2647 1/2 E CARLETON AVE 90065
Certificate Information: 2647 1/2 E CARLETON AVE 90065
- Application / Permit
- 22010-10000-02494
- Plan Check / Job No.
- B22LA09212
- Group
- Building
- Type
- Bldg-Addition
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Accessory Dwelling Unit
- Work Description
- CONVERT (E) DET GARAGE & ADD (22'-6"x 21'-0") IRR SHAPE ACCESSORY DWELLING UNIT PER GCS 65852.2 (e) (1) (B) and LAMC 12.22 A.33 (c) (d) and (g).
- Permit Issued
- Issued on 11/2/2023
- Issuing Office
- Current Status
- CofO Issued on 3/6/2025
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 5/18/2022 | APPLICANT |
| Assigned to Plan Check Engineer | 6/23/2022 | SELLA BENYAMIN |
| Corrections Issued | 6/24/2022 | TROY DEGUZMAN |
| Quality Review Completed | 6/29/2022 | OMID HEDAYAT |
| Plan Check Approved | 9/22/2023 | SELLA BENYAMIN |
| Issued | 11/2/2023 | APPLICANT |
| CofO in Progress | 3/4/2025 | ALIZAH MAYAGOITIA |
| Permit Finaled | 3/6/2025 | DEROLD HAUFF |
| CofO Issued | 3/6/2025 | DEROLD HAUFF |
| Permit Finaled | 3/6/2025 | DEROLD HAUFF |
Permit Application Clearance Information
| Address approval | Cleared | 7/12/2022 | WALLIE JONG |
| Grading Pre-Inspection | Cleared | 7/14/2022 | ROBERT HUGHES |
| Construction near power lines | Cleared | 9/6/2022 | RIDWAN HARDY |
| Supp. Use District POD/CDO/TDO | Cleared | 2/23/2023 | NASHYA JENSEN |
| ZI | Cleared | 2/23/2023 | NASHYA JENSEN |
| Eng Process Fee Ord 176,300 | Cleared | 6/9/2023 | CHRISTOPHER ROCHA |
| Sewer availability | Cleared | 6/9/2023 | CHRISTOPHER ROCHA |
| Hydrant and Access approval | Cleared | 6/29/2023 | MATTHEW CRAIG |
| ZI | Cleared | 7/6/2023 | YINGSHI HUANG |
| Low Impact Development | Cleared | 8/4/2023 | ANTHONY VARGAS |
| Roof/Waste drainage to street | Cleared | 8/15/2023 | CHRISTINA BRACO |
Contact Information
| Contractor | Select Design Construction Inc; Lic. No.: 972421-B | , |
| Engineer | Grigoryan,, Souren; Lic. No.: C93320 | 6506 TEESDALE AVE NORTH HOLLYWOOD, CA 91606 |
Inspector Information
| OSVALDO PARAMO, (213) 202-9854 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| PLUMBING-Rough | 11/15/2023 | Corrections Issued | OSVALDO PARAMO |
| Excavation/Setback/Form/Re-Bar | 12/4/2023 | No Access for Inspection | OSVALDO PARAMO |
| Footing/Foundation/Slab | 12/4/2023 | No Access for Inspection | OSVALDO PARAMO |
| Pre-Inspection | 12/6/2023 | Corrections Issued | ALIZAH MAYAGOITIA |
| Excavation/Setback/Form/Re-Bar | 12/19/2023 | Approved | OSVALDO PARAMO |
| Footing/Foundation/Slab | 12/19/2023 | Corrections Issued | OSVALDO PARAMO |
| ELECTRICAL-Rough | 3/8/2024 | Approved | OSVALDO PARAMO |
| Floor/Roof Diaphrgm/Shear Wall | 3/8/2024 | Partial Approval | OSVALDO PARAMO |
| PLUMBING-Rough | 3/8/2024 | Approved | OSVALDO PARAMO |
| Underground Mechanical | 3/8/2024 | Approved | OSVALDO PARAMO |
| Floor/Roof Diaphrgm/Shear Wall | 4/1/2024 | Approved | OSVALDO PARAMO |
| Wood Frame | 4/1/2024 | Corrections Issued | OSVALDO PARAMO |
| BUILDING-Rough-Frame | 4/12/2024 | Approved | OSVALDO PARAMO |
| Green Building Rough | 4/12/2024 | Approved | OSVALDO PARAMO |
| Insulation | 4/12/2024 | Approved | OSVALDO PARAMO |
| Interior/Exterior Lathing | 4/12/2024 | Partial Approval | OSVALDO PARAMO |
| Drywall Nailing | 5/3/2024 | Approved | OSVALDO PARAMO |
| Interior/Exterior Lathing | 5/24/2024 | Corrections Issued | ALIZAH MAYAGOITIA |
| Interior/Exterior Lathing | 5/28/2024 | Approved | LILIANA PORTILLO |
| Shower Pan | 5/28/2024 | Not Ready for Inspection | LILIANA PORTILLO |
| Shower Pan | 5/31/2024 | Approved | OSVALDO PARAMO |
| Final | 8/12/2024 | Not Ready for Inspection | OSVALDO PARAMO |
| Footing/Foundation/Slab | 8/12/2024 | Approved | OSVALDO PARAMO |
| Green Building Final | 8/12/2024 | Not Ready for Inspection | OSVALDO PARAMO |
| SGSOV-Seismic Gas S/O Valve | 8/12/2024 | SGSOV Not Ready | OSVALDO PARAMO |
| Smoke Detectors | 8/12/2024 | Not Ready for Inspection | OSVALDO PARAMO |
| Final | 9/23/2024 | Corrections Issued | OSVALDO PARAMO |
| Green Building Final | 9/23/2024 | Approved | OSVALDO PARAMO |
| SGSOV-Seismic Gas S/O Valve | 9/23/2024 | SGSOV Approved | OSVALDO PARAMO |
| Smoke Detectors | 9/23/2024 | Not Ready for Inspection | OSVALDO PARAMO |
| Final | 10/2/2024 | Corrections Issued | OSVALDO PARAMO |
| Smoke Detectors | 10/2/2024 | Not Ready for Inspection | OSVALDO PARAMO |
| Final | 10/4/2024 | Conditional Approval | OSVALDO PARAMO |
| Smoke Detectors | 10/4/2024 | Approved | OSVALDO PARAMO |
| Final | 3/4/2025 | OK to Issue CofO | ALIZAH MAYAGOITIA |