5123 S 7TH AVE 90043

Certificate Information: 5123 S 7TH AVE 90043

Application / Permit
22010-10000-02493
Plan Check / Job No.
B22LA09211
Group
Building
Type
Bldg-Addition
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Accessory Dwelling Unit
Work Description
ePlan CONVERT EXISTING DETACHED GARAGE (155 SF) WITH ADDITION TO BECOME ADU (1,200 SF max per Ordinance, LAMC 12.22 A.33 (c)-(d))
Permit Issued
Issued on 6/29/2022
Issuing Office
Current Status
CofO Issued on 5/13/2023
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 5/16/2022 APPLICANT
Assigned to Plan Check Engineer 5/18/2022 AUNG SOE
Corrections Issued 5/20/2022 AUNG SOE
Applicant returned to address corrections 6/11/2022 AUNG SOE
Plan Check Approved 6/12/2022 AUNG SOE
Issued 6/29/2022 APPLICANT
CofO in Progress 5/8/2023 ANTHONY EGSON
Permit Finaled 5/13/2023 DEROLD HAUFF
CofO Issued 5/13/2023 DEROLD HAUFF
Permit Finaled 5/13/2023 DEROLD HAUFF

Permit Application Clearance Information

Address approval Cleared 6/1/2022 CELINA MORENO
Roof/Waste drainage to street Cleared 6/1/2022 CELINA MORENO
Eng Process Fee Ord 176,300 Cleared 6/3/2022 CELINA MORENO
Sewer availability Cleared 6/3/2022 CELINA MORENO

Contact Information

Contractor Owner-Builder       ,
Engineer Ramirez, Cid, Jose Carlos; Lic. No.: C91046 5164 N RATON CIR      LONG BEACH, CA 90807
Engineer Ramirez, Cid, Jose Carlos; Lic. No.: NA91046       ,

Inspector Information

LUIS CASTRO, (213) 202-3436 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Footing/Foundation/Slab 7/14/2022 Not Ready for Inspection ANTHONY EGSON
Underground Mechanical 7/14/2022 Approved ANTHONY EGSON
Sewer 7/15/2022 Approved ANTHONY EGSON
Excavation/Setback/Form/Re-Bar 7/19/2022 Approved ANTHONY EGSON
Footing/Foundation/Slab 7/21/2022 Corrections Issued ANTHONY EGSON
Footing/Foundation/Slab 7/25/2022 Approved ANTHONY EGSON
BUILDING-Rough-Frame 9/9/2022 Not Ready for Inspection ANTHONY EGSON
Green Building Rough 9/9/2022 Not Ready for Inspection ANTHONY EGSON
PLUMBING-Rough 9/9/2022 Partial Inspection ANTHONY EGSON
ELECTRICAL-Rough 9/27/2022 Not Ready for Inspection ANTHONY EGSON
Floor/Roof Diaphrgm/Shear Wall 9/27/2022 Corrections Issued ANTHONY EGSON
PLUMBING-Rough 9/27/2022 Corrections Issued ANTHONY EGSON
Floor/Roof Diaphrgm/Shear Wall 10/5/2022 Not Ready for Inspection STUART CHAPMAN
PLUMBING-Rough 10/5/2022 Corrections Issued STUART CHAPMAN
ELECTRICAL-Rough 10/11/2022 Corrections Issued ANTHONY EGSON
Floor/Roof Diaphrgm/Shear Wall 10/11/2022 Corrections Issued ANTHONY EGSON
Floor/Roof Diaphrgm/Shear Wall 10/17/2022 Partial Approval ANTHONY EGSON
ELECTRICAL-Rough 10/24/2022 Corrections Issued ANTHONY EGSON
Insulation 11/4/2022 Approved ANTHONY EGSON
Drywall Nailing 11/10/2022 Approved ANTHONY EGSON
Drywall Nailing 11/16/2022 Not Ready for Inspection ANTHONY EGSON
Shower Pan 12/9/2022 Not Ready for Inspection ALIZAH MAYAGOITIA
Shower Pan 12/15/2022 Approved ANTHONY EGSON
BUILDING-Rough-Frame 4/19/2023 Approved ANTHONY EGSON
ELECTRICAL-Final 4/19/2023 Corrections Issued ANTHONY EGSON
Final 4/19/2023 Corrections Issued ANTHONY EGSON
Green Building Final 4/19/2023 Corrections Issued ANTHONY EGSON
Green Building Rough 4/19/2023 Approved ANTHONY EGSON
HVAC-Final 4/19/2023 Corrections Issued ANTHONY EGSON
PLUMBING-Final 4/19/2023 Corrections Issued ANTHONY EGSON
SGSOV-Seismic Gas S/O Valve 4/19/2023 SGSOV Not Required ANTHONY EGSON
Smoke Detectors 4/19/2023 Approved ANTHONY EGSON
ELECTRICAL-Final 4/25/2023 Approved ANTHONY EGSON
HVAC-Final 4/25/2023 Approved ANTHONY EGSON
PLUMBING-Final 4/25/2023 Approved ANTHONY EGSON
Final 5/8/2023 OK to Issue CofO ANTHONY EGSON
Green Building Final 5/8/2023 Approved ANTHONY EGSON