1079 W 30TH ST 90007

Certificate Information: 1079 W 30TH ST 90007

Application / Permit
22010-10000-02543
Plan Check / Job No.
B22LA09429
Group
Building
Type
Bldg-New
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Accessory Dwelling Unit
Work Description
EPLAN NEW 33'-9" X 40'-11" 2-STORY ACCESSORY DWELLING UNIT PER LAMC 12.22 A.33(c) AND (d) W/ 2-CAR GARAGE. ALL WORK PER ENGINEERING
Permit Issued
Issued on 10/26/2023
Issuing Office
Current Status
CofO Issued on 12/29/2024
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 5/18/2022 APPLICANT
Assigned to Plan Check Engineer 6/23/2022 RAPHAEL ROSAS
Corrections Issued 6/29/2022 RAPHAEL ROSAS
Quality Review Completed 7/1/2022 STEVEN KIM
Applicant returned to address corrections 10/4/2022 RAPHAEL ROSAS
Applicant returned to address corrections 11/1/2022 RAPHAEL ROSAS
Applicant returned to address corrections 8/9/2023 RAPHAEL ROSAS
Plan Check Approved 10/25/2023 RAPHAEL ROSAS
Issued 10/26/2023 APPLICANT
CofO in Progress 12/5/2024 WILLIAM SIERRA
Permit Finaled 12/29/2024 DEROLD HAUFF
CofO Issued 12/29/2024 DEROLD HAUFF
Permit Finaled 12/29/2024 DEROLD HAUFF

Permit Application Clearance Information

Address approval Cleared 6/30/2022 CHRISTOPHER ROCHA
Eng Process Fee Ord 176,300 Cleared 7/5/2022 CHRISTOPHER ROCHA
Sewer availability Cleared 7/5/2022 CHRISTOPHER ROCHA
Miscellaneous Cleared 7/21/2022 KATIE DEBIASE
Miscellaneous Cleared 7/21/2022 KATIE DEBIASE
Specific Plan Cleared 7/21/2022 KATIE DEBIASE
ZI Cleared 7/21/2022 KATIE DEBIASE
ZA Case Cleared 7/22/2022 JAZMIN ROQUE
ZI Cleared 7/22/2022 JAZMIN ROQUE
Low Impact Development Cleared 10/5/2022 CHRIS VONG
Roof/Waste drainage to street Cleared 10/8/2022 CHRISTOPHER ROCHA

Contact Information

Contractor Owner-Builder       ,
Engineer Polon,, Gordon Leonard; Lic. No.: C28564 709 19TH STREET      SANTA MONICA, CA 90402

Inspector Information

WILLIAM SIERRA, (213) 202-3122 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

METHANE-Barrier 12/18/2023 Not Ready for Inspection KATHRYN BUTTERWORTH
Rough-Elec/Plmb/HVAC 12/18/2023 Partial Approval KATHRYN BUTTERWORTH
Sewer 12/18/2023 Approved KATHRYN BUTTERWORTH
METHANE-Barrier 1/4/2024 Corrections Issued KATHRYN BUTTERWORTH
Excavation/Setback/Form/Re-Bar 1/10/2024 Partial Approval KATHRYN BUTTERWORTH
Footing/Foundation/Slab 1/10/2024 Not Ready for Inspection KATHRYN BUTTERWORTH
METHANE-Barrier 1/10/2024 Not Ready for Inspection KATHRYN BUTTERWORTH
METHANE-Subgrade 1/10/2024 Approved KATHRYN BUTTERWORTH
Excavation/Setback/Form/Re-Bar 1/11/2024 Approved KATHRYN BUTTERWORTH
Footing/Foundation/Slab 1/11/2024 Approved KATHRYN BUTTERWORTH
METHANE-Barrier 1/11/2024 Approved KATHRYN BUTTERWORTH
Floor/Roof Diaphrgm/Shear Wall 1/18/2024 Partial Approval SCOTT FINNILA
Deputy Wood Construction 1/29/2024 Conditional Approval JOSH MEISTER
ELECTRICAL-Rough 2/21/2024 Not Ready for Inspection ARTHUR NEGRETE
Floor/Roof Diaphrgm/Shear Wall 2/21/2024 Approved ARTHUR NEGRETE
HVAC-Rough 2/21/2024 Approved ARTHUR NEGRETE
PLUMBING-Rough 2/21/2024 Not Ready for Inspection ARTHUR NEGRETE
Wood Frame 2/22/2024 Approved ARTHUR NEGRETE
ELECTRICAL-Rough 2/23/2024 Approved ARTHUR NEGRETE
HVAC-Rough 2/23/2024 Approved ARTHUR NEGRETE
PLUMBING-Rough 2/23/2024 Approved ARTHUR NEGRETE
Insulation 3/1/2024 Approved ARTHUR NEGRETE
Drywall Nailing 3/14/2024 Approved ARTHUR NEGRETE
Green Building Rough 3/14/2024 Approved ARTHUR NEGRETE
Interior/Exterior Lathing 3/14/2024 Approved ARTHUR NEGRETE
Excavation/Setback/Form/Re-Bar 4/4/2024 Approved ARTHUR NEGRETE
METHANE-Rough 4/4/2024 Approved ARTHUR NEGRETE
BUILDING-Rough-Frame 7/19/2024 Approved JOSEPH MCGARRY
Final 7/19/2024 Corrections Issued JOSEPH MCGARRY
Green Building Final 7/19/2024 Approved JOSEPH MCGARRY
SGSOV-Seismic Gas S/O Valve 7/19/2024 SGSOV Approved JOSEPH MCGARRY
Service/Power Release 7/19/2024 Not Required JOSEPH MCGARRY
Smoke Detectors 7/19/2024 Approved JOSEPH MCGARRY
Verify Sprinkler Sign Off 7/19/2024 Approved JOSEPH MCGARRY
Deputy Methane Barrier 7/22/2024 Partial Approval JOSEPH MCGARRY
Special/Order Compliance 7/22/2024 Corrections Issued JOSEPH MCGARRY
Final 8/5/2024 Corrections Issued WILLIAM SIERRA
Final 8/9/2024 Conditional Approval WILLIAM SIERRA
Gas Test 8/9/2024 Approved WILLIAM SIERRA
SGSOV-Seismic Gas S/O Valve 8/9/2024 SGSOV Approved WILLIAM SIERRA
Final 10/17/2024 Conditional Approval JOHN QUINTANILLA
Final 10/24/2024 Corrections Issued WILLIAM SIERRA
Final 12/4/2024 OK to Issue CofO WILLIAM SIERRA