023 | DANIEL CORONADO |
| "T" removal | Cleared | 4/4/2023 | DANIEL CORONADO |
| Green Code | Cleared | 4/6/2023 | AARON COSTA |
| Address approval | Cleared | 4/15/2023 | CARLOS AGUILERA |
| Highway dedication | Cleared | 4/15/2023 | CARLOS AGUILERA |
| Permit | Cleared | 4/15/2023 | CARLOS AGUILERA |
| Eng Process Fee Ord 176,300 | Cleared | 4/17/2023 | CARLOS AGUILERA |
| Sewer availability | Cleared | 4/17/2023 | CARLOS AGUILERA |
| DAS Clearance | Cleared | 5/1/2023 | ERIC WONG |
| "Q" conditions | Cleared | 6/9/2023 | DANIEL CORONADO |
| Low Impact Development | Cleared | 7/14/2023 | JORGE MEJIA LEMUS |
| Roof/Waste drainage to street | Cleared | 7/19/2023 | CARLOS AGUILERA |
Contact Information
| Architect | Wanja,, Michael Joseph; Lic. No.: C37423 | 5151 SAN FELIPE ST #1700 HOUSTON, TX 77056 |
| Contractor | Kunzik & Sara Construction Inc; Lic. No.: 847939-B | 1699 LA COSTA MEADOWS DR #102 SAN MARCOS, CA 92078 |
| Engineer | Chen,, Jeff Y; Lic. No.: S4699 | 17500 REDHILL AVENUE SUITE 240 IRVINE, CA 92614 |
| Engineer | Tucker,, Keith D; Lic. No.: GE841 | PO BOX 8133 HUNTINGTON BEACH, CA 92615 |
Inspector Information
| JOHN KITCKO, (818) 374-1109 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Pre-Inspection | 1/8/2024 | Not Ready for Inspection | DANNY RODRIGUEZ |
| Pre-Inspection | 2/7/2024 | Partial Inspection | DANNY RODRIGUEZ |
| Excavation/Setback/Form/Re-Bar | 3/11/2024 | Not Ready for Inspection | DANNY RODRIGUEZ |
| Deputy Drilled-In Anchors | 5/17/2024 | Conditional Approval | ADAM BURGESS |
| Deputy Reinf. Concrete | 5/20/2024 | Conditional Approval | DANNY RODRIGUEZ |
| Footing/Foundation/Slab | 5/21/2024 | Partial Approval | DANNY RODRIGUEZ |
| Reinforced Concrete Frame | 5/21/2024 | Partial Inspection | DANNY RODRIGUEZ |
| Deputy Reinf. Concrete | 5/23/2024 | Approved | DANNY RODRIGUEZ |
| Deputy Reinf. Concrete | 5/24/2024 | Approved | DANNY RODRIGUEZ |
| Deputy Reinf. Masonry | 5/28/2024 | Conditional Approval | KENNETH ROBERTS |
| Deputy Reinf. Masonry | 5/29/2024 | Conditional Approval | GREGORY POMISH |
| Deputy Reinf. Masonry | 5/30/2024 | Conditional Approval | JEFFREY DURAN |
| Masonry Wall/Backfill | 5/31/2024 | Partial Approval | KENNETH ROBERTS |
| Deputy Steel/Welding | 6/5/2024 | Conditional Approval | JEFFREY DURAN |
| Deputy Steel/Welding | 6/6/2024 | Conditional Approval | GREGORY POMISH |
| Deputy Steel/Welding | 6/7/2024 | Approved | JOHN KITCKO |
| Masonry Wall/Backfill | 6/7/2024 | Partial Approval | JOHN KITCKO |
| Reinforced Masonry Frame | 6/7/2024 | Partial Approval | JOHN KITCKO |
| Deputy Steel/Welding | 6/11/2024 | Approved | JEFFREY DURAN |
| Deputy Steel/Welding | 6/12/2024 | Conditional Approval | JEFFREY DURAN |
