233 S ROCKINGHAM AVE 90049
Certificate Information: 233 S ROCKINGHAM AVE 90049
- Application / Permit
- 22010-10000-02578
- Plan Check / Job No.
- B22LA09528
- Group
- Building
- Type
- Bldg-New
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (23) Recreation Room
- Work Description
- NEW REC. ROOM, STORAGE, POOL EQUIMENT ROOM WITH POOL ABOVE. Supplemental per permit#21030-10000-07383. Revisions for this permit to include changes to grading quantities to accommodate newly proposed pool structure.
- Permit Issued
- Issued on 12/15/2022
- Issuing Office
- Current Status
- CofO in Progress on 4/23/2026
- Certificate of Occupancy
- Pending More Information
Permit Application Status History
| Submitted | 5/19/2022 | APPLICANT |
| Assigned to Plan Check Engineer | 6/17/2022 | JOE VO |
| Corrections Issued | 6/21/2022 | JOE VO |
| Quality Review Completed | 6/23/2022 | GARO TELMI |
| Plan Check Approved | 12/8/2022 | JOE VO |
| Issued | 12/15/2022 | APPLICANT |
| CofO in Progress | 4/23/2026 | HERBERT GIRON |
| CofO in Progress | 4/23/2026 | HERBERT GIRON |
| CofO in Progress | 4/23/2026 | HERBERT GIRON |
Permit Application Clearance Information
| Hydrant and Access approval | Cleared | 9/1/2022 | LAVEON RIDER |
| Eng Process Fee Ord 176,300 | Cleared | 9/8/2022 | CATHERINE ADROVER |
| Sewer availability | Cleared | 9/8/2022 | CATHERINE ADROVER |
| Specific Plan | Cleared | 9/27/2022 | FREDDY GARCIA |
| Low Impact Development | Cleared | 11/4/2022 | ANDRES COVARRUBIAS |
| Roof/Waste drainage to street | Cleared | 11/9/2022 | AHMED AMARRAGY |
| Miscellaneous | Cleared | 12/8/2022 | JOE VO |
Contact Information
| Contractor | Owner-Builder | , |
| Engineer | Daugherty,, Daniel Thomas; Lic. No.: C76588 | 31129 VIA COLINAS STE 707 WESTLAKE VILLAGE, CA 91362 |
| Engineer | Garcia,, Lionel J; Lic. No.: C58475 | 24702 NARBONNE AVE LOMITA, CA 90717 |
| Engineer | Garcia,, Lionel J; Lic. No.: S4653 | 24702 NARBONNE AVE LOMITA, CA 90717 |
| Geologist | Daugherty,, Daniel Thomas; Lic. No.: EG2569 | 31129 VIA COLINAS SUITE 707 WESTLAKE VILLAGE, CA 91362 |
Inspector Information
| HERBERT GIRON, (310) 914-3891 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Deputy Grading | 6/23/2023 | No Access for Inspection | KENNETH NAGLE |
| Excavation/Setback/Form/Re-Bar | 8/7/2024 | Approved | ARAM AVEDISIAN |
| Footing/Foundation/Slab | 8/7/2024 | Approved | ARAM AVEDISIAN |
| PLUMBING-Rough | 8/26/2024 | Partial Approval | ARAM AVEDISIAN |
| Deputy Reinf. Concrete | 9/13/2024 | Conditional Approval | JESUS RODRIGUEZ |
| Excavation/Setback/Form/Re-Bar | 9/13/2024 | Approved | JESUS RODRIGUEZ |
| Deputy Reinf. Concrete | 9/18/2024 | Conditional Approval | JESUS RODRIGUEZ |
| Floor/Roof Diaphrgm/Shear Wall | 10/9/2024 | Corrections Issued | JESUS RODRIGUEZ |
| Green Building Rough | 10/9/2024 | Not Ready for Inspection | JESUS RODRIGUEZ |
| Verify Sprinkler Sign Off | 10/9/2024 | Not Ready for Inspection | JESUS RODRIGUEZ |
| Structural Steel Frame | 10/17/2024 | Approved | JESUS RODRIGUEZ |
| Excavation/Setback/Form/Re-Bar | 11/1/2024 | Approved | JESUS RODRIGUEZ |
| Deputy Drilled-In Anchors | 11/14/2024 | Conditional Approval | JESUS RODRIGUEZ |
| Deputy Drilled-In Anchors | 11/15/2024 | Conditional Approval | JESUS RODRIGUEZ |
| Deputy Reinf. Concrete | 11/15/2024 | Conditional Approval | JESUS RODRIGUEZ |
