409 E 115TH ST 90061
Certificate Information: 409 E 115TH ST 90061
- Application / Permit
- 22010-10000-02603
- Plan Check / Job No.
- B22LA09639
- Group
- Building
- Type
- Bldg-New
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Accessory Dwelling Unit
- Work Description
- NEW DETACHED TWO STORY ADU PER LAMC 12.22 A.33 (c)-(d)
- Permit Issued
- Issued on 5/8/2024
- Issuing Office
- Metro
- Current Status
- CofO Issued on 4/22/2026
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 5/20/2022 | APPLICANT |
| Assigned to Plan Check Engineer | 6/16/2022 | MAHNAZ NOURHASHEMI |
| Corrections Issued | 6/23/2022 | MAHNAZ NOURHASHEMI |
| Quality Review Completed | 6/29/2022 | TEODORO DIAZ RODRIGUEZ |
| Building Plans Picked Up | 7/12/2022 | APPLICANT |
| Plan Check Approved | 5/8/2024 | MAHNAZ NOURHASHEMI |
| Issued | 5/8/2024 | APPLICANT |
| CofO in Progress | 3/5/2026 | ARTHUR NEGRETE |
| Permit Finaled | 4/22/2026 | ANSON MAGLASANG |
| Permit Finaled | 4/22/2026 | ANSON MAGLASANG |
| CofO Issued | 4/22/2026 | ANSON MAGLASANG |
Permit Application Clearance Information
| Community Plan Implem. Overlay | Cleared | 4/30/2023 | ADALBERTO VERA |
| Community Plan Implem. Overlay | Cleared | 5/12/2023 | TORI CHEN |
| Address approval | Cleared | 5/19/2023 | KHAING AYE |
| Community Plan Implem. Overlay | Cleared | 5/19/2023 | KHAING AYE |
| Hydrant and Access approval | Cleared | 5/26/2023 | KURT CORRAL |
| Low Impact Development | Cleared | 8/28/2023 | LUIS LUVANO |
| Community Plan Implem. Overlay | Cleared | 9/12/2023 | HELEN JADALI |
| Eng Process Fee Ord 176,300 | Cleared | 9/20/2023 | KHAING AYE |
| Roof/Waste drainage to street | Cleared | 9/20/2023 | KHAING AYE |
| Sewer availability | Cleared | 9/20/2023 | KHAING AYE |
Contact Information
| Contractor | A T S Design And Construction; Lic. No.: 971152-B | 18432 AMIE AVENUE TORRANCE, CA 90504 |
| Engineer | Dorta,, Michael Rohrs; Lic. No.: C72538 | 2445 VIA SONOMA PALOS VERDES ESTATES, CA 90274 |
Inspector Information
| JOHN KLARIN, (310) 732-4558 | Office Hours: 7:00-8:00 AM MON-FRI |
| ARTHUR NEGRETE, (310) 732-4558 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Footing/Foundation/Slab | 5/20/2024 | No Access for Inspection | JAMES CHAVEZ |
| PLUMBING-Rough | 5/20/2024 | No Access for Inspection | JAMES CHAVEZ |
| Excavation/Setback/Form/Re-Bar | 5/21/2024 | Partial Approval | BEN MOLSTAD |
| Pre-Inspection | 5/21/2024 | Not Ready for Inspection | BEN MOLSTAD |
| Underground Mechanical | 5/21/2024 | Corrections Issued | BEN MOLSTAD |
| Footing/Foundation/Slab | 5/22/2024 | Not Ready for Inspection | BEN MOLSTAD |
| Underground Mechanical | 5/22/2024 | Approved | BEN MOLSTAD |
| Footing/Foundation/Slab | 5/24/2024 | Approved | JAMES CHAVEZ |
| Floor/Roof Diaphrgm/Shear Wall | 6/6/2024 | Corrections Issued | BEN MOLSTAD |
| Floor/Roof Diaphrgm/Shear Wall | 6/7/2024 | Partial Approval | JAMES CHAVEZ |
| Deputy Wood Construction | 6/20/2024 | Conditional Approval | BEN MOLSTAD |
| BUILDING-Rough-Frame | 6/24/2024 | Not Ready for Inspection | BEN MOLSTAD |