| Deputy Steel/Welding | 6/13/2024 | Approved | JOHN KITCKO |
| Reinforced Masonry Frame | 6/13/2024 | Partial Approval | JOHN KITCKO |
| Deputy Steel/Welding | 6/14/2024 | Conditional Approval | JEFFREY DURAN |
| Deputy Reinf. Masonry | 6/20/2024 | Approved | DANNY RODRIGUEZ |
| Deputy Reinf. Masonry | 6/21/2024 | Conditional Approval | DANNY RODRIGUEZ |
| Deputy Steel/Welding | 6/21/2024 | Conditional Approval | DANNY RODRIGUEZ |
| Deputy Reinf. Masonry | 6/25/2024 | Conditional Approval | DANNY RODRIGUEZ |
| Reinforced Masonry Frame | 6/25/2024 | Partial Inspection | DANNY RODRIGUEZ |
| Deputy Steel/Welding | 6/27/2024 | Conditional Approval | DANNY RODRIGUEZ |
| Reinforced Masonry Frame | 7/1/2024 | Partial Approval | DANNY RODRIGUEZ |
| Footing/Foundation/Slab | 7/2/2024 | Partial Approval | DANNY RODRIGUEZ |
| Deputy Steel/Welding | 7/9/2024 | Conditional Approval | DANNY RODRIGUEZ |
| Reinforced Masonry Frame | 7/9/2024 | Not Ready for Inspection | DANNY RODRIGUEZ |
| Deputy Reinf. Masonry | 7/10/2024 | Approved | DANNY RODRIGUEZ |
| Reinforced Masonry Frame | 7/10/2024 | Partial Approval | DANNY RODRIGUEZ |
| Reinforced Masonry Frame | 7/12/2024 | Partial Approval | DANNY RODRIGUEZ |
| Deputy Steel/Welding | 7/15/2024 | Approved | DANNY RODRIGUEZ |
| Deputy Steel/Welding | 7/18/2024 | Approved | DANNY RODRIGUEZ |
| Deputy Steel/Welding | 7/19/2024 | Conditional Approval | ROBERT DAVIS |
| Deputy Reinf. Masonry | 7/24/2024 | Approved | DANNY RODRIGUEZ |
| Deputy Reinf. Masonry | 7/25/2024 | Conditional Approval | DANNY RODRIGUEZ |
| Deputy Reinf. Masonry | 7/26/2024 | Conditional Approval | DANNY RODRIGUEZ |
| Footing/Foundation/Slab | 7/26/2024 | Not Ready for Inspection | DANNY RODRIGUEZ |
| Deputy Steel/Welding | 7/29/2024 | Approved | DANNY RODRIGUEZ |
| Floor/Roof Diaphrgm/Shear Wall | 7/30/2024 | Partial Inspection | DANNY RODRIGUEZ |
| Green Building Rough | 7/30/2024 | Not Ready for Inspection | DANNY RODRIGUEZ |
| Structural Steel Frame | 7/30/2024 | Not Ready for Inspection | DANNY RODRIGUEZ |
| Verify Sprinkler Sign Off | 7/30/2024 | Not Ready for Inspection | DANNY RODRIGUEZ |
| Wood Frame | 7/30/2024 | Partial Inspection | DANNY RODRIGUEZ |
| Floor/Roof Diaphrgm/Shear Wall | 8/5/2024 | Partial Approval | DANNY RODRIGUEZ |
| Green Building Rough | 8/5/2024 | Not Ready for Inspection | DANNY RODRIGUEZ |
| Verify Sprinkler Sign Off | 8/5/2024 | Not Ready for Inspection | DANNY RODRIGUEZ |
| Wood Frame | 8/5/2024 | Partial Approval | DANNY RODRIGUEZ |
| Footing/Foundation/Slab | 8/9/2024 | Partial Approval | DANNY RODRIGUEZ |
| Deputy Steel/Welding | 8/16/2024 | Conditional Approval | DANNY RODRIGUEZ |
