2835 S REDONDO BLVD 90016

Certificate Information: 2835 S REDONDO BLVD 90016

Application / Permit
22010-10000-02546
Plan Check / Job No.
B22LA09432
Group
Building
Type
Bldg-Addition
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Dwelling - Single Family
Work Description
(E) ONE STORY SFD REMODEL AND ADDITION TO CONVERT INTO THREE STORY SFD AT FRONT OF THE LOT. AB 2097 ZERO PARKING REQ'D
Permit Issued
Issued on 8/29/2024
Issuing Office
Current Status
CofO Issued on 4/26/2026
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 5/25/2022 APPLICANT
Assigned to Plan Check Engineer 6/24/2022 SERGIO GUTIERREZ
Corrections Issued 6/27/2022 SERGIO GUTIERREZ
Quality Review Completed 6/28/2022 RODOLFO ARIAS
Applicant returned to address corrections 1/26/2023 SERGIO GUTIERREZ
Applicant returned to address corrections 8/1/2023 SERGIO GUTIERREZ
Applicant returned to address corrections 10/19/2023 SERGIO GUTIERREZ
Plan Check Approved 11/3/2023 SERGIO GUTIERREZ
Issued 8/29/2024 APPLICANT
CofO in Progress 4/22/2026 WILLIAM SIERRA
Permit Finaled 4/26/2026 DEROLD HAUFF
CofO Issued 4/26/2026 DEROLD HAUFF
Permit Finaled 4/26/2026 DEROLD HAUFF

Permit Application Clearance Information

Address approval Cleared 7/1/2022 JEANETTE VONG
Eng Process Fee Ord 176,300 Cleared 7/1/2022 JEANETTE VONG
Highway dedication Cleared 7/20/2022 CELINA MORENO
Permit Cleared 8/18/2022 JEANETTE VONG
Certificate of Compliance Cleared 8/25/2022 RUBEN VASQUEZ
Low Impact Development Cleared 2/17/2023 LUIS LUVANO
Hydrant and Access approval Cleared 3/6/2023 MATTHEW CRAIG
Roof/Waste drainage to street Cleared 3/10/2023 CELINA MORENO
Frnt yard landscape/Water mgmt Cleared 3/14/2023 SPENCER WEJROWSKI
Sewer availability Cleared 8/3/2023 CELINA MORENO
Miscellaneous Cleared 11/3/2023 SERGIO GUTIERREZ

Contact Information

Architect Feld,, Dovid Yitzchak; Lic. No.: C37588 921 S HOLT AVENUE      LOS ANGELES, CA 90035
Architect Feld,, Dovid Yitzchak; Lic. No.: NA37588       ,
Contractor Builders & Son'S Inc; Lic. No.: 961171-B       ,

Inspector Information

DAVID WILLIAMS, (213) 202-3126 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Footing/Foundation/Slab 10/9/2024 Approved ARTHUR NEGRETE
Deputy Steel/Welding 10/16/2024 Conditional Approval ANTHONY RAMOS
Wood Frame 10/30/2024 Approved ARTHUR NEGRETE
BUILDING-Rough-Frame 11/1/2024 Partial Approval ARTHUR NEGRETE
Floor/Roof Diaphrgm/Shear Wall 11/1/2024 Approved ARTHUR NEGRETE
Floor/Roof Diaphrgm/Shear Wall 11/19/2024 Approved ARTHUR NEGRETE
Floor/Roof Diaphrgm/Shear Wall 12/10/2024 Partial Approval JEFFREY MEAD
Floor/Roof Diaphrgm/Shear Wall 1/13/2025 Approved ARTHUR NEGRETE
ELECTRICAL-Rough 5/14/2025 Approved ARTHUR NEGRETE
HVAC-Rough 5/14/2025 Approved ARTHUR NEGRETE
PLUMBING-Rough 5/14/2025 Approved ARTHUR NEGRETE
BUILDING-Rough-Frame 5/16/2025 Approved ARTHUR NEGRETE
Green Building Rough 5/16/2025 Approved ARTHUR NEGRETE
Wood Frame 5/16/2025 Approved ARTHUR NEGRETE
Interior/Exterior Lathing 6/11/2025 Not Ready for Inspection ALEX COLIN
Shower Pan 6/11/2025 Approved ALEX COLIN
Insulation 6/13/2025 Approved ARTHUR NEGRETE
Interior/Exterior Lathing 6/13/2025 Approved ARTHUR NEGRETE
Insulation 6/16/2025 Approved ARTHUR NEGRETE
Interior/Exterior Lathing 6/23/2025 Approved ALEX COLIN
Drywall Nailing 6/25/2025 Approved ARTHUR NEGRETE
Gas Test 11/18/2025 Approved ARTHUR NEGRETE
ELECTRICAL-Final 3/4/2026 Approved BRENDAN MORELLI
Final 3/4/2026 Corrections Issued BRENDAN MORELLI
Gas Test 3/4/2026 Approved BRENDAN MORELLI
Green Building Final 3/4/2026 Not Ready for Inspection BRENDAN MORELLI
HVAC-Final 3/4/2026 Approved BRENDAN MORELLI
PLUMBING-Final 3/4/2026 Approved BRENDAN MORELLI
SGSOV-Seismic Gas S/O Valve 3/4/2026 SGSOV Not Ready BRENDAN MORELLI
Smoke Detectors 3/4/2026 Corrections Issued BRENDAN MORELLI
Final 3/19/2026 Corrections Issued WILLIAM SIERRA
Green Building Final 3/19/2026 Approved WILLIAM SIERRA
SGSOV-Seismic Gas S/O Valve 3/19/2026 SGSOV Not Ready WILLIAM SIERRA
Smoke Detectors 3/19/2026 Approved WILLIAM SIERRA
Final 4/15/2026 Corrections Issued BRENDAN MORELLI
SGSOV-Seismic Gas S/O Valve 4/15/2026 SGSOV Approved BRENDAN MORELLI
Final 4/21/2026 OK to Issue CofO WILLIAM SIERRA