5312 E NAVARRO ST 90032

Certificate Information: 5312 E NAVARRO ST 90032

Application / Permit
22010-10000-02610
Plan Check / Job No.
B22LA09658
Group
Building
Type
Bldg-New
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Accessory Dwelling Unit
Work Description
New detached ADU per ordinance and to comply with WFPP. **must withdraw 21014-20000-04718**
Permit Issued
Issued on 4/13/2023
Issuing Office
Metro
Current Status
CofO Issued on 4/29/2024
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 5/20/2022 APPLICANT
Assigned to Plan Check Engineer 5/24/2022 RICARDO RAMIREZ
Corrections Issued 5/26/2022 RICARDO RAMIREZ
Building Plans Picked Up 5/27/2022 APPLICANT
Issued 4/13/2023 APPLICANT
CofO in Progress 4/23/2024 ALIZAH MAYAGOITIA
CofO Issued 4/29/2024 DEROLD HAUFF
Permit Finaled 4/29/2024 DEROLD HAUFF

Permit Application Clearance Information

Address approval Cleared 5/27/2022 AMAAN MALIK
Grading Pre-Inspection Cleared 6/7/2022 KIRK LINKLATER
Eng Process Fee Ord 176,300 Cleared 6/10/2022 AMAAN MALIK
Sewer availability Cleared 6/10/2022 AMAAN MALIK
Low Impact Development Cleared 2/8/2023 SARAH YOUSSEF
Roof/Waste drainage to street Cleared 2/9/2023 TREVOR QUAN
GPI Written Notices Cleared 4/11/2023 RICARDO RAMIREZ

Contact Information

Contractor Owner-Builder       ,

Inspector Information

No Data Available.

Pending Inspections

No Data Available.

Inspection Request History

Excavation/Setback/Form/Re-Bar 4/20/2023 Corrections Issued AMY COLIN
PLUMBING-Rough 5/1/2023 Corrections Issued AMY COLIN
Wood Frame 5/1/2023 Approved AMY COLIN
Insulation 5/8/2023 Partial Approval AMY COLIN
Underground Mechanical 5/8/2023 No Access for Inspection RUBEN SALAS
Wood Frame 5/8/2023 No Access for Inspection RUBEN SALAS
Floor/Roof Diaphrgm/Shear Wall 5/12/2023 Approved AMY COLIN
BUILDING-Rough-Frame 6/7/2023 Partial Approval RUBEN SALAS
ELECTRICAL-Rough 7/17/2023 Approved AMY COLIN
HVAC-Rough 7/17/2023 Partial Approval AMY COLIN
PLUMBING-Rough 7/17/2023 Approved AMY COLIN
Wood Frame 7/17/2023 Approved AMY COLIN
Insulation 7/20/2023 Approved AMY COLIN
Drywall Nailing 7/27/2023 Approved AMY COLIN
Interior/Exterior Lathing 7/27/2023 Approved AMY COLIN
Shower Pan 7/27/2023 Approved AMY COLIN
Final 9/29/2023 Corrections Issued AMY COLIN
Footing/Foundation/Slab 9/29/2023 Approved AMY COLIN
Green Building Final 9/29/2023 Approved AMY COLIN
SGSOV-Seismic Gas S/O Valve 9/29/2023 SGSOV Approved AMY COLIN
Service/Power Release 9/29/2023 Not Ready for Inspection AMY COLIN
Smoke Detectors 9/29/2023 Approved AMY COLIN
Final 4/8/2024 Not Ready for Inspection LILIANA PORTILLO
Service/Power Release 4/8/2024 Not Ready for Inspection LILIANA PORTILLO
Final 4/22/2024 OK to Issue CofO ALIZAH MAYAGOITIA
Service/Power Release 4/22/2024 Approved ALIZAH MAYAGOITIA