| Deputy Steel/Welding | 8/21/2024 | Conditional Approval | DANNY RODRIGUEZ |
| Deputy Steel/Welding | 8/22/2024 | Approved | DANNY RODRIGUEZ |
| Deputy Steel/Welding | 8/23/2024 | Conditional Approval | DANNY RODRIGUEZ |
| Deputy Steel/Welding | 8/27/2024 | Approved | DANNY RODRIGUEZ |
| Light Gage Steel Frame | 9/3/2024 | Partial Approval | DANNY RODRIGUEZ |
| Floor/Roof Diaphrgm/Shear Wall | 9/11/2024 | Partial Approval | DANNY RODRIGUEZ |
| Insulation | 10/15/2024 | Partial Inspection | JOHN KITCKO |
| Light Gage Steel Frame | 10/25/2024 | Not Ready for Inspection | DANNY RODRIGUEZ |
| Light Gage Steel Frame | 10/28/2024 | Corrections Issued | DANNY RODRIGUEZ |
| Light Gage Steel Frame | 10/29/2024 | Partial Approval | DANNY RODRIGUEZ |
| Insulation | 10/30/2024 | Partial Approval | DANNY RODRIGUEZ |
| Light Gage Steel Frame | 10/30/2024 | Partial Approval | DANNY RODRIGUEZ |
| Drywall Nailing | 11/4/2024 | Partial Approval | GREGORY POMISH |
| Footing/Foundation/Slab | 11/15/2024 | Partial Approval | DANNY RODRIGUEZ |
| Deputy Reinf. Concrete | 11/18/2024 | Conditional Approval | DANNY RODRIGUEZ |
| Floor/Roof Diaphrgm/Shear Wall | 11/20/2024 | Partial Approval | GREGORY POMISH |
| Interior/Exterior Lathing | 1/2/2025 | Partial Approval | DANNY RODRIGUEZ |
| Deputy Drilled-In Anchors | 1/3/2025 | Conditional Approval | DANNY RODRIGUEZ |
| Deputy Reinf. Concrete | 1/3/2025 | Conditional Approval | DANNY RODRIGUEZ |
| Deputy Reinf. Concrete | 1/6/2025 | Conditional Approval | DANNY RODRIGUEZ |
| Deputy Reinf. Concrete | 2/20/2025 | Approved | DANNY RODRIGUEZ |
| Footing/Foundation/Slab | 3/7/2025 | Partial Approval | DANNY RODRIGUEZ |
| Piling/Pier/Caisson | 3/10/2025 | Not Ready for Inspection | DANNY RODRIGUEZ |
| Piling/Pier/Caisson | 3/12/2025 | Partial Approval | DANNY RODRIGUEZ |
| T-Bar Ceiling | 4/8/2025 | Partial Approval | DANNY RODRIGUEZ |
| T-Bar Ceiling | 4/10/2025 | Approved | DANNY RODRIGUEZ |
| Pre-Inspection | 4/11/2025 | Partial Inspection | DANNY RODRIGUEZ |
| Non Compliance | 6/9/2025 | Not Required | DANIEL VARNUM |
| Final | 6/17/2025 | Corrections Issued | ROBERT DAVIS |
| Footing/Foundation/Slab | 6/17/2025 | Approved | ROBERT DAVIS |
| Green Building Final | 6/17/2025 | Approved | ROBERT DAVIS |
| Green Building Rough | 6/17/2025 | Approved | ROBERT DAVIS |
| SGSOV-Seismic Gas S/O Valve | 6/17/2025 | SGSOV No Gas | ROBERT DAVIS |
| Smoke Detectors | 6/17/2025 | Approved | ROBERT DAVIS |
| Verify Sprinkler Sign Off | 6/17/2025 | Approved | ROBERT DAVIS |
| Wood Frame | 6/17/2025 | Approved | ROBERT DAVIS |
| Final | 6/23/2025 | OK for TCO | ROBERT DAVIS |
| Special/Order Compliance | 12/16/2025 | Not Ready for Inspection | JEFFREY DURAN |