| Green Building Rough | 6/24/2024 | Not Ready for Inspection | BEN MOLSTAD |
| MERV13>=Rough | 6/24/2024 | Not Ready for Inspection | BEN MOLSTAD |
| Verify Sprinkler Sign Off | 6/24/2024 | Not Ready for Inspection | BEN MOLSTAD |
| BUILDING-Rough-Frame | 7/12/2024 | Not Ready for Inspection | BEN MOLSTAD |
| Green Building Rough | 7/12/2024 | Approved | BEN MOLSTAD |
| MERV13>=Rough | 7/12/2024 | Approved | BEN MOLSTAD |
| PLUMBING-Rough | 7/12/2024 | Approved | BEN MOLSTAD |
| Underground Mechanical | 7/12/2024 | Partial Approval | BEN MOLSTAD |
| Verify Sprinkler Sign Off | 7/12/2024 | Not Ready for Inspection | BEN MOLSTAD |
| BUILDING-Rough-Frame | 7/19/2024 | Not Ready for Inspection | BEN MOLSTAD |
| ELECTRICAL-Rough | 7/19/2024 | Corrections Issued | BEN MOLSTAD |
| Verify Sprinkler Sign Off | 7/19/2024 | Not Ready for Inspection | BEN MOLSTAD |
| BUILDING-Rough-Frame | 7/23/2024 | Approved | JAMES CHAVEZ |
| ELECTRICAL-Rough | 7/23/2024 | Approved | JAMES CHAVEZ |
| Floor/Roof Diaphrgm/Shear Wall | 7/23/2024 | Partial Approval | JAMES CHAVEZ |
| HVAC-Rough | 7/23/2024 | Approved | JAMES CHAVEZ |
| Verify Sprinkler Sign Off | 7/23/2024 | Approved | JAMES CHAVEZ |
| Drywall Nailing | 7/24/2024 | No Access for Inspection | BEN MOLSTAD |
| Sewer | 7/25/2024 | Approved | BEN MOLSTAD |
| Underground Mechanical | 7/25/2024 | Approved | BEN MOLSTAD |
| Insulation | 7/26/2024 | Approved | BEN MOLSTAD |
| Interior/Exterior Lathing | 7/26/2024 | Not Ready for Inspection | BEN MOLSTAD |
| Drywall Nailing | 8/1/2024 | Approved | JOSEPH MCGARRY |
| Interior/Exterior Lathing | 8/1/2024 | Approved | JOSEPH MCGARRY |
| Shower Pan | 8/1/2024 | Approved | JOSEPH MCGARRY |
| ELECTRICAL-Final | 9/26/2024 | Corrections Issued | BARRY HACHE |
| Gas Test | 9/26/2024 | Approved | BARRY HACHE |
| ELECTRICAL-Final | 3/24/2025 | Corrections Issued | ANTHONY EGSON |
| Final | 3/24/2025 | Corrections Issued | ANTHONY EGSON |
| Green Building Final | 3/24/2025 | Not Ready for Inspection | ANTHONY EGSON |
| HVAC-Final | 3/24/2025 | Corrections Issued | ANTHONY EGSON |
| MERV13>=Final | 3/24/2025 | Approved | ANTHONY EGSON |
| PLUMBING-Final | 3/24/2025 | Corrections Issued | ANTHONY EGSON |
| SGSOV-Seismic Gas S/O Valve | 3/24/2025 | SGSOV Not Ready | ANTHONY EGSON |
| Service/Power Release | 3/24/2025 | Not Ready for Inspection | ANTHONY EGSON |
| Smoke Detectors | 3/24/2025 | Approved | ANTHONY EGSON |
| Final | 7/16/2025 | Corrections Issued | JOHN KLARIN |
| Green Building Final | 7/16/2025 | Corrections Issued | JOHN KLARIN |
| SGSOV-Seismic Gas S/O Valve | 7/16/2025 | SGSOV Approved | JOHN KLARIN |
| Service/Power Release | 7/16/2025 | Not Ready for Inspection | JOHN KLARIN |
| ELECTRICAL-Final | 3/4/2026 | Approved | ARTHUR NEGRETE |
| Final | 3/4/2026 | OK to Issue CofO | ARTHUR NEGRETE |
| Green Building Final | 3/4/2026 | Approved | ARTHUR NEGRETE |
| HVAC-Final | 3/4/2026 | Approved | ARTHUR NEGRETE |
| PLUMBING-Final | 3/4/2026 | Approved | ARTHUR NEGRETE |
| Service/Power Release | 3/4/2026 | Approved | ARTHUR NEGRETE |
| Service/Power Release | 4/6/2026 | Approved | ARTHUR NEGRETE |