154 S MEDIO DR 90049
Certificate Information: 154 S MEDIO DR 90049
- Application / Permit
- 22010-10000-02501
- Plan Check / Job No.
- B22LA09232
- Group
- Building
- Type
- Bldg-New
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Dwelling - Single Family
- Work Description
- eplan: New 2-story SFD w/attached garage
- Permit Issued
- Issued on 9/19/2023
- Issuing Office
- Current Status
- CofO Issued on 10/7/2025
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 5/23/2022 | APPLICANT |
| Assigned to Plan Check Engineer | 6/24/2022 | ADRIANA LOPEZ |
| Corrections Issued | 6/26/2022 | ADRIANA LOPEZ |
| Quality Review Completed | 7/5/2022 | GARO TELMI |
| Applicant returned to address corrections | 12/6/2022 | ADRIANA LOPEZ |
| Applicant returned to address corrections | 6/16/2023 | ADRIANA LOPEZ |
| Plan Check Approved | 6/26/2023 | ADRIANA LOPEZ |
| Plan Check Approved | 9/8/2023 | FARUK SEZER |
| Issued | 9/19/2023 | APPLICANT |
| CofO in Progress | 9/18/2025 | HERBERT GIRON |
| Permit Finaled | 10/7/2025 | RICHARD STEINBACH |
| CofO Issued | 10/7/2025 | RICHARD STEINBACH |
| Permit Finaled | 10/7/2025 | RICHARD STEINBACH |
Permit Application Clearance Information
| Miscellaneous | Cleared | 7/18/2022 | MAYELA VILLA |
| Permit | Cleared | 7/19/2022 | CATHERINE ADROVER |
| Eng Process Fee Ord 176,300 | Cleared | 7/20/2022 | CATHERINE ADROVER |
| Sewer availability | Cleared | 7/20/2022 | CATHERINE ADROVER |
| Work Adjacent to Public Way | Cleared | 7/26/2022 | SAUL GARCIA |
| Specific Plan | Cleared | 8/9/2022 | VALERIA CEJA |
| Hydrant and Access approval | Cleared | 8/18/2022 | LAVEON RIDER |
| Trees in Parkway | Cleared | 8/25/2022 | ADALBERTO VERA |
| Low Impact Development | Cleared | 5/25/2023 | MELINEH AGHAKHABIAN |
| Roof/Waste drainage to street | Cleared | 5/25/2023 | DINAH GARIN |
| GPI Written Notices | Cleared | 6/26/2023 | ADRIANA LOPEZ |
| Grading Pre-Inspection | Cleared | 6/26/2023 | ADRIANA LOPEZ |
Contact Information
| Architect | Leach,, Douglas John; Lic. No.: C15529 | 119 W TORRANCE BLVD #24 REDONDO BEACH, CA 90277 |
| Contractor | Drexel Construction Management Llc; Lic. No.: 1014160-B | , |
| Engineer | Parsa,, Abdollah; Lic. No.: C38604 | 118 S CATALINA AVE STE E REDONDO BEACH, CA 90277 |
| Engineer | Perez,, Christian Jose; Lic. No.: C80680 | 5061 ROCKVALLEY RD RANCHO PALOS VERDES, CA 90275 |
| Engineer | Tucker,, Keith D; Lic. No.: GE841 | PO BOX 8133 HUNTINGTON BEACH, CA 92615 |
Inspector Information
| HERBERT GIRON, (310) 914-3891 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| PLUMBING-Rough | 12/15/2023 | Partial Approval | ARAM AVEDISIAN |
| Sewer | 12/15/2023 | Approved | ARAM AVEDISIAN |
| Footing/Foundation/Slab | 1/12/2024 | Corrections Issued | KEVIN SARGSYAN |
| Deputy Reinf. Concrete | 1/16/2024 | Partial Approval | CHRISTOPHER WILSON |
| Excavation/Setback/Form/Re-Bar | 1/16/2024 | Partial Approval | CHRISTOPHER WILSON |
| Footing/Foundation/Slab | 2/13/2024 | Approved | CARLOS MATAMOROS |