| Excavation/Setback/Form/Re-Bar | 11/18/2024 | Approved | JESUS RODRIGUEZ |
| PLUMBING-Rough | 12/19/2024 | Approved | JESUS RODRIGUEZ |
| HVAC-Rough | 4/14/2025 | Not Ready for Inspection | HERBERT GIRON |
| HVAC-Rough | 5/9/2025 | Corrections Issued | TEMISTOCLES CAAL |
| ELECTRICAL-Rough | 5/15/2025 | Corrections Issued | HERBERT GIRON |
| Pre-Inspection | 5/20/2025 | Partial Inspection | HERBERT GIRON |
| Pre-Inspection | 6/10/2025 | Not Ready for Inspection | MEL KHACHATOURIAN |
| HVAC-Final | 6/25/2025 | Partial Inspection | HERBERT GIRON |
| Pre-Inspection | 7/8/2025 | Corrections Issued | HERBERT GIRON |
| Pre-Inspection | 7/15/2025 | Partial Inspection | HERBERT GIRON |
| ELECTRICAL-Rough | 7/18/2025 | Corrections Issued | HERBERT GIRON |
| HVAC-Rough | 7/18/2025 | Approved | HERBERT GIRON |
| Special/Order Compliance | 7/18/2025 | Corrections Issued | HERBERT GIRON |
| ELECTRICAL-Rough | 8/1/2025 | Approved | HERBERT GIRON |
| Special/Order Compliance | 8/1/2025 | Corrections Issued | HERBERT GIRON |
| Pre-Inspection | 8/6/2025 | Partial Inspection | HERBERT GIRON |
| Interior/Exterior Lathing | 8/28/2025 | Partial Approval | HERBERT GIRON |
| Shower Pan | 9/2/2025 | Approved | MICHAEL ALLEN |
| Shower Pan | 9/8/2025 | Approved | HERBERT GIRON |
| BUILDING-Rough-Frame | 9/9/2025 | Corrections Issued | HERBERT GIRON |
| Green Building Rough | 9/9/2025 | Approved | HERBERT GIRON |
| Verify Sprinkler Sign Off | 9/9/2025 | Approved | HERBERT GIRON |
| Interior/Exterior Lathing | 9/10/2025 | Partial Approval | HERBERT GIRON |
| Structural Steel Frame | 9/10/2025 | Not Ready for Inspection | HERBERT GIRON |
| BUILDING-Rough-Frame | 9/12/2025 | Conditional Approval | HERBERT GIRON |
| Insulation | 9/12/2025 | Corrections Issued | HERBERT GIRON |
| BUILDING-Rough-Frame | 9/16/2025 | Approved | HERBERT GIRON |
| Interior/Exterior Lathing | 9/17/2025 | Partial Approval | HERBERT GIRON |
| Drywall Nailing | 9/18/2025 | Partial Approval | HERBERT GIRON |
| Insulation | 9/18/2025 | Not Ready for Inspection | HERBERT GIRON |
| Drywall Nailing | 9/19/2025 | Not Ready for Inspection | MICHAEL ALLEN |
| Insulation | 9/22/2025 | Approved | HERBERT GIRON |
| Drywall Nailing | 9/23/2025 | Approved | HERBERT GIRON |
| Gas Test | 9/26/2025 | Not Ready for Inspection | HERBERT GIRON |
| Gas Test | 10/1/2025 | Not Ready for Inspection | HERBERT GIRON |
| Gas Test | 10/6/2025 | Approved | HERBERT GIRON |
| Enclosure/Fence | 1/6/2026 | Not Ready for Inspection | HERBERT GIRON |
| Pre-Inspection | 1/6/2026 | Partial Inspection | HERBERT GIRON |
| HVAC-Final | 2/17/2026 | Corrections Issued | HERBERT GIRON |
| HVAC-Final | 2/20/2026 | Approved | HERBERT GIRON |
| Pre-Inspection | 2/26/2026 | Partial Inspection | HERBERT GIRON |
| PLUMBING-Final | 3/5/2026 | Partial Approval | HERBERT GIRON |
| ELECTRICAL-Final | 3/9/2026 | Partial Inspection | HERBERT GIRON |
| ELECTRICAL-Final | 3/16/2026 | Approved | HERBERT GIRON |
| Smoke Detectors | 3/16/2026 | Approved | HERBERT GIRON |
| PLUMBING-Final | 3/25/2026 | Not Ready for Inspection | HERBERT GIRON |
| PLUMBING-Final | 4/9/2026 | Approved | HERBERT GIRON |
| Final | 4/21/2026 | OK to Issue CofO | HERBERT GIRON |
| Green Building Final | 4/21/2026 | Approved | HERBERT GIRON |
| SGSOV-Seismic Gas S/O Valve | 4/21/2026 | SGSOV Approved | HERBERT GIRON |