5637-5637 1/2 W HOMESIDE AVE 90016

Certificate Information: 5637-5637 1/2 W HOMESIDE AVE 90016

Application / Permit
22010-10000-02615
Plan Check / Job No.
B22LA09676
Group
Building
Type
Bldg-New
Sub-Type
1 or 2 Family Dwelling
Primary Use
(2) Duplex
Work Description
NEW 3 STORY DUPLEX WITH ATTACHED 2-STORY ACCESSORY DWELLING UNIT PER LAMC 12.22 A.33(c) and (e) NFPA 13D SPRINKLERED THROUGH OUT
Permit Issued
Issued on 8/1/2024
Issuing Office
Metro
Current Status
Issued on 8/1/2024
Certificate of Occupancy
Pending More Information

Permit Application Status History

Submitted 5/20/2022 APPLICANT
Assigned to Plan Check Engineer 6/16/2022 JAD BASMA
Corrections Issued 6/24/2022 JAD BASMA
Quality Review Completed 7/6/2022 TEODORO DIAZ RODRIGUEZ
Building Plans Picked Up 7/22/2022 APPLICANT
Plan Check Approved 8/1/2024 JAD BASMA
Issued 8/1/2024 APPLICANT

Permit Application Clearance Information

Address approval Cleared 6/30/2022 WALLIE JONG
Address approval Cleared 7/1/2022 WALLIE JONG
Eng Process Fee Ord 176,300 Cleared 7/1/2022 WALLIE JONG
Sewer availability Cleared 7/1/2022 WALLIE JONG
Frnt yard landscape/Water mgmt Cleared 7/5/2022 JASON CHAN
Hydrant and Access approval Cleared 9/22/2022 KURT CORRAL
Low Impact Development Cleared 7/13/2023 SAMUEL LINN
DAS Clearance Cleared 8/1/2023 JAD BASMA
Construction within easement Cleared 12/6/2023 OSCAR CASTRO
Roof/Waste drainage to street Cleared 12/6/2023 ADRIAN SANCHEZ

Contact Information

Contractor Blue Phoenix Builders Inc; Lic. No.: 1066549-B 4474 W ADAMS BLVD #205      LOS ANGELES, CA 90016

Inspector Information

STUART CHAPMAN, (213) 202-3126 Office Hours: 7:00-8:00 AM MON-FRI
ARTHUR NEGRETE, (213) 202-3126 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Footing/Foundation/Slab 9/13/2024 Partial Approval ARTHUR NEGRETE
METHANE-Barrier 9/13/2024 Not Ready for Inspection ARTHUR NEGRETE
METHANE-Subgrade 9/13/2024 Not Ready for Inspection ARTHUR NEGRETE
Footing/Foundation/Slab 10/4/2024 Approved ARTHUR NEGRETE
METHANE-Barrier 10/4/2024 Approved ARTHUR NEGRETE
METHANE-Subgrade 10/4/2024 Approved ARTHUR NEGRETE
Underground Mechanical 10/4/2024 Approved ARTHUR NEGRETE
Deputy Steel/Welding 10/15/2024 Conditional Approval STUART CHAPMAN
Floor/Roof Diaphrgm/Shear Wall 11/19/2024 Approved ARTHUR NEGRETE
Floor/Roof Diaphrgm/Shear Wall 12/20/2024 Approved ARTHUR NEGRETE
Sewer 1/6/2025 Approved ARTHUR NEGRETE
ELECTRICAL-Rough 3/13/2025 Approved ARTHUR NEGRETE
Floor/Roof Diaphrgm/Shear Wall 3/13/2025 Approved ARTHUR NEGRETE
PLUMBING-Rough 3/13/2025 Approved ARTHUR NEGRETE
Special/Order Compliance 3/13/2025 Partial Inspection ALEX COLIN
HVAC-Rough 3/17/2025 Approved ARTHUR NEGRETE
Special/Order Compliance 3/17/2025 Partial Inspection ALEX COLIN
BUILDING-Rough-Frame 3/25/2025 Approved ARTHUR NEGRETE
Green Building Rough 3/25/2025 Approved ARTHUR NEGRETE
METHANE-Rough 3/25/2025 Approved ARTHUR NEGRETE
Verify Sprinkler Sign Off 3/25/2025 Approved ARTHUR NEGRETE
Insulation 4/11/2025 Not Ready for Inspection ARTHUR NEGRETE
Interior/Exterior Lathing 4/11/2025 Approved ARTHUR NEGRETE
Drywall Nailing 4/25/2025 Approved ARTHUR NEGRETE
Shower Pan 5/9/2025 Approved ALEX COLIN
Interior/Exterior Lathing 5/19/2025 Approved REGINA MENDEZ