| Floor/Roof Diaphrgm/Shear Wall | 3/15/2024 | Approved | ARAM AVEDISIAN |
| Floor/Roof Diaphrgm/Shear Wall | 3/18/2024 | Corrections Issued | EVAN COOPER |
| Deputy Wood Construction | 6/13/2024 | Conditional Approval | MICHAEL PELHAM |
| Floor/Roof Diaphrgm/Shear Wall | 6/18/2024 | Corrections Issued | ARAM AVEDISIAN |
| Special/Order Compliance | 6/18/2024 | Partial Inspection | ARAM AVEDISIAN |
| Floor/Roof Diaphrgm/Shear Wall | 6/24/2024 | Partial Approval | ARAM AVEDISIAN |
| HVAC-Rough | 6/24/2024 | Approved | ARAM AVEDISIAN |
| ELECTRICAL-Rough | 7/3/2024 | Corrections Issued | ARAM AVEDISIAN |
| PLUMBING-Rough | 7/3/2024 | Approved | ARAM AVEDISIAN |
| Verify Sprinkler Sign Off | 7/3/2024 | Approved | ARAM AVEDISIAN |
| ELECTRICAL-Rough | 7/12/2024 | Approved | ARAM AVEDISIAN |
| Floor/Roof Diaphrgm/Shear Wall | 7/19/2024 | Approved | ARAM AVEDISIAN |
| Shower Pan | 8/2/2024 | Partial Approval | ARAM AVEDISIAN |
| Interior/Exterior Lathing | 8/6/2024 | Partial Approval | TEMISTOCLES CAAL |
| Shower Pan | 8/6/2024 | Approved | TEMISTOCLES CAAL |
| Interior/Exterior Lathing | 8/8/2024 | Approved | CARLOS MATAMOROS |
| BUILDING-Rough-Frame | 8/19/2024 | Approved | ARAM AVEDISIAN |
| Green Building Rough | 8/19/2024 | Approved | ARAM AVEDISIAN |
| Interior/Exterior Lathing | 8/19/2024 | Partial Approval | ARAM AVEDISIAN |
| Insulation | 8/27/2024 | Approved | JESUS RODRIGUEZ |
| Drywall Nailing | 9/11/2024 | Approved | JESUS RODRIGUEZ |
| Special/Order Compliance | 9/11/2024 | Corrections Issued | JESUS RODRIGUEZ |
| Interior/Exterior Lathing | 10/22/2024 | Approved | JESUS RODRIGUEZ |
| ELECTRICAL-Final | 6/18/2025 | Corrections Issued | HERBERT GIRON |
| ELECTRICAL-Final | 7/2/2025 | Not Ready for Inspection | HERBERT GIRON |
| HVAC-Final | 7/2/2025 | Corrections Issued | HERBERT GIRON |
| PLUMBING-Final | 7/2/2025 | Corrections Issued | HERBERT GIRON |
| ELECTRICAL-Final | 7/8/2025 | Corrections Issued | HERBERT GIRON |
| HVAC-Final | 7/8/2025 | Not Ready for Inspection | HERBERT GIRON |
| PLUMBING-Final | 7/8/2025 | Corrections Issued | HERBERT GIRON |
| ELECTRICAL-Final | 7/14/2025 | Approved | HERBERT GIRON |
| Final | 7/14/2025 | Corrections Issued | HERBERT GIRON |
| Green Building Final | 7/14/2025 | Approved | HERBERT GIRON |
| HVAC-Final | 7/14/2025 | Corrections Issued | HERBERT GIRON |
| PLUMBING-Final | 7/14/2025 | Approved | HERBERT GIRON |
| SGSOV-Seismic Gas S/O Valve | 7/14/2025 | SGSOV Not Ready | HERBERT GIRON |
| Service/Power Release | 7/14/2025 | Not Ready for Inspection | HERBERT GIRON |
| Smoke Detectors | 7/14/2025 | Approved | HERBERT GIRON |
| Final | 8/4/2025 | Not Ready for Inspection | HERBERT GIRON |
| HVAC-Final | 8/4/2025 | Approved | HERBERT GIRON |
| SGSOV-Seismic Gas S/O Valve | 8/4/2025 | SGSOV Approved | HERBERT GIRON |
| Final | 9/16/2025 | Corrections Issued | HERBERT GIRON |
| Final | 9/18/2025 | OK to Issue CofO | HERBERT GIRON |
| Service/Power Release | 9/18/2025 | Approved | HERBERT GIRON |