232 1/2 N AVENUE 58 90042

Certificate Information: 232 1/2 N AVENUE 58 90042

Application / Permit
22010-10000-02590
Plan Check / Job No.
B22LA09593
Group
Building
Type
Bldg-New
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Accessory Dwelling Unit
Work Description
NEW DETACHED 1-STORY ADU PER CA GOVT CODE65852.2(e)(1)(D) AND APPLICABLE PART OF LAMC 12.22 A.33(c)-(d),(g)
Permit Issued
Issued on 5/24/2023
Issuing Office
Metro
Current Status
CofO Issued on 6/27/2024
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 5/19/2022 APPLICANT
Assigned to Plan Check Engineer 6/2/2022 MAHNAZ NOURHASHEMI
Corrections Issued 6/8/2022 MAHNAZ NOURHASHEMI
Quality Review Completed 6/9/2022 SAI KHUM
Building Plans Picked Up 6/15/2022 APPLICANT
Applicant returned to address corrections 4/28/2023 MAHNAZ NOURHASHEMI
Plan Check Approved 5/24/2023 MAHNAZ NOURHASHEMI
Issued 5/24/2023 APPLICANT
CofO in Progress 6/20/2024 ALIZAH MAYAGOITIA
Permit Finaled 6/27/2024 DEROLD HAUFF
CofO Issued 6/27/2024 DEROLD HAUFF
Permit Finaled 6/27/2024 DEROLD HAUFF

Permit Application Clearance Information

Address approval Cleared 6/27/2022 TREVOR QUAN
Eng Process Fee Ord 176,300 Cleared 7/5/2022 TREVOR QUAN
Sewer availability Cleared 7/5/2022 TREVOR QUAN
Grading Pre-Inspection Cleared 7/13/2022 KIRK LINKLATER
Specific Plan Cleared 7/20/2022 PETE EYRE
Hydrant and Access approval Cleared 8/5/2022 RUEL COLE
HPOZ Cleared 2/16/2023 LYDIA CHAPMAN
Specific Plan Cleared 3/1/2023 PABLO ESTRADA
ZI Cleared 3/1/2023 PABLO ESTRADA
Low Impact Development Cleared 3/20/2023 ERNEST TSE
Highway dedication Cleared 4/6/2023 TREVOR QUAN
Roof/Waste drainage to street Cleared 4/11/2023 TREVOR QUAN
GPI Written Notices Cleared 5/16/2023 SAI KHUM

Contact Information

Contractor Owner-Builder       ,
Engineer Basma,, Ali J; Lic. No.: C53080 21757 DEVONSHIRE ST.   SUITE 3    CANOGA PARK, CA 91311

Inspector Information

No Data Available.

Pending Inspections

No Data Available.

Inspection Request History

Underground Mechanical 8/29/2023 Partial Approval CRAIG VAUGHAN
Excavation/Setback/Form/Re-Bar 9/8/2023 Approved CRAIG VAUGHAN
Footing/Foundation/Slab 9/8/2023 Approved CRAIG VAUGHAN
Floor/Roof Diaphrgm/Shear Wall 10/3/2023 Approved ROY SPAULDING
BUILDING-Rough-Frame 10/13/2023 Corrections Issued ROY SPAULDING
ELECTRICAL-Rough 10/13/2023 Approved ROY SPAULDING
Green Building Rough 10/13/2023 Not Ready for Inspection ROY SPAULDING
PLUMBING-Rough 10/13/2023 Partial Approval ROY SPAULDING
Verify Sprinkler Sign Off 10/13/2023 Approved ROY SPAULDING
BUILDING-Rough-Frame 11/16/2023 Approved ROY SPAULDING
Green Building Rough 11/16/2023 Approved ROY SPAULDING
HVAC-Rough 11/16/2023 Approved ROY SPAULDING
PLUMBING-Rough 11/16/2023 Approved ROY SPAULDING
Insulation 11/28/2023 Approved ROY SPAULDING
Interior/Exterior Lathing 11/28/2023 Approved ROY SPAULDING
Drywall Nailing 12/1/2023 Approved ROY SPAULDING
Shower Pan 12/1/2023 Approved ROY SPAULDING
Underground Mechanical 12/1/2023 Approved ROY SPAULDING
Interior/Exterior Lathing 12/4/2023 Approved AMY COLIN
Final 4/10/2024 Corrections Issued ALIZAH MAYAGOITIA
Green Building Final 4/10/2024 Not Ready for Inspection ALIZAH MAYAGOITIA
SGSOV-Seismic Gas S/O Valve 4/10/2024 SGSOV Not Ready ALIZAH MAYAGOITIA
Service/Power Release 4/10/2024 Not Ready for Inspection ALIZAH MAYAGOITIA
Smoke Detectors 4/10/2024 Approved ALIZAH MAYAGOITIA
Final 4/23/2024 Not Ready for Inspection ALIZAH MAYAGOITIA
Green Building Final 4/23/2024 Not Ready for Inspection ALIZAH MAYAGOITIA
SGSOV-Seismic Gas S/O Valve 4/23/2024 SGSOV Not Ready ALIZAH MAYAGOITIA
Service/Power Release 4/23/2024 Not Ready for Inspection ALIZAH MAYAGOITIA
Final 5/3/2024 Corrections Issued ALIZAH MAYAGOITIA
Green Building Final 5/3/2024 Approved ALIZAH MAYAGOITIA
SGSOV-Seismic Gas S/O Valve 5/3/2024 SGSOV Approved ALIZAH MAYAGOITIA
Service/Power Release 5/3/2024 Approved ALIZAH MAYAGOITIA
Final 6/18/2024 OK to Issue CofO ALIZAH MAYAGOITIA